You are on page 1of 6

B A S E A N D F O U N D AT I O N S Section B

Note : Special foundations are unnecessary. A level and Foundations


sufficiently strong concrete floor is adequate.
Main Block Materials
Introduction 1 Part Portland Cement
The responsibility for the design of the foundation 2 Parts clean sharp sand
(including seismic considerations) should be placed with 4 Parts washed ballast (3/4")
a civil or structural engineer specialising in this type of Grouting Mixture
work. 1 Part Portland Cement
Major functions of a foundation are to: 2 Parts clean sharp sand
Support the total weight of the generating set. When the water is added, the consistency of the mixture
Isolate generator set vibration from surrounding should be such that it can be easily poured.
structures. Should a suitable concrete base already exist or it is not
To support the structural design, the civil engineer will convenient to use rag-bolts, then rawl-bolts or similar
need the following details:- type of fixing bolt may be used. This obviates the
the plant’s operating temperatures (heat transfer from necessity of preparing foundation bolt holes as already
machines to mass could lead to undesirable tensile described. However, care should be taken that the
stresses). correct size of masonry drill is used.
the overall dimensions of the proposed foundation
mass. Modularised System/Enclosed-Silenced
the mounting and fixing arrangements of the Generators
generator bedframe. In the design of the layout for this type of system the
same constraints and guidance for the foundation should
Concrete Foundations be observed, however, as the generator set and
enclosure will be located directly onto the plinth, more
The foundation will require at least seven days between
care is required in its casting to ensure that it is flat and
pouring the concrete and mounting the generating set to
level with a "power float" type finish.
cure. It is also essential that the foundation should be
level, preferably within ± 0.5° of any horizontal plane and When the generator compartment is in the form of a
should rest on undisturbed soil. dropover enclosure, it will be necessary to provide a
weatherproofing sealing system in the form of angle
The following formula may be used to calculate the
section laid on an impervious strip seal. This will also act
minimum foundation depth :
as a bund to retain fuel, water or oil spillage.
k
t = ————
dxwxl
Vibration Isolation
t = thickness of foundation in m
Each generator is built as a single module with the
k = net weight of set in kg engine and alternator coupled together through a
d = density of concrete (take 2403 kg/m2) coupling chamber with resilient mountings to form one
w = width of foundation in (m) unit of immense strength and rigidity. This provides both
accuracy of alignment between the engine and alternator
l = length of foundation in (m)
and damping of engine vibration. Thus heavy concrete
The foundation strength may still vary depending on the foundations normally used to absorb engine vibration are
safe bearing capacity of supporting materials and the not necessary and all the generator requires is a level
soil bearing load of the installation site, therefore concrete floor that will take the distributed weight of the
reinforced gauge steel wire mesh or reinforcing bars or unit.
equivalent may be required to be used.

B2
B A S E A N D F O U N D AT I O N S Section B

Foundation Levelling
The generator can be placed directly on a level, concrete A poor foundation may result in unnecessary vibration of
floor, but where a permanent installation is intended, it is the plant.
recommended that the unit is placed on two raised
longitudinal plinths. This allows for easy access for Connections
maintenance and also allows a drip tray to be placed All piping and electrical connections should be flexible to
under the sump to meet fire regulation. Plinths should prevent damage by movement of the plant. Fuel and
raise the plant 100 to 125mm above floor level, the water lines, exhaust pipes and conduit can transmit
actual height depending on the type of plant. The plinths vibrations at long distances.
are normally cast in concrete but RSJ's or timber can be
used. If either of these two materials are used the
bearers should be bolted down with parobolts.
If in any doubt consult a Civil Engineer.
Bolting Down
Parobolts should also be used for anchoring the
concrete plinths when necessary.
Caution: Ensure that the concrete is completely set
and hardened before positioning the plant and
tightening holding down bolts.

300 kVA standard generator with base fuel tank in typical


plant room.

