PROPOSED ADDITIONS & ALTERATIONS FOR THE HOUSE FOR MR. NIRANJAN A.

AT No. 128/30, SRI SIDDHARTHA ROAD, KIRULAPANA, COLOMBO - 06.


PROJECT No. :- CSL / 304 / 902
DATE :- 20.06.2017
BILL OF QUANTITY
UP TO FIRST FLOOR SLAB LEVEL
Item
Description Unit Qty Rate Amount
No
1.0 B - PRELIMINARIES
1.1 Remove and take away Debris from all un wanted walls, Roof and foundations
and prepare the site for new construction Item 30,000.00

PRELIMINARIES CARRIED TO SUMMARY 30,000.00


2.0 D - EXCAVATION & EARTH WORK
2.1 Excavation
Up to DPC Level
2.1.1 Excavate to form Trench for Foundation Cu.ft - - 0.00
2.2 Earth Filling
Up to DPC Level
2.2.1 Filling under floors including levelling, watering &
compaction in 6" Layers with selected imported earth. Cu.ft - - 0.00

EXCAVATION & EARTH WORK CARRIED TO SUMMARY 0.00


3.0 F - CONCRETE WORK
3.1 F1 - INSITU CONCRETE
Rates shall include for:
* Form Work & Reinforcement
3.1.1 Plain Concrete Mix 1:3:6 ( 1 1/4" )
Up to DPC Level
3.1.1.1 3" Thick concrete under the Foundation. L.ft - - 0.00
3.1.1.2 3" thk. Concrete for ground floor Sq.ft. - - 0.00
3.1.2 Reinforced Concrete Mix 1:1 1/2:3 ( 3/4" )
Up to DPC Level
In 3'-6" x 3'-6" Column Base with 9" x 9" & 9"Ø Column Shaft (Rate including Excavation,
3.1.2.1
Lean Concrete , Base & Shaft Concreting) Cu.ft - - 0.00
3.1.2.2 In Staircase Base ( Rate including Excavation, Lean Concrete,
Base & Shaft Concreting) Cu.ft - - 0.00
Item
Description Unit
No

2nd Floor Slabe Level to Roof


3.1.2.7 In 9" x 9" & 9"Ø Column Shaft L.ft 100.00 250.00 25,000.00
3.1.2.9 In 12"X12" Beam L.ft 120.00 250.00 30,000.00

3.1.2.11 In 5" Thk. Slab concrete Sq.ft 400.00 210.00 84,000.00


3.1.2.13 In +-0m Level to +3.750m Level Staircase Sq.ft 100.00 210.00 21,000.00
3.1.2.15 In Lintel (Rate including Concrete Work, Form Work & L.ft - - -
3.2 F2 - FORM WORK
Rates shall include for:
* All necessary boardings, supports, erecting, framing, cutting angles,
cleaning, wetting & treatment before placing concrete & removal.
Second Floor Slab Level to Roof Level
3.2.5 In 9 " x 9" Ø Column Shaft Sq.ft 300.00 250.00 75,000.00
3.2.6 In 12" x 12" First Second Floor Beam Sq.ft 400.00 250.00 100,000.00
3.2.7 In 125 mm Thk. First Floor Slab Sq.ft 400.00 250.00 100,000.00
3.2.8 In +-0m Level to +3.750m Level Staircase Sq.ft 100.00 350.00 35,000.00
3.3 F3 - REINFORCEMENT WORK
* Cleaning, Cutting, Bending, lapping, fabrication, Binding Wires,
Ties, Spaces, Chairs, Placing & Provision of all necessary
temporary fixing & supports.
* Reinforcement steel rods should be having a minimum
characteristic strength of 460 N/mm2 & SLS approval.
Item
Description Unit
No
3.3.1 High Yield Tor Steel Bar
Up To Second Floor Slab Level
3.3.1.1 12mm dia. in 6" Thk. Second Floor Slab Kg 250.00 80.00 20,000.00
3.3.1.2 12mm dia. In Column 9" x 9" & Column Shaft Kg 100.00 80.00 8,000.00
3.3.1.3 12mm dia. in Staircase Base Kg 150.00 80.00 12,000.00
3.3.2 Mild Steel Round Bar
Second Floor Slab Level to Roof Level
3.3.2.3 6mm dia. In 9" x 9" Ø Column Shaft Kg 75.00 65.00 4,875.00
3.3.2.4 6mm dia. in 12" x 12" Second Floor Beam Kg 75.00 65.00 4,875.00

