Professional Documents
Culture Documents
Submitted By:
KKATT
Consult
Consultancy Services for the Resettlement Houses Design Review and KKATT
Construction Supervision Consult
TABLE OF CONTENTS
EXECUTIVE SUMMARY..........................................................................................................................................5
1.0 INTRODUCTION....................................................................................................... 7
1.1 Project background and details...............................................................................................................7
1.2 Project Location......................................................................................................................................7
1.3 Topography, Vegetation and Main Economic Activity..............................................................................8
1.4 Land scape and acreage of Project sites................................................................................................8
1.5 Scope of the Works.................................................................................................................................8
2.0 STATUS OF MOBILISATION..................................................................................... 9
2.1 Consultant’s Mobilisation........................................................................................................................9
2.1.1 Consultants Personnel................................................................................................................................9
2.1.2 Facilities for the Engineer............................................................................................................................9
2.2 Contractor’s Mobilisation.........................................................................................................................9
2.2.1 Site Establishment.......................................................................................................................................9
2.2.2 Contractor’s personnel................................................................................................................................9
2.2.3 Plant and Equipment...................................................................................................................................9
2.3 Materials on site....................................................................................................................................10
3.0 PROGRESS OF WORKS......................................................................................... 11
3.1 Correspondances..................................................................................................................................11
3.2 Project Meetings....................................................................................................................................11
3.3 Works programme.................................................................................................................................12
3.4 Physical progress..................................................................................................................................12
3.5 Financial Progress................................................................................................................................13
3.6 Contractor’s work program versus actual progress..............................................................................13
3.7 Rainfall records.....................................................................................................................................13
4.0 FINANCIAL STATUS............................................................................................... 14
4.1 Payments to the Consultant..................................................................................................................14
4.2 Payment to the Contractor....................................................................................................................14
5.0 ENVIRONMENT AND SOCIAL MANAGEMENT PLAN...............................................15
5.1 Environmental Management plan.........................................................................................................15
5.2 Social Impact.........................................................................................................................................16
5.3 Occupational Health and Safety Management.....................................................................................17
6.0 CHALLENGES AND SOLUTIONS............................................................................ 19
6.1 Quality Issues........................................................................................................................................19
6.2 Safety Issues.........................................................................................................................................19
6.3 Management Issues..............................................................................................................................19
7.0 WORK PLAN FOR NOVEMBER AND RESOURCES REQUIRED..............................20
APPENDIX........................................................................................................................ 21
A-1 PROGRESS PHOTOGRAPHS.............................................................................................................21
A-2 SITE INSTRUCTIONS.....................................................................................................................................24
List of Tables
List of Figures
List of Abbreviations
EXECUTIVE SUMMARY
CNOOC Uganda Limited is the operator of the Kingfisher Development Area (KDA) located in Buhuka
Parish, Kyangwali Sub-county, Hoima District. The Kingfisher oil field is approximately 300kms from
Kampala and 100 kms from Hoima town south of Lake Albert.
For this assignment, CNOOC has appointed KKATT Consult Limited to carry out the Design Review
and Construction Supervision of the resettlement houses for a duration of six (6) months.
The Consultant during this phase is the Company’s Representative on site. Activities carried out during
the Construction supervision phase ensure that the Contractor follows all the Quality, Health, Safety
and Environment plans put in place to deliver works with in the contract duration.
From the Construction supervision, project progress and challenges are tabulated in Table 1-1 below:
1.0 INTRODUCTION
CNOOC Uganda Limited is the Operator of the Kingfisher Development Area located in Buhuka Parish,
Kyangwali Sub-county, Hoima District. The Kingfisher oil field is approximately 300kms from Kampala
and 100 kms from Hoima town south of Lake Albert. CNOOC through its development phase of the oil
and gas sector has acquired land and resources to design and construct five (5) resettlement houses in
Kyangwali for five (5) physically displaced households. Each household will have a main house, kitchen
and latrine.
CNOOC through its continued development phase of the oil and gas sector has acquired land and
resources to further design and construct five (5) resettlement houses in King fisher region.
For this assignment, CNOOC has appointed KKATT Consult Limited to carry out the Design Review
and Construction Supervision of the resettlement houses for a duration of twelve (12) months, 6 months
defects liability period inclusive. Tabulated below (Table 1.1) are the details of the appointment:
Two different routes can be used to access the sites and these are from Hoima town:
Via the Hoima – Kaiso Tonya road, which is approximately 100Km to the Project Site;
Via Kabwoya – Buhuka, which is approximately 88Km, and this is the preferred route.
Lake Albert
Lake Victoria
Vegetation in this region is characterised by open grassland with mostly scattered thickets and very
scattered trees. Fishing and cattle grazing are the main economic activities within the Project areas.
Site 1 area was confirmed to be 0.445 acres, approximately 1800 sqm for the four (4) houses. Each of
the houses occupies a space of approximately 0.11125 acres (30m*15m) of which the house, kitchen
and latrine cover 63.36m2, 9.9m2 and 8.41m2 respectively. Area of Site 2 on the other hand is 0.222
acres approximately 900 sqm(30m*30m).
The project construction site are comprise Site 1 where four houses are to be constructed, Site 2 where the
5th house is to be constructed. These are approximately 4 km apart.
