WBS Structure of Construction of House Project

WBS Dictionary of the Project

WBS Number: WBS Name:


1.1.1 Concrete
WBS Predecessor(s): WBS Description:
None This component consists of pouring the foundation, installing the
patio and stairway. This component is the basis of all other
components.
Must-Start Date:
1-12-2017
Must-Finish Date:
31-12-2017
WBS Estimated Effort: Assumptions and Constraints:
31 The concrete will be delivered on a weekly basis on each Wednesday
by the contractor.
Assigned to:
Ali Aslam
WBS Number: WBS Name:
1.1.1.1 Pour Foundation
WBS Predecessor(s): WBS Description:
None This component consists of laying the foundation of the house. The
foundation should be according to the specifics in the map provided.
The foundation design is based on earthquake proof architecture.

Must-Start Date:
3-12-2017
Must-Finish Date:
20-12-2017
WBS Estimated Effort: Assumptions and Constraints:
20 The concrete will be delivered on a weekly basis on each Wednesday
by the contractor. It is assumed that the assignee has the architecture
Assigned to:
plan.
Rahim Khan

WBS Number: WBS Name:


1.1.1.2 Install Patio
WBS Predecessor(s): WBS Description:
1.1.1.1 This component consists of installing the patio of the house at the
specified location in the map. It also deals with all other things related
to the patio installment.
Must-Start Date:
20-12-2017
Must-Finish Date:
29-12-2017
WBS Estimated Effort: Assumptions and Constraints:
9 The concrete will be delivered on a weekly basis on each Wednesday
by the contractor. It is assumed that the assignee has the architecture
Assigned to:
plan.
Asfand Jhangir

WBS Number: WBS Name:


1.1.1.3 Stairway
WBS Predecessor(s): WBS Description:
1.1.1.1 To build the concrete structure of the stairway inside the house at the
specified location on the map and ensuring its stability.
Must-Start Date:
20-12-2017
Must-Finish Date:
30-12-2017
WBS Estimated Effort: Assumptions and Constraints:
10 The concrete will be delivered on a weekly basis on each Wednesday
by the contractor. It is assumed that the assignee has the architecture
Assigned to:
plan.
Rahim Khan

WBS Number: WBS Name:


1.1.2 Framing
WBS Predecessor(s): WBS Description:
1.1.1 To frame the exterior and interior walls along with the roof trusses.

Must-Start Date:
1-1-2018
Must-Finish Date:
20-1-2018
WBS Estimated Effort: Assumptions and Constraints:
10 The concrete will be delivered on a bi-daily basis by the contractor. It
is assumed that the assignee has the architecture plan.
Assigned to:
Ali Aslam

WBS Number: WBS Name:


1.1.2.1 Frame Exterior Walls
WBS Predecessor(s): WBS Description:
1.1.1 To frame the exterior walls according to the design and specifications
in the map.
Must-Start Date:
2-1-2018
Must-Finish Date:
10-1-2018
WBS Estimated Effort: Assumptions and Constraints:
8 The concrete will be delivered on a bi-daily basis by the contractor. It
is assumed that the assignee has the architecture plan.
Assigned to:
Farrukh Ali
WBS Number: WBS Name:
1.1.2.2 Frame Interior Walls
WBS Predecessor(s): WBS Description:
1.1.2.1 To frame the interior walls according to the design and specifications
in the map.
Must-Start Date:
11-1-2018
Must-Finish Date:
15-1-2018
WBS Estimated Effort: Assumptions and Constraints:
4 The concrete will be delivered on a bi-daily basis by the contractor. It
is assumed that the assignee has the architecture plan.
Assigned to:
Farrukh Ali

WBS Number: WBS Name:


1.1.2.3 Install Roofing Trusses
WBS Predecessor(s): WBS Description:
1.1.2.1 To install the roofing trusses of the house according to the specified
1.1.2.2 design.
Must-Start Date:
16-1-2018
Must-Finish Date:
20-1-2018
WBS Estimated Effort: Assumptions and Constraints:
4 The concrete will be delivered on a bi-daily basis by the contractor. It
is assumed that the assignee has the architecture plan.
Assigned to:
Farrukh Ali

WBS Number: WBS Name:


1.1.3 Plumbing
WBS Predecessor(s): WBS Description:
1.1.2 To install the water and gas lines in the house along with the
installation of bath and kitchen fixtures.
Must-Start Date:
20-1-2018
Must-Finish Date:
27-1-2018
WBS Estimated Effort: Assumptions and Constraints:
7 The notification for connecting the gas and water lines to the local
line has to be given to the local authority 1 day prior and exact time
Assigned to:
has to be communicated.
Behzad Ahmed

WBS Number: WBS Name:


1.1.3.1 Install Water Lines
WBS Predecessor(s): WBS Description:
1.1.2 To install the water lines in the house and connect them to the local
supply lines.
Must-Start Date:
20-1-2018
Must-Finish Date:
24-1-2018
WBS Estimated Effort: Assumptions and Constraints:
4 The notification for connecting the gas and water lines to the local
line has to be given to the local authority 1 day prior and exact time
Assigned to:
has to be communicated.
Javed Akram

WBS Number: WBS Name:


