Table 1

Project/Displ Rate Analysis BOQ Item Short


S.NO Project_Unit Type of Work Description Element Id UOM Quantity Rate/Unit Amount Start Date End Date
ay Name Code Code Description

VANIVILLAS VILLA 21 Sub Structure EW-00 EWEX Earth work Basement Base - 001 cum 44.18 0 0 18/11/2017 20/11/2017

44.18 0 0

VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 001 cum 33.38 0 0 18/11/2017 20/11/2017
VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 002 cum 33.38 0 0 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 003 cum 33.38 18/11/2017 20/11/2017
VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 004 cum 33.38 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 005 cum 33.38 18/11/2017 20/11/2017
VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 006 cum 33.38 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-01 EWEX Earth work Footing PIT - 007 cum 33.38 18/11/2017 20/11/2017

233.66
VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 001 cum 0.99 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 002 cum 0.67 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 003 cum 0.23 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 004 cum 0.82 18/11/2017 20/11/2017
VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 005 cum 0.79 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 006 cum 0.37 18/11/2017 20/11/2017

VANIVILLAS VILLA 21 Sub Structure EW-02 EWEX Earth work Plinth PL EW - 007 cum 0.57 18/11/2017 20/11/2017
4.44

VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 001 cum 0.23 18/11/2017 18/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 002 cum 0.23 18/11/2017 18/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 003 cum 0.23 18/11/2017 18/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 004 cum 0.23 18/11/2017 18/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 005 cum 0.23 18/11/2017 18/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 006 cum 0.23 18/11/2017 18/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC-01 PCC PCC Footing PCC-FT- 007 cum 0.23 18/11/2017 18/11/2017
1.61
VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 001 cum 0.16 18/11/2017 18/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 002 cum 0.11 19/11/2017 19/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 003 cum 0.04 20/11/2017 20/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 004 cum 0.14 21/11/2017 21/11/2017

VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 005 cum 0.13 22/11/2017 22/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 006 cum 0.06 23/11/2017 23/11/2017
VANIVILLAS VILLA 21 Sub Structure PCC- 02 PCC PCC Plinth Beam PCC-PB - 007 cum 0.09 24/11/2017 24/11/2017
0.73

VANIVILLAS VILLA 21 Sub Structure PCC- 03 PCC PCC Flooring PCC-FL - 001 cum 3.68 24/11/2017 24/11/2017
3.68

VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 001 cum 1.35 19/11/17 19/11/17
VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 002 cum 1.35 19/11/17 19/11/17
VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 003 cum 1.35 19/11/17 19/11/17
VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 004 cum 1.35 19/11/17 19/11/17
VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 005 cum 1.35 19/11/17 19/11/17

VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 006 cum 1.35 19/11/17 19/11/17

VANIVILLAS VILLA 21 Sub Structure RCC-01 RCC Footing Footing FOT - 007 cum 1.35 19/11/17 19/11/17

9.45
VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 001 cum 0.1 19/11/17 19/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 002 cum 0.1 20/11/17 20/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 003 cum 0.1 21/11/17 21/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 004 cum 0.1 22/11/17 22/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 005 cum 0.1 23/11/17 23/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 006 cum 0.1 24/11/17 24/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 02 RCC Column up to basement CL FO- 007 cum 0.1 25/11/17 25/11/17
0.7
VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 001 cum 0.14 25/11/17 25/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 002 cum 0.14 25/11/17 25/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 003 cum 0.14 25/11/17 25/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 004 cum 0.14 25/11/17 25/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 005 cum 0.14 25/11/17 25/11/17

VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 006 cum 0.14 25/11/17 25/11/17
VANIVILLAS VILLA 21 Sub Structure RCC- 03 RCC Column base to GF CL-BA - 007 cum 0.14 25/11/17 25/11/17

