P.O.BOX ____SAUDI ARABIA
Contents
1. SITE CLEARANCE PLAN ...................................................................................................................................2
1.1. SITE CLEARANCE ............................................................................................................................................... 2
12. Power
a. ASRF shall be provided with temporary electricity supply.
b. ASRF shall be responsible for all connection from the power point designated from the
Client and removal on completion all necessary wiring and accessories.
c. In case sources of lighting and power supply is unavailable or inadequate within the Site,
ASRF is responsible for the provision of temporary lighting and power supply at the
locations and in the manner as directed by the Client and submit installation detail and
routing of the electricity supply for the information of the Client prior to commencement of
the installation. The level of light shall be adequate for safety, routine inspections and
detailed inspection of finishes as the works proceeds.
d. The ASRF will disconnect the temporary power once it is no longer needed.
Prior to the start of any excavation works the existing underground facilities will be
investigated, if any, such as pipes, cables, foundations, etc. will be located and carefully
removed to designated location. Areas around the facilities will be cleared and made good .The
major works will be:
The sequence of carrying out the execution will as follows:
a. Levelling of land, surveying and mark up of the various building layouts.
b. Setting up the admin offices, temporary fencing, set up of security, set up waste system
(sewage and domestic waste), office internet and phone system and etc.).
c. Our strategy to construct is to follow the process flow. And then all the auxiliary buildings
and other infrastructures.
d. The steel frame structure will be designed ahead for procurement of materials, preparation
of shop drawings, cutting, welding and fabrication before delivering of completed
components to site for installation work. Installation of steel structures will be carried out
with mobile cranes. Moving in of process equipment will be coordinated with the Building
Structure works.
e. Once the Process buildings floor slabs are completed, mechanical installation will start.
Skids will be installed on the floor slabs. This will be followed by the underground pipes,
pipes supports, within the building.
f. Electrical installation will follow shortly after the skids and pipes started installation.
Normally, about 2 months after mechanical installation start.
20. Discharge
Outfall structure is half buried into the ground. The construction of the structure shall be as per
other water tank. Open cut with berm shall be utilized around the structure with provision for
working space. Base slab shall be cast followed by the wall to form the finished tank.
All of the temporary works materials will be removed and send the designated approved
disposing or dumping ground.