Professional Documents
Culture Documents
Abstract
Many IT implementations are unsuccessful in that projects are terminated before completion or they
are completed late and exceeds the budget by far. In many instances the users are not satisfied with
the system or they are not effectively using the system to its fullest potential. In very few instances
are any real benefits measured and realised.
Eskom Generation is in the process of implementing SAP R/3 Plant Maintenance (PM) version
3.1H at 10 power stations. The objective of this presentation will be to share the project
management approach being followed and the lessons learnt to ensure successful implementation.
The paper is a case study of a real-world implementation and the authors will present an objective
account of the project with specific focus on the PMBOK knowledge areas (i.e. integration, scope,
time, cost, quality/performance, human resources, communications, procurement, and risk
management).
1 INTRODUCTION
Effective plant maintenance is critical to the Eskom Vision of lowest cost electricity in the world
and the Generation objective of world class technical performance (90:7:3). To achieve this vision
and objective it is essential to have a world class Plant Maintenance (PM) system with embedded
best practices. You also need an empowered workforce utilising the system to its fullest potential to
maintain the Generation plant assets (book value of R24.044bn and annual maintenance cost of
R1.642 for 2000).
The current Plant Maintenance system Permac is at the end of its development life cycle and does
not serve the needs of the power stations. Permac does not have the functionality of “world class”
PM systems and is not integrated with the plant, financial and other systems. A detailed business
case was compiled investigating the cost and associated benefits for different software products and
implementation options for an integrated plant maintenance system. Approval was obtained from
the Generation Executive Committee to install SAP PM at 10 power stations (9 fossil and 1
nuclear).
2 PROJECT OVERVIEW
Paper presented at African Rhythm Project Management Conference 22 – 24 April 2002, Johannesburg, South Africa
Hosted by: Project Management Institute of South Africa (PMISA): www.pmisa.org.za ISBN Number: 0-620-28853-1
• Plant maintenance functionality integrated with the financial and commercial systems (i.e.
SAP);
• Plant maintenance functionality integrated with the plant configuration management system (i.e.
PiGo);
• Plant maintenance functionality using a “best of breed” system (i.e. Maximo); or
• Do nothing, keep the status quo (i.e. Permac and PiGo).
The second part of the project objective was to obtain buy-in from all the relevant stakeholder
forums, to obtain approval form the relevant management bodies, to obtain approval for the capital
expenditure and to negotiate contracts with the recommended software and hardware vendors as
well as the implementation partners.
DD EESSIIGGNN
PH
PH AASSEE
DD EELLIV
IVEERRYY
PH
PH AASSEE
PI
PILO
LO TT::
TTutuk
utukaa
GGRROO UU PP 11
DD uvh
uvhaa,, LeLeththaabbo,
o,
MM aati
timm bbaa
GGRROO UU PP 22
HH eend
ndri
rina
na,, MM aajub
jubaa,,
KKend
endal al
GGRROO UU PP 33
KKrieell
ri ,, MM atl
atl aa
KKOO EEBBEERRGG
Another challenging factor during project plan development is the fact that there are many
organisations involved in the project – each with their own methodologies and thinking. However,
the project plan is not developed in isolation. Input from all organisations is sought throughout the
planning process.
Reports from MS Project are used to guide the project execution and project control. The Theory of
Constraints (TOC) buffer management methodology is used where non-critical paths are protected
by feeding buffers, and the critical path is protected by the project buffer.
The scope statements were supported by the Steering Committee and authorised by the Project
Sponsor.
The resource planning is not done in isolation by the management team. Being a relatively small
project team, it is easy to obtain constant input from the team members regarding their preferences
and career aspirations. This ensures that the team members are motivated and they accept the
overall project plan.
3.4.2 Cost estimating
Cost estimating involved developing an approximation of the costs of the resources needed to
complete the project activities after consideration was given to various costing alternatives. Cost
estimates were compiled from information obtained from the potential software and hardware
vendors and implementation partners.
Execution Release Approval (ERA) for the project was obtained for the final cost baseline from the
Eskom Capital Investment Committee.
Eskom Corporate Audit is closely involved with the project. They review project deliverables,
monitor solution testing (including user tests) and are present during the final conversion of data
into the live system.
The system testing process is used to ensure that the solution fulfils the requirements of all
stakeholders. It includes different tests for each Power Station, namely unit testing, string testing,
system testing, user acceptance testing and dress rehearsal testing. Each of these tests is conducted
by different stakeholders, which include project team members and end users.
Each project phase is concluded with a Phase Closeout Report. This report is a summary of all the
activities and deliverables (with references) that are executed and completed during that phase. The
Steering Committee approves and signs-off this report which formally concludes each project
phase.
