Professional Documents
Culture Documents
CONTENTS
1.Purpose
2.Scope of Work
3.Definitions
4.References
7.Safety
8.Prior Activities
9.Procedure
10.Responsibilities
2- Scope of Work
a. This procedure is applicable to the following works associated with the
project.
b. This method statement outlines the procedures to be followed in construction
of the bituminous pavement layers.
c. It shall be carried out in the site area of the project according to Technical &
General Specifications and approved drawings.
3- Definitions
CM Construction Manager
PE / SE Project Engineer / Site Engineer
CS Chief Surveyor
ITP Inspection Test Procedures
HSSE Heath ,Safety, Security, and Environmental
T.S. Technical Specifications
4- References
Technical and GeneralSpecifications.
Project Quality Plan.
Project Safety Plan.
Warning tapes
Temporary signs
Safety Barriers
Traffic Cones
Grade Stakes
7- HSSE
a. Approved safety plan procedures shall be strictly followed.
b. Where possible hazards may arise from filling activities, the necessary
safety measures will be taken to prevent accident or injury at all times.
This may include barriers, warning tape/ net, signage, watchman, and
proper lighting.
c. Where work upon existing services may be required, the necessary work
permits and safety equipment should be obtained prior to the activity
commencement.
d. HSSE will enforce that Personal Protective Equipment be worn by site
personnel at all times during construction activities.
e. Provisions of adequate cool drinking water, shade, and salt water tablets
will be in place.
8- Prior Activities
a. The Surveyor will locate and mark all live services that are present in the
site (This includes above ground services as well as buried services).
b. These services (Electric, Telephone, Gas, Oil, Chemical, Water, Drainage,
etc) will be clearly marked using stakes and warning tapes. Near these
services, special precautions will be undertaken and coordination with
the Engineer will be carried out to avoid any damages during the filling
and compaction process.
c. Any existing service if exposed during previous excavation will be clearly
marked, protected, and properly supported during all activities.
9- Procedure
9.1 Binder Layer (Asphaltic base course)
9.1.1 Prior to the placement of bituminous base course layer, the sub-base
course will be cleaned and prepared by removal of dust and deleterious
materials by air jetting or mechanically sweeping or by any approved
means. The cleaned course will be afterwards lightly made wet prior to
the application of the prime coat.
9.1.2 An approved priming coat of grade MC-1 shall be applied to the non-
bituminous sub-base layer at the rate of ( 0.65 to 1.75) liters per m 2 in
accordance with Technical specifications. Prime coat is a cutback
bitumen spray that shall be applied (50~70 oC) to all surfaces of the
crushed aggregate base course. Blotter sand is used to correct areas with
excess prime coat materials.
9.1.3 The Bitumen Distributor shall be calibrated before use. The distributor
shall be self-powered and full circulation spray bars adjustable laterally
and vertically. Heating and Mixing of bituminous materials will be
carryout accordance with T.S.
Base (*) cm
Sub-base (*) cm
9.1.8 Placing and compaction of Binder bituminous layer will be carried out in
accordance with T.S.
9.1.9 Asphalt lay down will proceeds from start to end direction along the Road.
Placement of Binder course shall begin along the centerline of a Road or
on the high side of areas with a one-way slope. The mixture shall be
placed in consecutive adjacent strips towards the uphill direction of the
Road as opposed to the downhill direction.
9.1.10 The paver will setup include the cut wooden blocks for the paver screed
to rest upon at the start of each paving day. The wooden block will reflect
the actual loose thickness of the asphalt concrete before compaction.
Normally setup the paver to 7.5m width lane with screws. However, it
can be adjusted depending on the available paving area.
9.1.11 Depending on the available area, pavers will maximize to continuous
operation. Every control point will be checked for elevation at the
beginning of the works and while processing the work.
9.1.12 Two separate equipped work teams will execute for asphalt placement at
adjacent lanes in echelon simultaneously.
In order to minimize the formation of cold joints, two running pavers
shall keep in a constant distance (D – Fig 1) in longitudinal direction.
9.1.13 According to the above Fig 1, Paving shall be conducted along the center line
until complete the available working area and follows the sequence from center
to edge.
9.1.14 The temperature of the mix (139 ~ 163 oC) will be checked in both the hauling
truck and in the paver hopper and recorded. Temperature of asphalt materials at
laying site will be control.
9.1.15 Placing and compacting of mixture will be uniform with minimum stopping and
starting of the paver. Placing and compaction shall be in accordance with T.S.
9.1.16 Once complete the compaction, string line shall be used for first lift of
bituminous surface course and then survey the grade of that lift. Provided grades
of that lift of bituminous base course meet the tolerances in accordance with
T.S.
9.1.17 Thickness and cross slope will be controlled by one gauge man with the
Asphalt paver, which shall be equipped with measure, depth stick and ruler.
9.1.18 Transverse joint shall be saw cut and carefully removed and painted with
bituminous tack coat before new material is placed against it.
9.1.19 The longitudinal joint in one course shall offset the longitudinal joint in the
course immediately below by at least 15 cm and 30 cm Max. (Otherwise
Specified), however, the joint in the surface top course shall be at the centerline
of final pavements surface.
9.2.1 Prior to the placement of bituminous Wearing layer, the Binder layer will
be cleaned and prepared by removal of dust and deleterious materials by
air jetting or mechanically sweeping or by any approved means.
9.2.2 An approved bitumen tack coat of grade RC-2 shall be applied to the
binder courses at the rate of (0.25 to 0.35) litres per m 2 or as ordered by
the Engineer.
9.2.3 Sufficient time will be allowed for the curing of the tack coat before
placing Wearing bituminous pavement layer.
9.2.4 Placing and compacting of mixture will be uniform with minimum
stopping and starting of the paver. Placing and compaction shall be in
accordance with T.S.
9.2.5 Every pass of the roller should proceed straight into the compacted mix
and return in the same path. After the required passes are completed, the
roller should move to the outside of the pavement on cooled material and
repeat the procedure (Fig 2).
10.1 The CM will coordinate with PE / SE and ensure that the necessary
resources to implement the approved method statement have been
allocated to the task.
10.2 The PE / SE will ensure that the site preparation activities are conducted
according to the approved method statement and all in-situ tests are
implemented.
10.3 Quality Control Engineer will ensure that the materials being used are in
accordance to the project specifications.
10.4 The HSSE officer along with his team will ensure implementation of all
HSSE procedures related to the nature of the works being carried out and
in accordance with Project Safety Plan.
10.5 The CS along with his team will ensure that all levels, coordinates and
stations are accordance with the approved drawings.