B3
ROOM DESIGN GUIDANCE NOTES Section B

Generator installations with acoustic The dimension "E" as indicated on the layout diagrams is
treatment to achieve 85dBA at 1 metre based upon using standard manufacturers silencers to
achieve 85dBA at 1m, please ensure that the intended
Note:- The layout drawings provided are intended as a
silencers to be used can be positioned as indicated as
guide and to form the basis of the installation design, but
this dimension affects the builders works such as
before the room design is finalised please ensure you
apertures to the walls for the exhaust outlet.
have a "project specific" generator general arrangement
drawing. Certain ambient temperatures or specific site The exhaust run as indicated exits via the side wall
requirements can affect the finalised generator build, through a wall sleeve, packed with a heat resistant
layout configuration and room dimensions. medium and closed to the weather with wall plates.
Should the generator room, internally or externally, be
Room size allowance
constructed with plastic coated profiled steel sheet
The dimensions as indicated A & B allow for good cladding, it is important to ensure that the wall sections
maintenance/escape access around the generator. at the exhaust outlet are isolated from the high exhaust
Ideally you should allow a minimum distance of 1 metre pipe temperature and sealed by a specialist cladder. The
from any wall, tank or panel within the room. same applies for any exhaust going through or near any
Machine access timber or plastic guttering.
It is important to remember that the generator has to be It is good installation practice for the exhaust system
moved into the constructed generator room, therefore within the generator room to be insulated with a
the personnel access door has to be of a sufficient size minimum of 50mm. of high density, high temperature
to allow access alternatively the inlet/outlet attenuator mineral insulation covered by an aluminium overclad.
aperture should be extended to the finished floor level, This reduces the possibility of operator burn injury and
with the bottom uplift section built when the generator is reduces the heat being radiated to the operating
in the room. generator room.
Inlet and outlet attenuators with weather louvres Cable systems
The inlet and outlet attenuators should be installed within The layout drawings assumes that the change-over
a wooden frame and are based on 100mm. airways with switch-gear is external to the generator room and
200mm. acoustic modules. The attenuators should be located in the power distribution room. Specific project
fitted with weather louvres with a minimum 50% free requirements can affect this layout.
area, good airflow profile and afford low restriction The power output cables from the generator output
airflow access. The noise level of 85dB(A) at 1m will breaker to the distribution panel must be of a flexible
comply with minimum EEC Regulations. To achieve construction:-
lower levels attenuator size can more than double in
EPR/CSP (6381TQ)
length.
PCP (H07RNF)
The weather louvres should have bird/vermin mesh
screens fitted on the inside, but these screens must not Should the cable route length from the generator to the
impede the free flow of cooling and aspiration air. distribution room be extensive the flexible cables can be
terminated to a load terminal close box to the generator
The outlet attenuator should be connected to the radiator
and then extended to the distribution room with
ducting flange with a heat and oil resistant flexible
armoured multi-core cables. (See typical load terminal
connection.
box layout).
Exhaust systems The flexible power cables as installed should be laid up
The exhaust systems shown on the layout drawings are in trefoil, placed on support trays/ladder rack in the
supported from the ceiling. Should the building trench with the recommended inter-spacing and
construction be such that the roof supports were unable segregated from the system control cables.
to support the exhaust system, a floor standing steel The cables should be correctly supported and rated for
exhaust stand will be needed. Exhaust pipes should the installation/ambient conditions.
terminate at least 2.3m above floor level to make it
The flexible single core power cables when entering any
reasonably safe for anyone passing or accidentally
panel must pass through a non ferrous gland plate.
touching.
It is recommended that stainless steel bellows be fitted
to the engine exhaust manifold followed by rigid
pipework to the silencer.

B4
ROOM DESIGN GUIDANCE NOTES Section B

Change-over panels. Doors.


Should the change-over panel be positioned within the Doors should always open outwards. This not only
generator room due note must be made of the floor/wall makes for a better door seal when the set/s are running
space that must be made available. but allows for a quick exit/panic button or handle to get
For change-over cubicles up to 1000Amp. rating the wall out. Make allowance for the generator to be moved into
mounting panel of maximum depth 420mm. can be the room by using double doors at the attenuator space.
mounted directly above the cable trench in the side Generator installations WITHOUT
access area without causing too many problems.
acoustic treatment.
For change-over cubicles from 1600Amp. and above, a
floor standing panel is used which needs additional Note: Handy rule of thumb for INTAKE louvres. Use 1.5 x
space to be allocated. Refer to Page D11 for dimensions. radiator area.
The room dimensions need to be increased in the area All the previous notes regarding "generator installations
of the cable duct/change-over panel to allow space and with acoustic treatment" equally apply to installations
man access around cubicles with the following without acoustic attenuators with the exception of
dimensions. A minimum of 800mm. for rear access paragraph 3 relating to the Inlet and Outlet louvres.
should be allowed. Inlet and outlet louvres.
The cable trench in the area of the change-over cubicle The inlet and outlet weather louvres should be installed
needs to be increased in size to allow for the mains, load within a wooden frame with a minimum 50% free area,
and generator cable access requirement. good airflow profile and low restriction airflow access.
Generator Sets. The weather louvres should have bird/vermin mesh
screens fitted on the inside, but must not impede the free
All generators shown include 8 hour base fuel tanks.
flow of cooling and aspiration air.
Free standing tanks can be provided but additional room
space will be required. The outlet weather louvre should be connected to the
radiator ducting flange with a heat and oil resistant
Canvas ducting between the radiator and ductwork or
flexible connection.
attenuator should be a minimum of 300mm.
Air inlet should be at the rear of the alternator to allow When a radiator is mounted on the end of the
adequate circulation. plant main frame, position the set so that the
radiator is as close to the outlet vent as possible,
otherwise recirculation of hot air can take place.
The recommended maximum distance away from
the outlet vent is 150mm without air ducting.