0.98

VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 001 cum 0.29 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 002 cum 0.29 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 003 cum 0.29 25/11/17 25/11/17
VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 004 cum 0.29 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 005 cum 0.29 25/11/17 25/11/17
VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 006 cum 0.29 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 04 RCC Column GF to FF CL-GF - 007 cum 0.29 25/11/17 25/11/17
2.03

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 001 cum 0.22 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 002 cum 0.22 25/11/17 25/11/17
VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 003 cum 0.22 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 004 cum 0.22 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 005 cum 0.22 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 006 cum 0.22 25/11/17 25/11/17
VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 007 cum 0.22 25/11/17 25/11/17

VANIVILLAS VILLA 21 Super Structure RCC- 05 RCC Column FF to TR CL-FI - 008 cum 0.22 25/11/17 25/11/17

1.76

1
Table 1

1 General 12

2 Carriage of Materials 12
3 Earth Work 12
3 Mortars 12
3 Concrete Work 12
3 Reinforced Cement
Concrete Work

3 Brick Work
3 Stone Work
Marble Work
Wood Work and PVC
Work

Steel Work
Flooring
Roofing
Finishing
Sanitary Installation
Water Supply
Drainage
Aluminium Work
Water Proofing
Shutering work

2
Table 1
Project/Display Project_Unit BOQ BOQ Item Short Description Description Element Id Type of Work Quantity Rate/Unit Amount UOM Start Date End Date
Name Code

VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -A1- 001 SUBSTRUCTURE 3.12 300 936 cum 2017-11-26 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -A2- 002 SUBSTRUCTURE 3.12 300 936 cum 2017-11-27 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -A3- 003 SUBSTRUCTURE 3.12 300 936 cum 2017-11-28 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -A4- 004 SUBSTRUCTURE 3.12 300 936 cum 2017-11-29 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -B3- 005 SUBSTRUCTURE 3.12 300 936 cum 2017-11-30 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -C1- 006 SUBSTRUCTURE 3.12 300 936 cum 2017-12-1 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -C2- 007 SUBSTRUCTURE 3.12 300 936 cum 2017-12-2 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -C3- 008 SUBSTRUCTURE 3.12 300 936 cum 2017-12-3 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -D3- 009 SUBSTRUCTURE 3.12 300 936 cum 2017-12-4 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -D4- 010 SUBSTRUCTURE 3.12 300 936 cum 2017-12-5 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -E1- 011 SUBSTRUCTURE 3.12 300 936 cum 2017-12-6 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A100 Foundations A103 Site earthwork Site earthwork EXC -E2- 012 SUBSTRUCTURE 3.12 300 936 cum 2017-12-7 2017-11-30
Footing Footing
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -A1- SUBSTRUCTURE 100 936 cum 5-12-17 6-12-17
A100 Foundations 0.43
001
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -A2- SUBSTRUCTURE 100 936 cum 6-12-17 7-12-17
A100 Foundations 0.43
002
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -A3- SUBSTRUCTURE 100 936 cum 7-12-17 8-12-17
A100 Foundations 0.43
003
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -A4- SUBSTRUCTURE 100 936 cum 8-12-17 9-12-17
A100 Foundations 0.43
004
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -B3- SUBSTRUCTURE 100 936 cum 9-12-17 10-12-17
A100 Foundations 0.43
005
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -C1- SUBSTRUCTURE 100 936 cum 10-12-17 11-12-17
A100 Foundations 0.43
006
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -C2- SUBSTRUCTURE 100 936 cum 11-12-17 12-12-17
A100 Foundations 0.43
007
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -C3- SUBSTRUCTURE 100 936 cum 12-12-17 13-12-17
A100 Foundations 0.43
008
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -D3- SUBSTRUCTURE 100 936 cum 13-12-17 14-12-17
A100 Foundations 0.43
009
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -D4- SUBSTRUCTURE 100 936 cum 14-12-17 15-12-17
A100 Foundations 0.43
010
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -E1- SUBSTRUCTURE 100 936 cum 15-12-17 16-12-17
A100 Foundations 0.43
011
VILLA PRIMERO VILLA 1 A105 PCC-under footing PCC-under footing
PCC -E2- SUBSTRUCTURE 100 936 cum 16-12-17 17-12-17
A100 Foundations 0.43
012

