ID Task Name Duration Start FinishSep 24, '17 Oct 8, '17 Oct 22, '17 Nov 5, '17 Nov

Start FinishSep 24, '17 Oct 8, '17 Oct 22, '17 Nov 5, '17 Nov 19, '17 Dec 3, '17 Dec 17, '17 Dec 31, '17 Jan 14, '18 Jan 28, '18 Feb 11, '18 Feb 25, '18 Mar 11, '18 Mar 25, '18 Apr 8, '18 Apr 22, '18 May 6, '18 May 20, '18 Jun 3, '18
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T
1 A.A. Decentralised Wastewater Management System Pilot 1397 Thu 8/20/15 Sun 6/16/19
2 Project for Koye
1 Project Feche Condominium Site
commencement 149 days?
days? Thu 8/20/15 Fri 1/15/16
3 1.1 Signing Contract 1 day? Thu 8/20/15 Thu 8/20/15
4 1.2 site hand over 1 day? Fri 9/25/15 Fri 9/25/15
5 1.3 Opening L/C 121 days Thu 9/17/15 Fri 1/15/16
6 2 Mobilization 259 days Sat 9/5/15 Fri 5/20/16
7 2.1 Staff Mobilization,Organization Establishment 20 days Sat 9/5/15 Thu 9/24/15
8 2.2 Office & Vehicles 10 days Sat 9/5/15 Mon 9/14/15
9 2.3 Camp construction 36 days Wed 11/25/15 Wed 12/30/15
10 2.4 Construction equipment & staff mobilization 36 days Wed 11/25/15 Wed 12/30/15
11 2.5 Land acquisition(disposal,quarry,workshop) 45 days Sat 12/19/15 Mon 2/1/16
12 2.6 Access road construction 19 days Mon 5/2/16 Fri 5/20/16
13 3 Shop Drawings Preparation & Submission 204 days Thu 8/20/15 Thu 3/10/16
14 3.1 topography mapping 12 days Sat 9/26/15 Wed 10/7/15
15 3.2 Geotechnical Investigation 30 days Thu 8/20/15 Fri 9/18/15
16 3.2 Submission of Shop Drawings by Step 87 days Thu 12/10/15 Sat 3/5/16
30 3.3 Approval of Shop Drawings by Step 83 days Sat 12/19/15 Thu 3/10/16
44 4 L/C Equpeiments & Materials Procurement and 677 days? Mon 12/21/15 Fri 10/27/17
45 Acceptance
4.1 Materials Approvel Sheet Approved 71 days Mon 12/21/15 Mon 2/29/16
46 4.2 Factory manufacture 634 days? Tue 2/2/16 Fri 10/27/17
47 4.2.1 First shipment including (manufacturing, land 109 days Tue 2/2/16 Fri 5/20/16
48 transportation,
4.2.2 port arrivel
Second shipment etc.) (manufacturing, land
including 395 days Thu 3/10/16 Sat 4/8/17
49 transportation,
4.2.3 port arrivel
Third shipment etc.)(manufacturing, land
including 458 days Thu 3/10/16 Sat 6/10/17
50 transportation,
4.2.4 port arrivel
Fourth shipment etc.) (manufacturing, land
including 99 days? Fri 3/24/17 Fri 6/30/17
51 transportation, port arrivel etc.)
4.3 Factory Inspection 387 days Sun 5/8/16 Mon 5/29/17
52 4.4 Transport & Site Acceptance 476 days Sat 7/9/16 Fri 10/27/17
53 4.4.1 First shipment (shipping, land transportation, 50 days Sat 7/9/16 Sat 8/27/16
54 site
4.4.2arrivel
Second & acceptance etc.)
shipment (shipping, land 50 days Sun 4/9/17 Sun 5/28/17
55 transportation, site arrivel
4.4.3 Third shipment & acceptance
(shipping, etc.)
land transportation, 50 days Sun 6/11/17 Sun 7/30/17
56 site arrivel & acceptance etc.)
