You are on page 1of 12

SITE CLEARANCE PLAN

FEBRUARY 28, 2018

ASRF
P.O.BOX ____SAUDI ARABIA
Contents
1. SITE CLEARANCE PLAN ...................................................................................................................................2
1.1. SITE CLEARANCE ............................................................................................................................................... 2

Site Clearance Plan February 2018 1|P a g e


1. SITE CLEARANCE PLAN

1.1. Site Clearance


The clearance of the site will follow sequentially with the development of the site. Once the temporary
facilities are no longer required they will be cleared away and debris will be immediately transported to
the designated dumping location. The order of execution of the works is as explained below
1. Prior to commencing the construction, construction permit shall be obtained from the local
authority.
2. Pre-construction survey shall be done for the surrounding areas to record the existing
environment before construction. This will include capturing the existing surrounding utilities,
building and infrastructures.
3. Survey the construction site and locate existing utility amenities including water, electricity,
sewerage lines and possible phone lines.
4. Determine the exact boundaries for fencing with the help of the blueprints given by the project
client.
5. Hoarding permit shall be obtained before erecting the site hoarding. This shall include the
permit for the Project Sign Board. The Project sign board will be removed after the completion
of the project
6. Boundary, topographic and hydrographic survey shall be done to get detailed information of
the project site. All areas blocking the surveying will be cleared away
7. Upon approval of the permit, hoarding shall be erected around the project site. Project sign
board shall also be erected at approved location. Signs outside the fence should include
"Construction Work in Progress" and "All Visitors Must Report to Site Office." Signs inside the
fence should introduce the site safety regulations, and give specifications about emergency and
first aid equipment. Hoarding will be removed after the completion of the permanent works.
8. Carry out soil tests on different locations on the site. The tests need to be analyzed by a
geotechnical engineer, an environmental engineer and lab technician. Soil test results can
indicate contamination or possible problems with foundations, excavations and concrete
pouring.
9. Search the site for underground utilities and obstacles such as old wells, excavation shafts,
electrical cables and gas or water channels. Remove obstacles, cover or fill if necessary.

Site Clearance Plan February 2018 2|P a g e


10. Site Office and Accommodation
a. Proposed location of temporary site office shall be located next to the proposed
construction as per allocated and subject to Client approval. It will house the Client's,
Consultants, Contractor and Sub-contractors site office, storage plus all the amenities for
the staff and workers. Figure below shows the layout of a typical site office layout for such
project.
b. Permit shall be obtained for the construction and erection of site facilities from local
authority. Location of the site facilities shall be determine once the site and surrounding
survey has been done and authority advise is obtained. This is important for the
construction activities and logistic not a hindrance to the public.
Site facilities shall include:
a. Site offices with communication facilities
b. Water tanks, if no direct source
c. First aid room
d. Generator sets
e. Toilets (Pre-fab or portable for site use)
f. Workers rest areas with proper facilities for summer
g. Drinking and chilled water
h. Site canteen
i. Material storage and laydown with security measures and protective devices such as
alarms, vehicle tracking systems, manned guarding, CCTV and locks to prevent theft of
construction equipment and materials
j. The accommodation for the laborers shall be as per local requirement and the location shall
be made known once finalized. Laborers shall commute at minimum distance to site to
avoid delay and traffic congestion.
k. Locations for temporary lay down shall be on allocated areas and are subject to approval by
client.
l. All these temporary facilities will be cleared away when they are no longer required.

Site Clearance Plan February 2018 3|P a g e


11. Temporary Works Erection
ASRF shall comply with all regulations concerning temporary works erection.
When necessary or instructed, ASRF shall provide temporary hoarding, fencing, barriers and
other necessary safety precautionary measure to the satisfaction of the Client for protecting the
public and others during the proper execution of the Works. All materials are to be submitted
for approval by the Client prior to commencement of the installation.
In particular, ASRF shall protect the all public areas from damage and dirt while execution the
Works.