3
Table 1
LOD table

Model Element MEA Project Phase Notes

Conceptual Design Schematic Design Design Development Construction Documentation Construction Facility Management
CO SD DD CD CN FM Legend

SPATIAL Project Phase

Site boundaries, CO Conceptual Design


setbacks

Grids SD Schematic Design

Levels DD Design Development

Zones CD Contract
Documentation
Spaces, rooms CN Construction

SITE

Topography Model Element Author (MEA)

Excavation A Architect

Stormwater C Contractor

Services S Structural Engineer

Roads Mechanical Engineer


M

Parking E Electrical Engineer

Paths, paving P Hydraulic Engineer

Walls, fencing Fire Services


F Engineer
Soft landscaping Cv Civil Engineer

SUBSTRUCTURE Landscape Architect


L

Footings O Other

Retaining walls

Subsoil drainage LOD Level of Development

STRUCTURE 100 Conceptual

Floor structures 200 Approximate


geometry
Beams 300 Precise geometry

Shaft openings 400 Fabrication

Stair & ramp 500 As-built


structures

Walls – load
bearing

Columns

Roof structures

ENCLOSURE

Roofing

Cladding

Column claddings

Curtain walls

Windows

External doors,
openings

INTERIOR

Partitions

Internal doors,
openings

Ceilings

Flooring

Balustrading

F, F & E

Casework, joinery

Fixtures

Fittings

Equipment (non-
service)

Furniture

Signage

MECHANICAL

Plant &
equipment
Ductwork

Pipework

Air terminals

Services in risers

HYDRAULIC

Plant &
equipment
Sanitary fixtures

Pipework

Fire services

Services in risers

ELECTRICAL

Electrical fixtures

Power outlets

Switch &
distribution
boards

Cable trays,
ducts
Lighting

Communications

Security

Services in risers

CONVEYING

Lifts, escalators

4
Table 1
LOD table (UniFormat alternative)

Model Element by CSI UniFormat TM classification MEA Project Phase Notes

Conceptual Schematic Design Contract Facility


Design Design Development Documentation Construction Management
CO SD DD CD CN FM Legend

A SUBSTRUCTURE Project Phase


A101 A101.01 Site clearing manual

A101.02 Site clearing machine

A102 Footing Marking

A103 Site earthwork Footing

A104 Sand Filling under footing

A105 PCC-under footing

A106.01 Column Marking

A106.02 Reinforcement for footing

A106.03 Shuttering for footing


A106
Footing Concrete
A100 A106.04 Footing Concrete
Foundations
A106.05 Shuttering for Pedestrial

A106.06 Pedestrial Concrete

A107 Backfill Foundation CO Conceptual Design


A108 Earthwork Plinth Beam SD Schematic Design
A109 Sand Filling under Plinth DD Design Development
Beam

A110 PCC-under Plinth beam CD Contract Documentation


A111.01 Reinforcement for Plinth
Beam

A111.02 Shuttering for Plinth Beam


A111 Plinth Beam Concreting

A111.03 Plinth Beam Concrete

A201 Basement Excavation

A202 Basement walls


A200
A203 Sand filling
Basement
construction A204 PCC

A205 Basement Flooring CN Construction

B SHELL

B101.01 Column Marking Model Element


Column Reinforcement Author (MEA)
B101.02 A Architect
B101 Ground Floor Column Column Shuttering
B101.03 C Contractor
Concreting
Verification
B101.04
Column Concreting
B101.05
B102 Block work for plinth