Flexible cable should be used

Control panel

Note:
Alternator If flexible cable is used
terminal box DMC between switchboard,
remote panel and generator,
a load terminal box
is un-neccessary

Multicores run between


set and DMC cubicle

To changeover
switchboard
Load terminal box must be used
if connecting cable is PVC/SWA/PVC

Fig. B1 Cable Connections


B5
RECOMMENDED ROOM SIZES Section B

CUMMINS ENGINE POWERED 37 kVA - 511 kVA GENERATING SETS WITHOUT ACOUSTIC TREATMENT.
SINGLE SETS.

Prime Type Room dimensions Set Set C/L Exhaust Outlet Inlet
Rating of 2000 1999 Length width height back position Offset Height Louvre Uplift Louvre Cable trench position
KVA ENGINE Model Model A B C D P E X F G H J K L M N
32.5 B3.3G1 26 DGGC CP30-5 3100 3000 2600 400 1500 159 2300 650 700 650 750 800 420 400 1165
50 B3.3G2 40 DGHC CP50-5 3100 3000 2600 400 1500 275 2300 750 800 650 900 900 420 400 1165

38 4B3.9G 30 DGBC CP40-5 3100 3000 2600 400 1500 141 2300 650 750 600 750 850 520 400 1325
52 4BT3.9G1 42 DGCA CP50-5 3200 3000 2600 400 1500 194 2300 650 750 600 750 850 520 400 1325
64 4BT3.9G2 51 DGCB CP60-5 3200 3000 2600 400 1500 194 2300 650 750 600 750 850 520 400 1325
70 4BTA3.9G1 56 DGCC CP70-5 3250 3000 2600 400 1500 194 2300 650 750 600 750 850 520 400 1410

96 6BT5.9G2 77 DGDB CP90-5 3500 3000 2600 400 1500 168 2300 700 860 540 800 800 520 400 1630
106 6BT5.9G2 85 DGDF CP100-5 3500 3000 2600 400 1500 168 2300 700 860 540 800 800 520 400 1630

129 6CT8.3G2 103 DGEA CP125-5 3850 3000 2700 400 1500 255 2300 850 1025 600 1000 1150 520 400 1910
153 6CTA8.3G 122 DGFA CP150-5 3850 3000 2700 400 1500 255 2300 850 1025 600 1000 1150 520 400 1910
185 6CTA8.3G 148 DGFB CP180-5 3850 3000 2700 400 1500 255 2300 850 1025 600 1000 1150 520 400 2070
200 6CTAA8.3G 163 DGFC CP200-5 3950 3000 2700 400 1500 255 2300 850 1025 600 1000 1150 520 400 2070

233 LTA10G2 186 DFAB CP200-5 4850 3250 2800 500 1625 361 2300 1000 1075 520 1150 1250 625 400 2285
252 LTA10G3 202 DFAC CP250-5 4850 3250 2800 500 1625 361 2300 1000 1075 520 1150 1250 625 400 2285

315 NT855G6 252 DFBH CP300-5 4850 3200 2700 500 1600 284 2300 1000 1300 700 1250 1400 625 400 2525
350 NTA855G4 280 DFCC CP350-5 4850 3200 2700 500 1600 284 2300 1000 1300 700 1250 1400 625 400 2525
431* NTA855G6 340 DFCE CS450-5 4850 3200 2700 500 1600 284 2300 1000 1300 700 1250 1400 625 400 2630

431 KTA19G3 345 DFEC CP400-5 5275 3400 3000 500 1700 320 2500 1400 1450 700 1600 1675 775 400 2815
450 KTA19G3 360 DFEL CP450-5 5275 3400 3000 500 1700 320 2500 1400 1450 700 1600 1675 775 400 2815
511 KTA19G4 409 DFED CP500-5 5275 3400 3000 500 1700 320 2500 1400 1450 700 1600 1675 775 400 2815

Before finalising the generator room layout please ensure you read the guidance notes.
*Standby rating only.

B6
a P

X
F

aa
RECOMMENDED ROOM SIZES

Cummins Generating Sets 30 kVA - 511 kVA


Generator 100m layout without Acoustic Treatment

SEE NOTES

SET
SET

CANVAS
DUCTING

WALL PLATES & SLEEVE


SEE NOTES

EXHAUST

H
AIR
FLOW
DATUM

SET
DATUM
N

FUEL TRANSFER
TRENCH IF BULK
TANK INCLUDED
A
M

CABLE TRENCH

EXHAUST HUNG FROM CEILING


50mm MINERAL LAGGING
AND ALUMINIUM CLAD

FLEXIBLE EXHAUST
BELLOWS

SUB BASE FUEL TANK

B7
AIR
FLOW

600

TRENCH
Section B

PANEL PC005
(IF SUPPLIED)

TRENCH TO
SWITCHROOM

SEE NOTES
RE PLANT ACCESS

WEATHER LOUVRE
SEE NOTES

H
B

You might also like