Data Training
Software Site User
Purification Solution Material
Factory Readiness Profiles
Confirmation Update
& Support
Environment Conversion
Management Testing Configuration Training
(incl Project Coordination
infrastructure)
Solution
Testing
Production
Architecture &
Infrastructure
Figure 2 illustrates the project team organisation and reporting relationships. The project team
consists of 5 teams, namely the project management team, the systems integration team, the data
preparation team, the solution preparation team and the human performance & site preparation
team.
The Steering Committee plays an overseeing role. They provide overall leadership, guidance and
approval of the project. During monthly Steering Committee meetings, the project management
team gives status feedback, highlights issues and risks and obtains their input and approval as and
when necessary.
During rollout/implementation phases, the project team is split in two, due to the fact that some
team members have to be at the Power Station sites. The one major challenge that the team is faced
with then, is to maintain good communication channels between the central and site based teams.
Figure 3 below illustrates the team organisation during Rollout phases:
Change
Change Project Mgmt FSC
FSC
Mgmt
Central
Data Purif & Conversion Solution Preparation
Solution/
Solution/
Interfaces
Integration
Change
Rollout Mgmt
Mgmt
Mgmt
Site
PS 1
Roles
Roles && Training
Training Technical
Technical Dress
Dress
PS 2 Profiles
Profiles
Training
Training
Logistics Environm Rehearsal
Outages
Outages
Logistics Environm Rehearsal
PS 3
The team also attended detailed SAP PM training to help them understand the system that they are
working with. Successes are celebrated after key milestones have been achieved, e.g. through
activities such as team sport events, social dinners, etc.
Much attention is also given to do regular knowledge transfer sessions. This entails that an expert
in a subject/area spends time to transfer his/her knowledge to other team members. Individual
growth and motivation is a natural result of this effort.
Performance contracts are negotiated with each team member to include project objectives as well
as individual performance objectives. Team members are provided with regular performance
feedback. This leads to clear performance improvements.
The communication plan is a matrix that indicates exactly which message is sent to which audience
group, when and which communication channel is used. The matrix is a ‘living’ document that is
updated regularly, due to the fact that additional communication needs may arise during the
project/phase, audience groups may change, etc.
dy the
bo t
h i s w er s j e c t m e n
• T m p o p r o m p le
e K+ o i
Pr M2 am t ; w
te P P M ll o
M2K+ o fo
A ls
o je S
ya n
tio
Sp wn
Communications he ta
ck
T
• he m e n
ct
Coordinators t ple s & if
O
im o c e s n e s
on er
ba
Sp
pr e r v e ar y
in t c e s s
on
so sh
ne
ed
Project Champions
hi
p
Figure 4 illustrates the general flow of messages to the stakeholders. Each stakeholder group is
responsible to ensure that messages are communicated to the stakeholders on the level below.
Power Station Representatives (PSR’s) were identified and formally appointed at each Power
Station to ensure that the power stations actively participate in the SAP PM system implementation.
These individuals co-ordinate all the actions for their power stations to ensure that the requirements
of their station are met. They are also responsible for the data purification effort at their power
station. All project communication is directed to the PSR. He/she is then responsible to disseminate
the information to the right individuals on site.
The project sponsors are the Steering Committee members and functional owners. This body
empowers the project team to implement SAP PM. They follow the implementation process closely
and intervene when necessary.
The feedback loops are an essential part of the model. Each stakeholder group is responsible to
communicate any feedback (e.g. questions, issues, etc.) to the level above, or directly to the project
communication co-ordinators. The feedback is tracked in order to customised future messages.
Data Purification Group 3 Target as at 04 Mar 02: 90% (Completion target date is 15 Apr 02)
Progress (measured • Matla: 86.75%
based on data loaded into • Kriel: 90.02%
the purification tool) • Koeberg: 91.19%
Figure 6. Data purification progress
In order to ensure that risks are not overseen a standing agenda item has been added to the two
weekly management meetings and weekly project progress meeting to identify any new risks.
The NEC Professional Services Contract was used for the procurement of implementation partner
services with different main options to be negotiated during each phase of the project e.g. target or
termed contracts.
3.9.3 Solicitation
The software vendors submitted the names of accredited implementation partners for their products.
An enquiry was issued to all potential software and implementation partners during a site meeting
where the scope, specifications, contract documents and conditions, etc. were discussed. Proposals
were submitted at the time of tender closing.
References
1. A Guide to the project management Body of Knowledge. 2000 Edition. Exposure Draft.
2. William R Duncan. Scoping out a Scope Statement. PM Network December 1994.
3. Peg Thomas. Creating a Shared Vision with a Project Team. PM Network January 1997.
Martin Smith
Martin Smit is a Project Manager and is working for Eskom Generation. He has National Diplomas
in Civil and Mechanical Engineering and Datametrics. He also has a Mechanical Engineers
Certificate of Competency. He has been a PMP since 1992 and also is a Professional Technologist
(Engineering). He is a member of a number of Institutes and has been a Member of the Project
Management Institute (USA) since 1988. He held various management positions in construction,
project and maintenance management.