You are on page 1of 3

EDG COMMISSIONING

ACTIVITY REPORT
Month of October 2017

Client: Schlumberger Vendor Company Compagnia Tecnica Motori S.p.A.


Heavy Oil Production Facility (HOPF) at Umm
Project:
Niqa Vendor Name Nenad Milosavljevic – CTM Commissioning engineer
System: Fire Water Pumps
CTM Job: 8362

Date Activity description


10/10/2017 Travel day (Italy to Kuwait)

Visual Inspection of installed equipment.


Check the level of Lube Oil, Coolant and Fuel. Inspection of electrical interconnection between the Deasel tank and Diesel pump - Control
11/10/2017
panel.
Check the battery and refilling the battery (bank 1 & 2) by electrolyte - Diesel pum A

Check the battery and refilling the battery (bank 1 & 2) by electrolyte - Diesel pum B
12/10/2017 Energize the control panel by 240V/440V. Energize the battery charger and preheating system. Disconnect the battery bank n°1 (diesel
pump B). Charge the battery by external charger due to low voltage.

Connect the battery bank n°1 – Diesel pump B.


Energize the control panel (battery 24Vdc). Preparation for first crank of diesel pump B.
Prime the engine by diesel. Crank the diesel pump – Diesel engine run 1500rpm. Oil pressure 6 bar.
13/10/2017
The pump not running. Stop the engine and remove the Coupling protection cover. (The engine flange and pump flange of flexible coupling is
not bolted and not aligned).
Carry out inspection – Diesel pump A (The engine flange and pump flange of flexible coupling is not bolted and not aligned)

14/10/2017 Diesel pum A - Preparation for aligment (aligment bolts – not availeble on site)

Date Activity description

1 of 3
EDG COMMISSIONING
ACTIVITY REPORT
Month of October 2017

Travel from Damietta to Al Shabab site.


Modification of DST 4602 Controller parameters in order to run in parallel with grid.
Carry out functional test:
11/09/2017 ON Load test with the grid (100% of nominal load)
Preliminary check and inspection of second EDG, preparation for first crank.
First crank and run EDG (from the gauge panel)
Start EDG in manual mode from the Local control Panel.

Carry out functional test:


12/09/2017 NO load test and simulation of Shutdown during NO Load test.
ON Load test with the grid (100% of nominal load) – with Pgesco and Owner representative

Carry out functional test and modification in order to provide additional protection in case of failure signal from under voltage relay (main
voltage presents and inhibit start) – requested by Pegaco.
13/09/2017
Carry out the test after modifications (simulate remote and V3/V4 voltage signal missing – Q3 close and Bus voltage present)
EDG start in auto mode and perform the synchronizing before to close the Generator Breaker)

Carry out functional test and modification in order to provide cooling time after opening of Generator Circuit Breaker (in Auto mode – ON load
Test mode)
14/09/2017
Protection relay setting and wiring modification in order to disable protection for 27 and 80U during the stopping EDG (NG 20 enable Input 1
and assigned the Block 1 to disable 27/80U during the stopping)

15/09/2017 Day OFF (Friday)

Travel from Damietta to Al Shabab site.


Modification of DST 4602 Controller parameters in order to run in parallel with grid.
Carry out functional test:
16/09/2017 ON Load test with the grid (50% of nominal load)
Adjustment of DST 4602 parameters in order to stabilized the EDG Load as per set value (ON Load test mode)
Protection relay setting and wiring modification in order to disable protection for 27 and 80U during the stopping EDG (NG 20 enable Input 1
and assigned the Block 1 to disable 27/80U during the stopping)

17/09/2017 Carry out final modification – wiring (replace and arrange the temporary wiring)

Date Activity description

2 of 3
EDG COMMISSIONING
ACTIVITY REPORT
Month of October 2017

Carry out functional test after wiring modification with PGESCo and Owner representatives
18/09/2017 Issue the final documents dossier related to commissioning activities (Commissioning report, Commissioning Test sheet and Commissioning
activity report)

19/09/2017 Site visit – South Helvan (requested by Techint)

20/09/2017 Travel from Egypt to Italy

DATE NAME SIGNATURE


CTM Commissioning Engineer
TECHINT West Damitta Project

3 of 3

You might also like