12. Power
a. ASRF shall be provided with temporary electricity supply.
b. ASRF shall be responsible for all connection from the power point designated from the
Client and removal on completion all necessary wiring and accessories.
c. In case sources of lighting and power supply is unavailable or inadequate within the Site,
ASRF is responsible for the provision of temporary lighting and power supply at the
locations and in the manner as directed by the Client and submit installation detail and
routing of the electricity supply for the information of the Client prior to commencement of
the installation. The level of light shall be adequate for safety, routine inspections and
detailed inspection of finishes as the works proceeds.
d. The ASRF will disconnect the temporary power once it is no longer needed.

13. Maintenance of Temporary Works


Maintain, alter, adapt and move Temporary Works as necessary. Clear away when no longer
required and make good.

14. Site Access and Material Delivery


a. Our employees and workmen shall observe all rules and regulations of the statutory codes
and regulations, with regard to access to site, security thereof, issuing of passes and the
like.

Site Clearance Plan February 2018 4|P a g e


b. It is the responsibility of ASRF to plan and coordinate with Client and other work packages
contractors (if any) to work out the delivery route and schedule. We shall allow for delivery
time restrictions. Material delivery schedules shall be submitted to and agreed by Client in
advance prior to any deliveries being made.
c. ASRF shall comply with all requirements of the Road and Transport Authority (RTA); obtain
authorization to cross pavements and similar areas. When using public roads for access
purpose, co-operate with RTA and others using such roads to ensure that they are kept free
obstruction at all times and comply with any restriction on access.
d. ASRF shall keep all access clean and should clear away all debris arising from the Works in a
neat and orderly manner.

15. Noise/ Nuisance Mitigation Measures


a. ASRF shall comply with all Regulations concerning the prevention of nuisance arising from
noise, water, smoke, dust, and accumulation of rubbish, mosquito breeding and all other
causes.
b. ASRF shall provide throughout the whole period of the Contract and extended period, if
any, mufflers or other suitable noise suppressors on all pneumatic drills, compressors and
other plant which may cause a noise nuisance to the general public.
c. ASRF shall store, cover or treat all items on the Site, capable of retaining water to prevent
the collection of water in them.
d. ASRF shall provide throughout the construction period an approved central collection point
on the Site for depositing of all empty cans, oil drums, packings and other receptacles
capable of holding water and for the regular collection and removal of such articles from
the site.
e. ASRF shall not burn debris, or any other matter on the Site.

16. Site Constraint


Work activities such as excavation shall confine within the boundary limits. For any activities
such as material delivery, movement of construction vehicles and etc., ASRF shall take every
precaution necessary to cause minimum of nuisance, disturbance or inconvenience to the
nearby premises.

Site Clearance Plan February 2018 5|P a g e


17. Construction plan with clearance strategy
Site surveying works, subsoil investigations, marine investigation, will be conducted. Site
preparation and earth works including all soil improvements if required will also be carried out.

Prior to the start of any excavation works the existing underground facilities will be
investigated, if any, such as pipes, cables, foundations, etc. will be located and carefully
removed to designated location. Areas around the facilities will be cleared and made good .The
major works will be:
The sequence of carrying out the execution will as follows:
a. Levelling of land, surveying and mark up of the various building layouts.
b. Setting up the admin offices, temporary fencing, set up of security, set up waste system
(sewage and domestic waste), office internet and phone system and etc.).
c. Our strategy to construct is to follow the process flow. And then all the auxiliary buildings
and other infrastructures.
d. The steel frame structure will be designed ahead for procurement of materials, preparation
of shop drawings, cutting, welding and fabrication before delivering of completed
components to site for installation work. Installation of steel structures will be carried out
with mobile cranes. Moving in of process equipment will be coordinated with the Building
Structure works.
e. Once the Process buildings floor slabs are completed, mechanical installation will start.
Skids will be installed on the floor slabs. This will be followed by the underground pipes,
pipes supports, within the building.
f. Electrical installation will follow shortly after the skids and pipes started installation.
Normally, about 2 months after mechanical installation start.