B103 Pit Sand Filling for Plinth

B104 Anti termite treatment

B105 Sand Filling for plinth

B106 PCC For Flooring

First Slab Shuttering


B107.01
First Slab Reinforcement
B107.02
B100 B107
First Floor Slab Concreting
Superstructur B107.03
Electrical conduit for slab
e
First Slab Concrete
B107.04

B108 Water Curing work

Column Marking
B109.01
Column Reinforcement
B109.02
B109 First Floor Column Concreting
Column Shuttering
B109.03

Column Concreting
B109.04 S Structural Engineer
Second Slab Shuttering
B110.01

Second Slab Reinforcement


B110.02
Second Floor Slab
B110
Concreting Electrical conduit for slab
B110.03

Second Slab Concrete


B110.04

B111 Water Curing work

B201.01 Ground floor Exterior wall


work upto Sill Level M Mechanical Engineer
B201.02 Shuttering for Sill

B201.03 Reinforcement for Sill

B201.04 Concrete for Sill

B201.05 Ground floor Exterior wall


B201 Ground Floor Block work work upto Lintel

B201.06 Shuttering for Lintel

B201.07 Reinforcement for Lintel

B201.08 Concrete for Lintel

B201.09 Ground floor Exterior wall


work above Lintel

B202.01 First floor Exterior wall work


upto Sill Level

B202.02 Shuttering for Sill


B200 Exterior
B202.03 Reinforcement for Sill
Block work
B202.04 Concrete for Sill

B202.05 First floor Exterior wall work


B202 First Floor Block work upto Lintel

B202.06 Shuttering for Lintel

B202.07 Reinforcement for Lintel

B202.08 Concrete for Lintel

B202.09 First floor Exterior wall work


above Lintel

B215 Parapet Block work

B216 Outer Plasting-North

B217 Outer Plasting-South

B218 Outer Plasting-East

B219 Outer Plasting-West

B301 Roof Concrete


E Electrical Engineer
B302 water Proof work
B300 Roofing B303 Tile work

P Hydraulic Engineer
C INTERIORS F Fire Services Engineer
C101 Door Frame Fixing
Cv Civil Engineer
C102 Window Frame Fixing
L Landscape Architect
C103 Electrical Conduit Works

C104 Plumbng Works

C105 Sunken Water proofing

Hall Ceiling Plastering


C106.01
Kitchen Ceiling Plastering
C106.02
Ground Floor Ceiling
C106
Plastering Bedroom Ceiling Plastering
C106.03

Toilet Ceiling Platering


C106.04
Family Ceiling Plastering
C107.01
Bedroom 1 Ceiling Plastering
C107.02
C107 First floor Ceiling Plastering
Bedroom 2 Ceiling Plastering
C107.03

Toilet Ceiling Platering


C107.04

C108.01 North hall Wall Plastering

C108.02 South hall Wall Plastering

C108.03 East hall Wall Plastering

C108.04 west hall Wall Plastering

C108.05 North Kitchen wall Plastering

C108.06 South Kitchen wall Plastering

C108.07 East Kitchen wall Plastering

C108.08 West Kitchen wall Plastering

C108 Ground floor Wall Plastering C108.09 North bedroom Wall


Plastering

C108.10 South bedroom Wall


Plastering

C100 Interior C108.11 East bedroom Wall Plastering


construction
C108.12 west bedroom Wall
Plastering

C108.13 North toilet wall Plastering

C108.14 South toilet wall Plastering

C108.15 East toilet wall Plastering

C108.16 West toilet wall Plastering

C109.01 North family Plastering

C109.02 South family Wall Plastering

C109.03 East family Wall Plastering

C109.04 west family Wall Plastering

C109.05 North bedroom 1 Wall


Plastering

C109.06 South bedroom 1 Wall


Plastering

C109.07 East bedroom 1 Wall


Plastering

C109.08 west bedroom 1 Wall


Plastering
C109 First floor Wall Plastering
C109.09 North bedroom 2 Wall
Plastering

