Rate Analysis: what is it and what’s the correct procedure for building up a unit
rate

Rate Analysis: what is it and what’s the correct procedure for


building up a unit rate

Rate Analysis: what is it and what’s the correct


procedure for building up a unit rate
Rate Analysis can be defined as the analytical study (qualitative and quantitative) that leads to
the definition of a new unit rate referring to a given job or work type, by identifying its basic
elements.

But when does a Rate Analysis become necessary?


In normal practice, a quantity surveyor uses the price list items acquired from a regional or any
other official Price Book. But what if a specific work description isn’t available? Well in these
cases, we need to resort to “building up” the unit rate by identifying the elementary resources as
components of the analysed rate.

How is a new unit rate defined?


The starting point to define the new unit rate, is to run a careful analysis of the elements and
resources that build up to form the new work item.
The elementary components, or resources, are generally the following:

• workforce
• materials
• hired equipment
• overheads
• company profits

Labor
The cost of labor is defined by the type of workers (specialised, qualified operators) and the
hours of work necessary per quantity unit.

Materials
To define the cost of the necessary materials, you need to determine the following:

• the purchase price


• on-site transport costs
• unloading
• stacking and storage
• waste (an excess percentage of unwanted material due to the production processes)

Rentals
Meaning the rented equipment or machinery that may be of 2 main types:

• “operated equipment”: this means that the rental cost is inclusive of both the equipment, or
machinery, and the necessary operational labor (eg. a crane and the crane operator).
The operated equipment rental includes the labor costs required for its use, the fuel, lubricants,
insurance costs and maintenance.
• “without operator”: in this case the equipment or machinery is rented with the operator. This
kind of freight cost does not include the cost due to labor required for its use. Neither does it
take into account the cost for fuel, lubricants or maintenance.

Overheads
Overheads are the costs incurred in an indirect way and not directly related to the works or to
the construction site.
On average they are quantifiable with a fixed percentage of between 13% and 17% – (may vary
from zone to zone).
Overhead costs include the following items:

• Administrative and Management


• site technical systems
• surveys and audits
• temporary occupations and security arrangements
• etc.

Company Profits
Known as the expected revenue for the company and is typically 10% of the costs incurred.

Rate Analysis: The advantages of using a software


In this section we’ll see how to set up a rate analysis using a construction estimating program,
PriMus by ACCA software.

The software allows you to dynamically calculate the rate of a given work item.

PriMus, in fact, allows you to easily and dynamically build up a new rate by means of a rate
analysis feature and therefore calculate the total unit rate from elementary resources or even
from other structured rates whose final rate is the result of a combination of several sub-
resources. To determine the rate of an item, the following may be used:

• primary costs
• compounds costs
• data from price lists
• data from other rate analysis items and references
The Rate Analysis document can also be very useful for the building company in the preparation
of tenders or in setting up the site, but also for the surveyor who needs to draft a project plan of
works or follow the works on-site.

PriMus can also determine the “Site Requirements” through a quantitative evaluation of those
elementary items (materials, human resources, equipment, etc.) needed for the project.

This aspect may be different from country to country and for this reason, where in Brazil, the
“Site Requirements” is replaced by the so called “ABC analysis”, this has been integrated into
the software with the ‘ABC curve”, thus adapting to local legislation. One of the most obvious
advantages of using a software to perform a Rate Analysis is the dynamic management of price
variations. With the software, in fact, we can change the unit rate of an element used in a rate
analysis and notice that the any analyzed rates that contain the varied rate, are all updated
throughout the entire construction estimate document.

The Rate Analysis module configuration allows you to set the values for Overheads, Company
Profits, etc).

Configuration of the Rate Analysis Module in PriMus

The analysis elements can be acquired from other reference documents too such as price
books, other price lists, estimates, etc. In the numeric fields, you can:

• insert quantities and amounts, algebraic formulas


• acquire values from tables
• use specific variables

Use of specific variables can be very useful in order to automatically acquire values from other
elements used in the same rate analysis. In this case, all price list item data is seamlessly
updated.
An example of how variables are used in PriMus

A detail of the numeric fields in PriMus

For each item, the software also allows the user to customise the data settings so as to obtain
a useful amounts summary to print as a Rate Analysis report, a Site Materials Requirements
report (with or without the unit rates) and a construction estimate.
Organisation of an on-screen data and amounts summary in PriMus

Click here to learn more about PriMus, the Construction Estimating software

By Newsroom | March 20th, 2017 | Focus | 0 Comments

Share This Story, Choose Your Platform!


     

Related Posts
Languages

Deutsch
Español
Français
Português

Search ... 

Recent Posts

 Classical and modern townhouses. The Lafayette Park project by Mies Van der Rohe

 The 7 dimensions of the BIM methodology

 Townhouses drawing plans with Area Views, 3D BIM Models and CAD resources

 Minecraft trains next generation of BIM managers

 Alvar Aalto’s Viipuri Library project with a BIM software

Categories

 BIM Projects

 Concepts

 Focus

 News

 Problem Solving
 Tech Research

 Tools and Functions

 Uncategorized

Archives

 May 2018

 April 2018

 March 2018

 February 2018

 January 2018

 December 2017

 November 2017

 October 2017

 September 2017

 August 2017

 July 2017

 June 2017

 May 2017

 April 2017

 March 2017

 February 2017
Find us on Facebook

ACCA software S.p.A.

Contrada Rosole 13 - 83043

BAGNOLI IRPINO (AV) - Italy