18. General Approach


The construction staging of the project will involve activities on the sites with concentration of
works during day possessions. While the main construction method is discussed here, detailed
method statement for each activity shall be submitted for approval prior to commencement of
any works. The number machineries to be used during the activities shall be identified upon
starting of the works. Typical work sequence of the construction.

Site Clearance Plan February 2018 6|P a g e


Before the commencement of any works, approved construction drawings and relevant permit
shall be obtained from the authorities. The main activities involved for the construction shall be
a. Site Clearing Works
Prior to the commencement of works, the setting out shall be carried out by the qualified
Surveyor to ensure the platform that has been handed over at the correct levels.

b. Excavation and Underground Services


Once the surveying of the building (i.e. Building Control Points) is executed by the surveyor
as specified in the endorsed Pre-computation plan, the proposed corners of the buildings
and boundary walls are pegged.
i. Excavation, fills and compaction
Once the pegging is in place, cement or plaster dust is sprinkled beneath the perimeter
building lines to act as a guide for trenching and excavating. Platform and Floor finish
level will be based on the TBM as the reference / localized datum.
The work shall be excavated to the dimensions as shown on the Construction
Drawings. Sides of excavation will endure a slight oversized trenching to allow for
installation of side timber formwork (including its bracings mechanism) or blocks.
Excavation for structures would be to the lines and grades shown or as required to
accomplish the construction. Maintain a tolerance of +/-25mm beneath plain concrete
foundations and +/-15mm beneath reinforced concrete foundations and ground
bearing slabs.
ii. Limits of Excavation
Excavate to the depths and widths, as shown. Allow for forms, working space, granular
base, and finish topsoil as shown or required. No excavation would be carried out for
raft and slabs deeper then elevation shown unless otherwise required achieving a
minimum structural fill depth. In excavation for foundation, bottom of excavation shall
not be disturbed. Manually excavate for the last 200mm to final level. All excavations
shall be kept clear of water arising from any cause. Barricade open excavations and
provide warning tapes and lights.
iii. Excavation for Trenches

Site Clearance Plan February 2018 7|P a g e


Provide required clearance on both side for ample working room and other materials
(pipe or conduit). Excavate trenches to depths indicated and required. Do not backfill
trenches until test and inspection are carried out.
c. Backfilling and Compaction
Backfilling of earth around raft would be carried out in layers of using plate compactor (with
vibration). Place backfill material free of roots, organic matter, trash, and rocks larger than
4-inch diameter.

d. Removal of extra excavated materials


Excavated material that are of no use to the site will be remove to the designated dumping
ground.
e. Structural Steel Works
Structural steel frame shall be erected from one end while the installation skids and pipe
racks commence on the other end. For safety reasons, one activity will stop when they
meet at one point. This will speed up the construction works. Such sequence will be
outlined in detailed prior to starting the works. Detailed method statement shall be
supplied upon request prior to construction works for Client's review. Structural steel
erection shall involve:
i. Installation of hold-down bolts
ii. Erection of vertical members
iii. Levelling and Grouting of base plate
iv. Erection of main frame
v. Installation of braced members
vi. Installation of purloins and side rails
vii. Fixing of roof and cladding
viii. Installation of crane including corbels and crane beams
ix. Painting of the steel elements