Inspections of contractor’s heavy construction equipment has been carried out in Kampala by the CNOOC
safety team in Kampala to ensure that they are adequate and in accordance with the terms and conditions
specified in the Terms of reference. Poor tools were further were further checked by the CNOOC Health
ans safety team in Hoima.
Contractor’s machinery mobilisation to site has been effective for carrying out the preliminary works.
The Contractor sources aggregates and stone dust from Kibaale at a Chinese quarry. A copy of the quality
certificates have not been submitted from proposed supplier. Delivered material on site is as indicated in
Table 2-4.
The consultant has cautioned the contractor about the slow progress and enlightened him on ‘ Liquidated
damages’ penalties associated as per Article 2.2 of his contract.
3.5 Correspondances
In carrying out the requirement of the contract, the consultant has made necessary correspondances to and
from the company or contractor . Few of the correspondances were written as the main means of
communication have been through the email. Records of signed copies, which are acknowledged by the
Contractor or Company, are kept for future reference.
Outward correspondences refer to correspondances coming from the Consultant to the Company and or
the Contractor while inward correspondances refer to formal commucations received from the Contractor
and or Company are shown in Table 3-3.
The meeting provided a formal arrangement for checking the contractor’s performance against the work
program and provided on spot solutions to site issues.
Table PROGRESS OF WORKS-10: Meetings held and a brief of the issues discussed
No. Date Venue and Purpose of the meeting, Including brief issues discussed.
Kick off Meeting
The meeting was held at CNOOC offices.
Company congratulating KKATT Consult upon being awarded the Consultancy
1. services contract.
23/08/ 2017
Coompany confirmed Contract duration and Construction Supervision period.
Consultant Request of Documents from the Company.
The Company rectifying dicripances in the Contract Document on“Page 42, Item
1.3 and Pages 45 item 4.1 & 4.2
Interface meeting
2. The meeting was held at CNOOC offices.
04/10/2017
Company introduced Consultant to Contractor.
Company informally established Lines of communication.
Management Meeting No.1
3.
The meeting was held at Consultant’s offices in Nsambya.
1 06/10/2017
Consultant and Contractor sought to find ways of sddressing the variations in
quantities in the BoQ as requested by the Company.
4. 12 /10/2017 Site Visit/ Meeting at King fisher
The meeting was held at King fisher area, Hoima District.
Consultant to check Structural stability of existing resettlement house prototypes in
the rift valley.
No. Date Venue and Purpose of the meeting, Including brief issues discussed.
Kick off Meeting
The meeting was held at CNOOC offices.
Company congratulating KKATT Consult upon being awarded the Consultancy
1. services contract.
23/08/ 2017
Coompany confirmed Contract duration and Construction Supervision period.
Consultant Request of Documents from the Company.
The Company rectifying dicripances in the Contract Document on“Page 42, Item
1.3 and Pages 45 item 4.1 & 4.2
Interface meeting
2. The meeting was held at CNOOC offices.
04/10/2017
Company introduced Consultant to Contractor.
Company informally established Lines of communication.
Management Meeting No.1
3.
The meeting was held at Consultant’s offices in Nsambya.
1 06/10/2017
Consultant and Contractor sought to find ways of sddressing the variations in
quantities in the BoQ as requested by the Company.
5. 27/10/ 2017 Site Meeting
The meeting was held at CNOOC offices.
Company disappointed in the progress of events since no agreement has been
reached by Consultant and Contractor.
6. 30/10/ 2017 Management Meeting
The meeting was held at Contractor’s offices in Muyenga.
Proposing adoptions or variations from the Design Review that are agreeable with
the Consultant so that work can progress.
As part of our Health and Safety Policy, contractor’s workers are educated and made
vigilant against spread of STDs and how to prevent the aforementioned.
Increased spread of
Human Curb spread of Basic hygiene rules such as washing hands with soap after visiting toilets and before
communicable
Interactions communicable diseases. eating any foods or groceries were emphasized. Hand sanitary facilities shall be
diseases.
provided so that workers can wash their hands whenever they are going to eat, touch
anything contaminated or after visiting toilets and latrines.
Public Safety
Control and Drivers of all project vehicles have been cautioned against exceeding speed limits and other traffic
management regulations. A contact number has been engraved on the sides of the vehicles for anyone to call and
of traffic to report bad driving exhibited by our drivers
Control of Accidents
prevent motor Transport of construction materials was done in conformity with Uganda traffic law.
Construction occurring due to
accidents
traffic construction traffic
and thus safe
guard the
public
According to the work schedule, contractor is expected to be out of the substructure by end of November.
To achieve this target, contractor has brought the necessary machinery to site and expects to start strip
foundations with in the second week of November.
APPENDIX
General structure
Photo 3: Roofing of the shade for workers Photo 4: Backhoe removing spoil from excavations
Photo 5: Block making machine delivered to site Photo 6: Stock Pile of Block making Material
Substructure
Photo 7: setting out for Excavation preparations at Site 2 Photo 8: Foundation Excavation for Kitchen
Photo 9: Trimming and removing away top soil with in Photo 10: Removing of top weak soil within
foundations in Site 1 foundations
Photo 11: Trimmed foundations and removed top Photo 12: Excavation and making level foundation 3rd
vegetable soil block house
Photo 13: Manufactured hollow blocks at camp site Photo 14: Manufactured 400 blocks of 150mm at
Contractors Camp site