C109.10 South bedroom 2 Wall


Plastering

C109.11 East bedroom 2 Wall


Plastering

C109.12 west bedroom 2 Wall


Plastering

C109.13 North toilet wall Plastering

C109.14 South toilet wall Plastering

C109.15 East toilet wall Plastering

C109.16 West toilet wall Plastering

C201 Stair construction

C200 Stairs Railing work

C202 Stair finishes LOD Level of Development


Hall Painting 100 Conceptual
C301.01
Kitchen Painting
C301.02
Ground Floor Wall finishes
C301
Painting Bedroom Painting
C301.03
Toilet Painting
C301.04
Family Painting
C302.01

Bedroom 1 Painting
C302.02
First Floor Wall finishes
C302
Painting Bedroom 2 Painting
C302.03
Toilet Painting
C302.04
C303 Wall Tiling work

Hall Floor Tile 200 Approximate geometry


C304.01
C300 Interior
finishes C304.02
kitchen Floor Tile
C304 Ground Floor finishes
Bedroom Floor Tile
C304.03
Toilet Floor Tile
C304.04
Family Floor Tile
C305.01

Bedroom 1 Floor Tile


C305.02
C305 First Floor finishes
Bedroom 2 Floor Tile
C305.03

Toilet Floor Tile


C305.04
C305 Door Shutter fixing

C306 Window Shutter fixing

C307 Ceiling finishes 300 Precise geometry

D SERVICES 400 Fabrication


D10 Conveying D101 Elevators and lifts 500 As-built
D102 Escalators and moving
walks

D103 Other conveying systems

D201 Plumbing fixtures

D202 Domestic water distribution

D200 D203 Sanitary waste


Plumbing
D204 Rainwater drainage

D205 Other plumbing systems

D30 HVAC D301 Energy supply

D302 Heat generating systems

D303 Cooling generating systems

D304 Distribution systems

D305 Terminal and package units

D306 Controls and instrumentation

D307 Systems testing and


balancing

D308 Other HVAC systems &


equipment

D40 Fire protection D401 Sprinklers

D402 Standpipes

D403 Fire protection specialties

D404 Other fire protection


systems

D501 Electrical service and


distribution

D502 Lighting and branch wiring

D500 D503 Communications and


Electrical security

D504 Other electrical systems

D505 Home Automation

E EQUIPMENT & FURNISHINGS


E10 Equipment E1010 Commercial equipment

E1020 Institutional equipment

E1030 Vehicular equipment

E1090 Other equipment

E20 Furnishings E2010 Fixed furnishings

E2020 Moveable furnishings

F SPECIAL CONSTRUCTION & DEMOLITION


F10 Special F1010 Special structures
construction
F1020 Integrated construction

F1030 Special construction


systems

F1040 Special facilities

F1050 Special controls &


instrumentation

F20 Selective build. F2010 Building elements demolition


demo

F2020 Hazardous components


abatement

G BUILDING
SITEWORK
G10 Site preparation G1010 Site clearing
1
G1020 Plinth Beam Earthwork 9

G1030 Site earthwork 3

G1040 Hazardous waste


remediation

G1050 Site Marking 2

G1060 Foundation back 8


filling
G20 Site G2010 Roadways
improvements
G2020 Parking lots

G2030 Pedestrian paving

G2040 Site development

G2050 Landscaping

G30 Site civil/mech. G3010 Water supply & distribution


utilities systems

G3020 Sanitary sewer systems

G3030 Storm sewer systems

G3040 Heating distribution

G3050 Cooling distribution

G3060 Fuel distribution

G3090 Other civil/mechanical


utilities

G40 Site electrical G4010 Electrical distribution


utilities
G4020 Site lighting

G4030 Site communications and


security

G4090 Other electrical utilities

G50 Other site G5010 Service tunnels


construction
G5090 Other site systems and
equipment