4.4.3 Fourth shipment (shipping, land transportation, 118 days Sun 7/2/17 Fri 10/27/17
57 site arrivelcompleted
materials & acceptance etc.) 0 days Fri 6/30/17 Fri 6/30/17
58 5 Civil Constructions 800 days? Tue 1/12/16 Wed 3/21/18
59 Excavation and Earth work 787 days Tue 1/12/16 Thu 3/8/18
60 Excavation and cartaway 480 days Tue 1/12/16 Sun 12/31/17
61 Backfill work 230 days Sun 1/22/17 Thu 3/8/18
62 Biological Treatment Unit (BTU) 751 days? Tue 3/1/16 Wed 3/21/18
63 BT-Section 1,2,3 & 4 Lean concrete, base slab and 239 days Tue 3/1/16 Tue 10/25/16
64 walls
BT-Section4-North wall-3rd stage 26 days? Wed 10/26/16 Sun 11/20/16
65 BT-Section2-South wall-3rd stage 15 days Tue 11/1/16 Tue 11/15/16
66 BT-Section1-1st wall-3rd stage 5 days? Thu 10/27/16 Mon 10/31/16
67 BT-Section1-2nd wall-3rd stage 5 days? Wed 11/16/16 Sun 11/20/16
68 BT-Section3-East wall-2nd stage 13 days Thu 11/24/16 Tue 12/6/16
69 BT-Section4-South wall-1st stage 12 days Tue 11/15/16 Sat 11/26/16
70 BT-Section3-West wall-2nd stage 12 days Wed 11/30/16 Sun 12/11/16
71 BT-Section4-South wall-2nd stage 12 days Wed 12/7/16 Sun 12/18/16
72 BT-Section3-East wall-3rd stage 14 days Sun 12/11/16 Sat 12/24/16
73 BT-Section3-West wall-3rd stage 14 days Wed 12/14/16 Tue 12/27/16
74 BT-Section4-South wall-3rd stage 14 days Sun 12/25/16 Sat 1/7/17
75 BT-Section5-lean concrete 2 days? Sun 1/8/17 Mon 1/9/17
76 BT-Section5-base slab 16 days Tue 1/10/17 Wed 1/25/17
77 BT-Section5-1st stage wall 25 days Fri 1/27/17 Mon 2/20/17
78 BT-Section5-2nd stage wall 25 days Wed 2/22/17 Sat 3/18/17
79 BT-Section5-3rd time wall 32 days Mon 3/20/17 Thu 4/20/17
80 Finishing works 257 days Thu 1/12/17 Wed 3/21/18
81 Final Clarification Tank (FCT) 655 days Sun 6/5/16 Wed 3/21/18
82 FCT-1 & 2 base slabs 145 days Sun 6/5/16 Thu 10/27/16
83 FCT2-1st stage wall 12 days Fri 10/28/16 Tue 11/8/16
84 FCT1-2nd stage wall 25 days Wed 11/9/16 Sat 12/3/16
85 FCT2-2nd stage wall 24 days Sun 12/4/16 Tue 12/27/16
86 Finishing works, Stair and Shaft construction 210 days Fri 12/9/16 Wed 3/21/18
87 Control Building (CB) 533 days Wed 10/5/16 Wed 3/21/18
88 Control building footing pad & foundation column 27 days Wed 10/5/16 Mon 10/31/16
89 Control building 1st column 7 days Tue 11/1/16 Mon 11/7/16
90 Control building beam and slab 20 days Wed 11/9/16 Mon 11/28/16
91 Roof cover construction 21 days Fri 12/9/16 Thu 12/29/16
92 Block wal construction 65 days Mon 1/30/17 Tue 4/4/17
93 Finishing work 225 days Wed 4/26/17 Wed 3/21/18
94 Door and windows 35 days Sat 5/20/17 Fri 6/23/17
95 installations 20 days Sat 11/12/16 Sat 7/22/17
96 Lifting Pump Station (LPS) 574 days Mon 5/2/16 Sun 11/26/17