19. Seawater Intake

Site Clearance Plan February 2018 8|P a g e


Seawater intake is the integral part of the construction works. This part of the works often takes
longer and more challenging than others. The construction of the intake structure shall be
outlined as below.
The following measures shall be considered when constructing the deep intake structure:
a. Silt curtain will be installed prior to any dredging / excavation / marine works as protective
barrier to control pollution caused by suspended sediments, such as silt, soil or stone dust.
b. To engage qualified Professionals to design and review the temporary earth retaining
structure. Possible cases of ground heaving and effects to the adjacent structure will be
addressed in the design prior to submission for approval. Close monitoring and supervision
shall be done by qualified engineers / site supervisors during construction to make sure that
acceptable limit as per local requirement for temporary excavation works are followed.
c. Erosion Control Measures (ECM) will be designed and shall be in-place before the
construction start. Compliance to the Professional Engineers designed ECM is a must
throughout the construction.
d. Safety shall be observed at all time during any construction activities.
Authority Submission
Prior to the construction of the intake, approval from related agencies shall be obtained for the
permanent works, temporary works and marine works.
Preliminary Works
a. Proposed location and alignment of the Intake Chamber will be set out by licensed
surveyor. This will be done using the approved pre-computation plan. With this setting out,
preliminary preparation works can be carried out.
b. ECM shall be in place to control siltation to nearby drain / sea.
c. Preliminary works also includes instrumentation works that will be carried out in the vicinity
to monitor the ground movement with initial reading taken and submitted to relevant
authority and consultants.
Temporary and RC Construction Sequence
Bore Piling Work
a. Setting out of Bore Piles by licensed surveyor, with bore piles carry out by Bored Piling
contractor.
b. Unsuitable earth from the boring shall be disposed to approve off-site dumping locations.
No earth shall be directed to sea.

Site Clearance Plan February 2018 9|P a g e


c. Bore Piles Load Test to be determined by Professional Engineer, to comply with local
requirement.
Temporary Work (ERSS-Sheet Piling)
a. Submission of temporary work approved by local authority.
b. Setting out of Sheet Piling location by licensed surveyor.
c. Install monitoring instrument prior to sheet piling works and initial readings shall be
recorded before commencing sheet piling works.
d. Partial Removal of rock revetment for Sheet Piles affected by landside location.
e. Sheet Piling Work to commence on the land side first.
f. Sheet Piling Work to commence on the offshore location at a plan date.
g. Upon completion of Sheet Piling Work,
h. Upon approval from Engineer, monitoring instrument will be initialized, before proceeding
with 1st layer excavation work.
i. Excavate to 1st layer strut, and install 1st layer strut / waler
j. Upon approval from Engineer, excavate 2nd layer strut and install 2nd layer waler / strut /
runner beam.
k. Continue to monitor the readings of instrumentation and report to Engineer.
l. Repeat until the last layer of strut is installed.
m. Sufficient temporary pumps will be made available to remove seepage from the sea, if
required.
n. The construction of RC work and dismantling of strut will follow the following sequences
i. Lean concrete of formation level in preparation for base slab construction work.
ii. Setting out of position of the intake chamber carry out by licensed surveyor.
iii. Hack off bore piles to cut off level.
iv. Install Rebar and formwork, and cast base slab providing wall starter bar.
v. Cast wall kicker.
vi. Dismantle last layer strut/waler after obtaining Engineer's approval.
vii. Erect perimeter wall rebar and formwork, and cast wall in approximately 3m height.
viii. This is followed by casting of internal wall progressively.
ix. Dismantle perimeter wall formwork after concrete gain sufficient strength.
x. Backfill sand between sheet pile and perimeter wall in layers of approximately 500mm.
xi. Compact each layer of sand prior to backfilling to required height.

Site Clearance Plan February 2018 10 | P a g e


xii. Item 6 to 9 is repeated until, top slab is cast
xiii. Remove Sheet Pile with the approval of Engineer
xiv. Reinstate the shoreline to the satisfaction of the relevant authority.

20. Discharge
Outfall structure is half buried into the ground. The construction of the structure shall be as per
other water tank. Open cut with berm shall be utilized around the structure with provision for
working space. Base slab shall be cast followed by the wall to form the finished tank.
All of the temporary works materials will be removed and send the designated approved
disposing or dumping ground.

Site Clearance Plan February 2018 11 | P a g e

You might also like