ACTIVITY REPORT
Month of October 2017
Check the battery and refilling the battery (bank 1 & 2) by electrolyte - Diesel pum B
12/10/2017 Energize the control panel by 240V/440V. Energize the battery charger and preheating system. Disconnect the battery bank n°1 (diesel
pump B). Charge the battery by external charger due to low voltage.
14/10/2017 Diesel pum A - Preparation for aligment (aligment bolts – not availeble on site)
1 of 3
EDG COMMISSIONING
ACTIVITY REPORT
Month of October 2017
Carry out functional test and modification in order to provide additional protection in case of failure signal from under voltage relay (main
voltage presents and inhibit start) – requested by Pegaco.
13/09/2017
Carry out the test after modifications (simulate remote and V3/V4 voltage signal missing – Q3 close and Bus voltage present)
EDG start in auto mode and perform the synchronizing before to close the Generator Breaker)
Carry out functional test and modification in order to provide cooling time after opening of Generator Circuit Breaker (in Auto mode – ON load
Test mode)
14/09/2017
Protection relay setting and wiring modification in order to disable protection for 27 and 80U during the stopping EDG (NG 20 enable Input 1
and assigned the Block 1 to disable 27/80U during the stopping)
17/09/2017 Carry out final modification – wiring (replace and arrange the temporary wiring)
2 of 3
EDG COMMISSIONING
ACTIVITY REPORT
Month of October 2017
Carry out functional test after wiring modification with PGESCo and Owner representatives
18/09/2017 Issue the final documents dossier related to commissioning activities (Commissioning report, Commissioning Test sheet and Commissioning
activity report)