97 LPS base slab and first lift wall 206 days Mon 5/2/16 Wed 11/23/16
98 LPS 2nd time wall 10 days Sun 12/4/16 Tue 12/13/16
99 LPS top slab 12 days Sat 12/17/16 Wed 12/28/16
100 Finishing work 82 days Sun 10/9/16 Sun 11/26/17
101 Primary Clarification Tank (PCT) 654 days? Mon 6/6/16 Wed 3/21/18
102 PCT 1 & 2 base slabs 195 days Mon 6/6/16 Sat 12/17/16
103 PCT2-1st stage wall 11 days? Wed 12/28/16 Sat 1/7/17
104 PCT2-2nd stage wall 30 days Sun 1/8/17 Mon 2/6/17
105 Finishing works, Stair and Shaft construction 157 days Sun 10/9/16 Wed 3/21/18
106 Biological Sludge Gravity Thickener and Aerated 675 days Mon 5/16/16 Wed 3/21/18
107 Mixing
BSGT Sludge
and AMSTTankbase slab and wall 217 days Mon 5/16/16 Sun 12/18/16
108 BSGT-1st stage wall 13 days Thu 12/29/16 Tue 1/10/17
109 BSGT-2nd stage wall 35 days Fri 1/13/17 Thu 2/16/17
110 Finishing work and Stair construction 180 days Mon 11/14/16 Wed 3/21/18
111 Sludge Dewatering Building (SDB) 654 days? Mon 6/6/16 Wed 3/21/18
112 SDB footing pad, foundation column and Grade beam 193 days Mon 6/6/16 Thu 12/15/16
113 SDB-1st floor column 6 days? Mon 12/26/16 Sat 12/31/16
114 SDB-1st floor beam and slab 12 days? Mon 1/2/17 Fri 1/13/17
115 SDB-2nd floor column 7 days? Sun 1/15/17 Sat 1/21/17
116 SDB-2nd floor beam 9 days? Mon 1/23/17 Tue 1/31/17
117 Roof truss and cover construction 42 days Wed 2/1/17 Tue 3/14/17
118 Block wal construction 45 days Wed 3/15/17 Fri 4/28/17
119 Finishing work 212 days Sat 5/20/17 Wed 3/21/18
120 Door and windows 21 days Wed 6/7/17 Tue 6/27/17
121 installations 70 days Thu 1/5/17 Wed 7/5/17
122 Chlorination tank 668 days Mon 5/23/16 Wed 3/21/18
123 CT base slab, wall and walkway slab 168 days Mon 5/23/16 Sun 11/6/16
124 Finishing work 200 days Sat 12/17/16 Wed 3/21/18
125 Chemical Building (CB) 541 days Tue 9/27/16 Wed 3/21/18
126 CB- footing pad and foundation column 113 days Tue 9/27/16 Tue 1/17/17
127 CB-ground beam and slab 9 days Wed 1/25/17 Thu 2/2/17
128 CB-1st column 10 days Fri 2/3/17 Sun 2/12/17
129 CB-top beam 18 days Tue 2/14/17 Fri 3/3/17
130 Roof truss and cover construction 28 days Sat 3/4/17 Fri 3/31/17
131 Block wal construction 21 days Sat 4/8/17 Fri 4/28/17
132 Finishing work 205 days Sat 5/20/17 Wed 3/21/18
133 Door and windows 21 days Sat 6/3/17 Fri 6/23/17
134 installations 60 days Sat 1/28/17 Thu 6/29/17
135 Blower and Energy Building (BEB) 445 days Sun 1/1/17 Wed 3/21/18
136 BB+EB-footing 28 days Sun 1/1/17 Sat 1/28/17
137 BB+EB-ground beam and column 15 days Wed 2/1/17 Wed 2/15/17
138 BB+EB-1st floor column 12 days Fri 2/17/17 Tue 2/28/17
139 BB+EB-top beam 21 days Wed 3/1/17 Tue 3/21/17