CONCRETE WORK CARRIED TO SUMMARY 519,750.00


4.0 G - MASONRY WORK
4.1 G1 - BRICK WORK / BLOCK WORK
Rates shall include for:
* All rough and fair cutting, forming rough & fair groves, throats,
mortices, chases, rebates & holes, stops & mitres.
Second Floor Slab Level to Roof Level
4.1.1 4.5" Thick Brick Wall Cement Sand 1 : 5 in Foundation Sq.ft 1,500.00 175.00 262,500.00
4.1.2 9" Thick Brick Wall Cement Sand 1 : 5 in Foundation Sq.ft - - 0.00
4.1.3 9" Thick Block Wall Cement Sand 1:5 in Foundation Sq.ft - - 0.00
Item
Description Unit
No
4.2 G2 - STONE WORK
Rates shall include for:
* Extra stone for joints, mortices, holes ,stops & arises Rough &
Fair square cutting
Up to DPC Level
4.2.1 6" x 9" Random Rubble Masonry in 1:5 cement & sand mortar in
Foundation. Cu.ft - - 0.00

MASONARY WORK CARRIED TO SUMMARY 262,500.00


5.0 H - WATER PROOFING
5.1 Damp Proof Course
5.1.1 3/4" Thick Damp Proof Course in 1:3 Cement and sand on Tie
Beam & Apply Three Coats of Hot Tar Blinded with Fine Sand L.ft - - 0.00
5.3 Water Proofing
DPC Level To First Floor Slab Level
5.3.1 Water Proofing Treatment for Toilet Floors using Approved
Product including preparation of surface according to Manufacturs
Specification. Sq.ft 100.00 60.00 6,000.00
6 WATER PROOFING CARRIED TO SUMMARY 6,000.00
K - METAL WORK
Iron Work
Hand Rail
DPC Level To First Floor Slab Level
6.1 Iron Hand Railing for +-0m Level to +3.750m Level Staircase L.ft - - 0.00

7 METAL WORK CARRIED TO SUMMARY 0.00


L - WOOD WORK
L2 - JOINERY
Rates shall include for:
* Screws, Locks, Hinges, Fasteners & Installation.
7.1 Doors
DPC Level To First Floor Slab Level
Door Type D1 (3-0' x 8-0') Timber Frame Pannel Door
with Fixed Glass - 01 Nos.
Door Type D3 (3-0' x 7-0') Marine Door - 01 Nos. Nos 1.00 35,000.00 35,000.00
Door Type D4 ( (2'-6'' x 7-0') Timber Frame Door - 01 Nos. Nos 3.00 20,000.00 60,000.00
7.2 Window
Window Ttpe SD1(4' x 4') Sliding Door Window- 01 Nos. Nos 3.00 12,000.00 36,000.00

7.4 L - WOOD WORK


P - ROOF COVERING & ROOF PLUMBING
Rates shall include for:
* All cutting, notchimg, drilling, sinking, trimming, forming, jointing
laps, straight cutting & waste, splayed edges & the like including
fixing in position complete with all nails, spikes, screws, priming
points & ends.
* Ceiling For Roof with Approved & Quality Material
Rafter, Purlin, Strut & Valance Board )
* Roof Structure ( Rafters, Reepers, Ridge Plate, Wall Plate, Hip
Rafter, Purlin, Strut & Valance Board )
First Floor Slab Level To Roof Level
7.4.1 23° Slope Temporary Roof on Timber Frame Work complete
with Ridges, Hips & all the Roof Plumbing Work accoding to the
Detail Drawings. Item 1.00 150,000.00 150,000.00
WOOD WORK CARRIED TO SUMMARY 281,000.00
8.0 T - FLOOR, WALL & CEILING FINISHES
8.1 T1 - FLOOR FINISHES
Rates shall include for:
* Cutting, Bedding Mortars & Adhesives, Grouting, Cleaning,
Sealing & Polishing

8.1.1 Cement Rendering with smooth finishes by using colored cement, Sand Mortar mixture Sq.ft 400.00 50.00 20,000.00

8.2 Plastering
To Second Floor Slab Level to Roof Level
8.2.1 10mm Thick 1 : 4 Cement & Sand Plaster Finished Semi Rough for
External Wall -4.5" walls Sq.ft 1,500.00 40.00 60,000.00
8.2.2 10mm Thick 1 : 4 Cement & Sand Plaster Finished Semi Rough for
Internal Wall -4.5" walls Sq.ft 1,500.00 40.00 60,000.00

FLOOR, WALL AND CEILING FINISHES WORK CARRIED TO SUMMARY 140,000.00


9.0 V - PAINTING
Rates shall include for:
* All preparation of surfaces, cleaning down, smothing, knotting,
protection of the floors, fittings.
DPC Level To First Floor Slab Level
9.1 Prepare & apply approved colour & quality paint to Plinth. Sq.ft.
9.2 Prepare & apply one Primer coat & two coats of Weather shield
paint of approved colour & quality to External faces of walls Sq.ft. 1,500.00 40.00 60,000.00
9.3 Prepare & apply one Primer coat & two coats of Emulsion paint
of approved colour & quality to Internal faces of walls Sq.ft. 1,500.00 55.00 82,500.00
PAINTING WORK CARRIED TO SUMMARY 142,500.00

Prepared By : ………………………………………
M.T.Ahamed
J.K.S.S.
Nusky
Jayakody
Quantity Surveyor
Mobile No: +94 77 3940214
Address: 128/38, Sri Siddhartha Road, Colombo -06