1.1.3.2 Install Gas Lines
WBS Predecessor(s): WBS Description:
1.1.2 To install the gas lines in the house and connect them to the local
supply lines.
Must-Start Date:
22-1-2018
Must-Finish Date:
25-1-2018
WBS Estimated Effort: Assumptions and Constraints:
3 The notification for connecting the gas and water lines to the local
line has to be given to the local authority 1 day prior and exact time
Assigned to:
has to be communicated.
Javed Akram
WBS Number: WBS Name:
1.1.3.3 Install Gas Lines
WBS Predecessor(s): WBS Description:
1.1.3.1 To install the kitchen and bath fixtures in the kitchen and all
1.1.3.2 bathrooms in the house.
Must-Start Date:
25-1-2018
Must-Finish Date:
27-1-2018
WBS Estimated Effort: Assumptions and Constraints:
2 None
Assigned to:
Javed Akram

WBS Number: WBS Name:


1.1.4 Electrical
WBS Predecessor(s): WBS Description:
1.1.3 To install the electrical wiring, outlets and electrical fixtures in the
house and connecting them to the local supply.
Must-Start Date:
27-1-2018
Must-Finish Date:
4-2-2018
WBS Estimated Effort: Assumptions and Constraints:
8 The notification for connecting the electrical wiring to the local line
has to be given to the local authority 1 day prior and exact time has to
Assigned to:
be communicated.
Tanveer Yasir

WBS Number: WBS Name:


1.1.4.1 Install Wiring
WBS Predecessor(s): WBS Description:
1.1.3 To install the electrical wiring in the house and connecting them to
the local supply.
Must-Start Date:
27-1-2018
Must-Finish Date:
31-1-2018
WBS Estimated Effort: Assumptions and Constraints:
4 The notification for connecting the electrical wiring to the local line
has to be given to the local authority 1 day prior and exact time has to
Assigned to:
be communicated.
Haris Khan

WBS Number: WBS Name:


1.1.4.2 Install Outlets/Switches
WBS Predecessor(s): WBS Description:
1.1.4.1 To install the electrical outlets/switches in the house at all the
locations.
Must-Start Date:
1-2-2018
Must-Finish Date:
2-2-2018
WBS Estimated Effort: Assumptions and Constraints:
2 None
Assigned to:
Haris Khan

WBS Number: WBS Name:


1.1.4.2 Install Fixtures
WBS Predecessor(s): WBS Description:
1.1.4.1 To install the electrical fixtures in the house at all the locations.
1.1.4.2
Must-Start Date:
3-2-2018
Must-Finish Date:
4-2-2018
WBS Estimated Effort: Assumptions and Constraints:
2 The electrical fixtures are delivered by the contractor 1 day prior.
Assigned to:
Haris Khan

WBS Number: WBS Name:


1.1.5 Interior
WBS Predecessor(s): WBS Description:
1.1.4
To install the interior components i.e. drywall, carpets and painting of
the house.
Must-Start Date:
3-2-2018
Must-Finish Date:
10-2-2018
WBS Estimated Effort: Assumptions and Constraints:
7 The drywall, paint and carpets have been received 1 day prior to the
starting date.
Assigned to:
Aliya Rizwan

WBS Number: WBS Name:


1.1.5.1 Install Drywall
WBS Predecessor(s): WBS Description:
1.1.4 To install drywall in the wall frames of the house.
Must-Start Date:
3-2-2018
Must-Finish Date:
5-2-2018
WBS Estimated Effort: Assumptions and Constraints:
3 The drywall has been received at least 1 day prior to the starting date.
Assigned to:
Javed Bashir

WBS Number: WBS Name:


1.1.5.2 Install Carpets
WBS Predecessor(s): WBS Description:
1.1.5.1 To install carpets on the floor of the house where ever specified.
1.1.5.3
Must-Start Date:
10-2-2018
Must-Finish Date:
10-2-2018
WBS Estimated Effort: Assumptions and Constraints:
1 The carpets has been received at least 1 day prior to the starting date.
Assigned to:
Javed Bashir
WBS Number: WBS Name:
1.1.5.3 Painting
WBS Predecessor(s): WBS Description:
1.1.5.1 To paint the walls of the house according to the specified colors.
Must-Start Date:
6-2-2018
Must-Finish Date:
9-2-2018
WBS Estimated Effort: Assumptions and Constraints:
4 The paint has been received at least 1 day prior to the starting date.
Assigned to:
Hamza Bashir

WBS Number: WBS Name:


1.1.6 Roofing
WBS Predecessor(s): WBS Description:
1.1.5 To install felt, shingles and vents in the roof of the house.
Must-Start Date:
10-2-2018
Must-Finish Date:
16-2-2018
WBS Estimated Effort: Assumptions and Constraints:
7 All the materials have been delivered to the storage space 2 days
prior necessarily.
Assigned to:
Junaid Bajwa

WBS Number: WBS Name:


1.1.6.1 Install Felt
WBS Predecessor(s): WBS Description:
1.1.5 To install felt on the roof of the house.
Must-Start Date:
10-2-2018
Must-Finish Date:
12-2-2018
WBS Estimated Effort: Assumptions and Constraints:
3 None
Assigned to:
Rizwan Asif

WBS Number: WBS Name:


1.1.6.2 Install Shingles
WBS Predecessor(s): WBS Description:
1.1.6.1 To install shingles on the roof of the house.
Must-Start Date:
12-2-2018
Must-Finish Date:
15-2-2018
WBS Estimated Effort: Assumptions and Constraints:
4 None
Assigned to:
Rizwan Asif

WBS Number: WBS Name:


1.1.6.3 Install Vents
WBS Predecessor(s): WBS Description:
1.1.5 To install vents in the roof of the house.
Must-Start Date:
10-2-2018
Must-Finish Date:
17-2-2018
WBS Estimated Effort: Assumptions and Constraints:
8 None
Assigned to:
Hammad Ali