140 Roof truss and cover construction 21 days Wed 3/22/17 Tue 4/11/17
141 Block wal construction 28 days Wed 4/12/17 Tue 5/9/17
142 Finishing work 180 days Wed 5/31/17 Wed 3/21/18
143 Door and windows 21 days Tue 6/13/17 Mon 7/3/17
144 installations 70 days Sat 2/4/17 Sun 7/9/17
145 Pretreatment Unit/Self Cleaning Screening/ 443 days Tue 1/3/17 Wed 3/21/18
146 Pre-TB- footing 14 days Tue 1/3/17 Mon 1/16/17
147 Pre-TB- ground beam and column 14 days Tue 1/17/17 Mon 1/30/17
148 Pre-TB- 1st floor column and slab 21 days Tue 1/31/17 Mon 2/20/17
149 Pre-TB- 2nd floor column and slab 21 days Tue 2/21/17 Mon 3/13/17
150 Block wal construction 28 days Tue 4/4/17 Mon 5/1/17
151 Finishing work 176 days Tue 5/23/17 Wed 3/21/18
152 Door and windows 21 days Tue 5/30/17 Mon 6/19/17
153 installations 50 days Tue 1/31/17 Tue 6/27/17
154 Shade construction 160.5 days Tue 4/4/17 Fri 11/10/17
155 Distribution Chamber and Primary Sludge Pumping 419 days Fri 1/27/17 Wed 3/21/18
156 Station
DCPSPS-base slab 16 days Fri 1/27/17 Sat 2/11/17
157 DCPSPS-1st stage wall 14 days Sun 2/12/17 Sat 2/25/17
158 DCPSPS-2nd stage wall 14 days Sun 2/26/17 Sat 3/11/17
159 Finishing work 168 days Sun 4/2/17 Wed 3/21/18
160 Guard House 451 days Mon 12/26/16 Wed 3/21/18
161 GH-footing 8 days Mon 12/26/16 Mon 1/2/17
162 GH-ground beam and column 32 days Tue 1/3/17 Fri 2/3/17
163 GH-1st floor beam and column 14 days Sat 2/4/17 Fri 2/17/17
164 Roof truss and cover construction 21 days Sat 3/11/17 Fri 3/31/17
165 Block wal construction 15 days Sat 4/1/17 Sat 4/15/17
166 Finishing work 187 days Sun 5/7/17 Wed 3/21/18
167 Door and windows 21 days Sun 5/14/17 Sat 6/3/17
168 installations 45 days Fri 1/6/17 Tue 6/6/17
169 Store and Warehouse 38 days Mon 2/12/18 Wed 3/21/18
170 Footing pad, foundation column and masonry wall 7 days Mon 2/12/18 Sun 2/18/18
171 Ground beam and slab 12 days Mon 2/19/18 Wed 3/7/18
172 Column 3 days Fri 2/23/18 Sun 2/25/18
173 Top beam 5 days Thu 3/8/18 Mon 3/12/18
174 Roof truss and cover construction 4 days Thu 3/15/18 Sun 3/18/18
175 Block wal construction 5 days Mon 2/26/18 Fri 3/2/18
176 Finishing work 15 days Wed 3/7/18 Wed 3/21/18
177 Door and windows 3 days Sun 3/11/18 Tue 3/13/18
178 installations 7 days Wed 3/7/18 Tue 3/13/18
179 Pavement 3 days Wed 3/14/18 Fri 3/16/18
180 Compound work 353 days Mon 4/3/17 Wed 3/21/18
181 Excavation and earthwork 65 days Mon 4/3/17 Tue 6/6/17
182 Asphalt work 30 days Tue 2/20/18 Wed 3/21/18
183 Drainage and water supply work 131 days Wed 7/26/17 Mon 2/12/18
184 Manholes construction 144 days Wed 6/7/17 Mon 2/12/18
185 Fence and gate construction 102 days Wed 6/21/17 Wed 3/21/18
