Professional Documents
Culture Documents
Project: Sugar Refinery Plant BILL OF QUANTITY Owner: Durrah Advanced Development Co.
Location: King Fahd Industrial Port Yanbu, KSA FINAL Rev. Date: 9 May 2018
DIVISION 2
2 SITE CONSTRUCTION
2.1 EXCAVATION
2.1.1 Excavation for foundation in all soils of whatever nature
encountered to the lines and grades required for
foundations, keeping the saftey of adjacent structure in
consideration by properly protecting the sides of trenches,
compacting the bottom of excavated surface, dispose of
surplus etc., complete the job, as per drawings in all
respect.
Supply Pipe
Pipeline 16301
Valve pits 459
Meter Chambers 82
Air Relief Pits 67
Thrust blocks 951
Manholes 267
Culverts 306
Pipe Bridge Foundation 620
Return Pipe M3
Pipeline 6718
Culverts 90
Thrust blocks 297
Out fall structure 605
Industrial Waste
Pipeline 4263
Meter Chamber 29
Thrust blocks 53
Sewer pipe 75
Electrical Works
Electrical Room 918
Duct Banks 1486
Inspection Chamber 449
Sub Total
2.2 BACK FILLING AND COMPACTION
M3
Sewer pipe 60
M3
Supply Pipe 3690
Return Pipe 1174
Industrial Waste 973
Process & Potable Water 581
Sewer pipe 8
Sub Total
Dewatering by lowering and controlling groundwater levels M3 54000
and hydrostatic pressures to permit excavation and approx.
construction to be performed in near-dry conditions. (Lump
sum)
Sub Total
DIVISION 3
3 CONCRETE WORKS
Prior to any substructure work, the contractor shall check
and coordinate the design of the reinforced concrete
foundations and related structures, and shall submit shop
drawings and calculations for consultant's review and
approval.
3.1 SUBSTRUCTURE
Supply Pipe
Valve pits 7
Meter Chambers 2
Air Relief Pits 1
Thrust blocks 18
Manholes 5
Culverts 9
Pipe Bridge Foundation 15
Return Pipe
Culverts 5
Thrust blocks M3 7
Out fall structure 11
Industrial Waste
Culverts 4
Meter Chambers 2
Thrust blocks 3
Electrical Works
Electrical Room 34
Duct Banks 60
Inspection Chamber 16
Return Pipe
Culverts M3 60
Thrust blocks 133
Out fall structure 187
Industrial Waste
Culverts 22
Meter Chambers 15
Thrust blocks 29
Electrical Works
Electrical Room 229
Duct Banks 265
Inspection Chamber 300
Sub Total
DIVISION 4
4.0 MASONRY
M2 285
Sub Total
DIVISION 7
7 THERMAL AND MOISTURE PROTECTION
Supply Pipe
Valve pits 80
Meter Chambers 15
Air Relief Pits 13
Thrust blocks 211
Manholes 46
Culverts 84
Pipe Bridge Foundation 148
Return Pipe
Culverts 30
M2
Thrust blocks 70
Out fall structure 121
Industrial Waste
Culverts 39
Meter Chambers 13
Thrust blocks 9
Electrical Works
Electrical Room 348
Duct Banks 550
Inspection Chamber 21
Sub Total
7.2 WATER PROOFING
7.2.1 Supply and apply two coats of liquid bituminous paint to all
concrete surfaces that comes in direct contact with
earth/soil as shown on drawing, complete in all respects.
(Awazil or approved equal).
Supply Pipe
Valve pits 320
Meter Chambers 75
Air Relief Pits 52
Thrust blocks 844
Manholes 184
Culverts 336
Pipe Bridge Foundation 296
Return Pipe
Culverts 120
Thrust blocks M2 280
Out fall structure 242
Industrial Waste
Culverts 156
Meter Chambers 65
Thrust blocks 36
Electrical Works
Electrical Room 522
Duct Banks 1925
Inspection Chamber 105
Sub Total
DIVISION 8
8 DOORS & WINDOWS
8.1 DOORS
8.1.1 Supply and install 45mm thick Steel Frame with 44mm
thick painted Steel door with all required hardware at
Electrical room, as per drawings and specifications,
complete in all respects.
8.2 WINDOWS
8.2.1 Supply and install powder coated aluminum framed
louver with mastic sealant and other accessories to be
EA
approved and supplied by specialist, as per the approved
shop drawing and specification, complete in all respects.
DIVISION 9
9.0 FINISHES
9.1.1 Epoxy coating on the floor as per drawings and
M² 160
specification, complete with all respect.
9.2 CEILING
9.2.1 Smooth Cement plastering for soffit of structural slab, as
per drawing and specification, complete in all respect.. M2 160
Sub Total
Grand Total
The following Codes, Regulations, and Standards are supposed to be used for the development of detailed design
drawings:
The Detailed design will be based on local governing codes and requirements, as well as the listed
industry standards and any owner standards. If conflicts exist between the different codes,
industry standards and owner standards, then the more stringent will be used.
Royal Commission for Jubail and Yanbu General Design Criteria and Technical Guidelines –Current Edition
ASTM standards, current edition
Marafiq Standard Specifications-Current Edition
General Design Criteria and Technical Guidelines & Standard Drawings – Current Edition, RCJY/Directorate
General
ACI 318 for YanbuEdition
- Current Project