186 Water tightness test for all water retaining structures 232 days Fri 3/24/17 Fri 11/10/17
187 PSGT, BSGT, PSST and AMST tank 85 days Fri 3/24/17 Fri 6/16/17
188 PCT 1 & 2 tank including collection pit 40 days Mon 5/8/17 Fri 6/16/17
189 FCT 1 &2 tank including collection pit 119 days Sat 6/17/17 Fri 10/13/17
190 Biological Treatment Unit 48 days Sun 9/24/17 Fri 11/10/17
191 Lifting Pump Station 20 days Sat 6/17/17 Thu 7/6/17
192 Chlorination tank and distribution chamber 79 days Fri 7/7/17 Sat 9/23/17
193 6 Installations of EM Equipments 312 days Sat 5/20/17 Tue 3/27/18
194 6.1 Primary Sludge Gravity Tank 155 days Mon 9/18/17 Mon 2/19/18
195 6.2 Coarse Screen & Lift Pump Station Unit 155 days Mon 9/18/17 Mon 2/19/18
196 6.3 Primary Treatment Unit 140 days Tue 10/3/17 Mon 2/19/18
197 6.4 Biological Treatment Unit 284 days Mon 5/22/17 Thu 3/1/18
198 6.5 Final Clarification Tank 140 days Tue 10/3/17 Mon 2/19/18
199 6.6 Sludge Stabilization Tank 165 days Mon 9/18/17 Thu 3/1/18
200 6.7 Sludge Dewatering Building 190 days Wed 8/30/17 Wed 3/7/18
201 6.8 Tertiary Treatment 190 days Wed 8/30/17 Wed 3/7/18
202 6.9 laboratory 185 days Mon 9/4/17 Wed 3/7/18
203 6.10 Compound work 247 days Mon 5/22/17 Wed 3/7/18
204 6.11 PLC & ELC 248 days Sat 5/20/17 Wed 3/7/18
205 6.12 Unit Commissioning & PLC Commissioning 21 days Wed 3/7/18 Tue 3/27/18
206 7 Whole System Commissioning & Running 40 days Tue 3/13/18 Sat 4/21/18
207 7.1 Test and Acceptance 40 days Tue 3/13/18 Sat 4/21/18
208 8 Completion and Hand-over 215 days Sun 4/22/18 Thu 11/22/18
209 8.1 Whole Works Acceptance 30 days Sun 4/22/18 Mon 5/21/18
210 8.2 Issuing Taking Over Certificate 5 days Tue 5/22/18 Sat 5/26/18 5/26
211 8.3 Running & Training 180 days Sun 5/27/18 Thu 11/22/18
212 8.4 As-built drawing and EM test Repoprt Submission 22 days Tue 4/24/18 Tue 5/15/18
213 8.5 Retention Release (2.5%) 14 days Wed 5/16/18 Tue 5/29/18
214 8.6 Demobilization 3 days Thu 5/24/18 Sat 5/26/18
215 9 Defects Notification Period 386 days Sun 5/27/18 Sun 6/16/19
216 9.1 365 days as Defects Notification Period 365 days Sun 5/27/18 Sun 5/26/19
217 9.2 Issuing Performance Certificate 7 days Mon 5/27/19 Sun 6/2/19
218 9.3 Retention Release(2.5%) and final settlement 14 days Mon 6/3/19 Sun 6/16/19

Task Summary External Milestone Manual Task Manual Summary External Tasks Deadline
Project: KKFCS-WWTP3 Revised Wo
Split Project Summary Inactive Milestone Duration-only Start-only External Milestone
Date: 22 January 2018
Milestone External Tasks Inactive Summary Manual Summary Rollup Finish-only Progress

Remark: Compound road construction is total dependent on Fence construction on south side Page 1