You are on page 1of 8

1

Analysis of South-East Europe Transmission


Network Expansion Plan under the Future
Market Conditions
Milan Vukasovic, Mladen Apostolovic and Sreten Skuletic

Greece and Albania have a deficit of electric energy. Control


Abstract-- The South-East Europe region is faced with the area of Serbia, operated by EMS (Elektromreza Srbije), got
new challenges related to organization of electricity market. a variable energy balance during a year. The load flows are
The main goal of this paper is to analyze present South-East oriented from the North to the South, most of the year. The
Europe power transmission system infrastructure, taking into
biggest problem, recognized in the SEE region, lies in
account recent developments, and to examine influence of the
future market activities on a reinforced power grid. The tripping of 400 kV Blagoevgrad (Bulgaria) – Thessaloniki
analysis has been made for several scenarios of cross-border (Greece) tie-line. If that happens, it will lead to tripping of
electricity exchanges, taking into account planned transmission 400 kV Kosovo B (Serbia-UNMIK) – Skopje 5 (Macedonia)
network projects as well as foreseen investments in a new tie-line, in most of the cases. Therefore, these two overhead
generation capacities in the following few years. Change in the lines are recognized as the cross-border capacities of the
electricity consumption in the region has also been taken into
account. Analysis, which has been performed, emphasized a
special importance in the SEE region. At present, profile
several critical bottlenecks in the transmission network that which is defined as a critical one is the border between
must be solved in a due time in order not to limit cross-border Serbia-UNMIK and Macedonia. This profile is mutually
electricity trade and thus not to distort competiveness in the cross-connected with three interconnection lines: one 400
regional electricity market in South-East Europe. kV over-head line (OHL) Kosovo B – Skopje 5 and two 220
kV OHLs Kosovo A – Skopje 1 (which are temporary out of
Index Terms-- analysis, congestion, energy, flows, market,
operation as they were destroyed during the war 1999 [2]).
SEE, trade
Non-availability of 220 kV double line between Serbia-
I. INTRODUCTION UNMIK and Macedonia highly-affects electricity exchange
in direction North-South, mostly in summer months (July
F UTURE commercial electricity exchange, which will be
caused by the establishment of South-East Europe (SEE)
electricity market in the so called 8th region, as it was
and August) when Greece has peak demand and big imports
from the other power systems. Especially dangerous regime
during the summer is outage of 400 kV bus bars in sub-
defined by Ministerial Council of the Energy Community station (SS) Kosovo B (Serbia-UNMIK). Power flows in this
[1], will have a high influence on power flows in the region. case can have negative influence on the critical bottlenecks
It is also important to underline the importance that the (220 kV OHL Prizren(SR) – Fierze(AL), 220 kV OHL
future transmission capacity allocation mechanism will have Podgorica 1(CG) – Vau Dejes(AL) and 400 kV
on allocated/real power flows and security of operation Blagoevgrad(BG) – Thessaloniki(GR)) and therefore lead to
(bottlenecks in transmission network). Methods for cascade outages and power supply cuts in the particular
allocation of cross-border transmission capacities were region (example: 25th of July, 2007).
constantly evolving in a previous years towards the market Commercial congestion is permanently present in
based mechanisms (explicit auctions), which are currently directions from Romania to Serbia and from Bulgaria to
applied on the most of the borders in SEE region. Outcome Serbia. Reason for this lies in the fact that Romania and
of these allocation procedures clearly shows the necessity for Bulgaria got a surplus of electric energy and Serbia is used
the transmission network expansion in order to as a transit area towards Montenegro, Macedonia and
accommodate all the wishes of market participants for cross- Greece (countries with electric energy deficit). It should be
border electricity trade. The classical planning principle for mentioned that the power system of Turkey, controlled by
expansion of transmission network can not be applied under system operator TEIAS, is currently not synchronized with
the deregulated environment or it could lead to the non- the UCTE network.
optimal solution (over-investments).
Romania, Bulgaria and Bosnia and Herzegovina are II. SEE NETWORK MODEL AND ANALYZED SCENARIOS
electric energy exporters, whereas Montenegro, Macedonia,
In the analysis described in this paper, current thermal
limits are used as rated limits for over-head lines. These
M. Vukasovic is with Verbund Austrian Power Grid AG, Vienna, limits are established based on the temperature (different
Austria (e-mail: Milan.Vukasovic@verbund.at).
M. Apostolovic is with Energy Financing Team, Belgrade, Serbia
limits for winter and summer models) to which conductor is
(e-mail: mladen.apostolovic@eft-group.net). heated by current above which either the conductor material
S. Skuletic is with the Faculty of Electrical Engineering, University of would start being softened or the distance between
Montenegro, Podgorica, Montenegro (e-mail: skuletic@cg.ac.yu).
2

conductor and ground would drop beyond permitted limits. reinforcements (Fig. 1) and the foreseen investments in
For transformers, rated installed MVA power is used as generation capacities, i.e. power plants (Table I), as it is
thermal limit. Every branch with current above its thermal given in [3]. Consumption has been changed (increased by
limit is considered as overloaded. 15%) proportionally in all SEE country nodes, except for
The electric power systems in the one part of the SEE Greece where load has been just slightly adjusted (for 4%
region are modeled with the complete 400 kV and 220 kV due to the fact that numerous potential investments in the
networks (or 150 kV network in the case of Greece) and Greece until 2012 have not been taken into account).
additionally 110 kV network for the power system of Generation and consumption have not been changed in
Montenegro (meshed network). Hungary, Croatia and Slovenia.
The analysis has been performed for the target year 2012,
taking into account the planned transmission network

Fig. 1. Existing tie-lines, recently built (Ia and Ib) and some of the newly planned (II and III) tie-lines in the SEE region

SEE transmission network is connected radial (island model) o Ib) Stip(MK) – Chervena Mogila(BG), 42km long
with the power system of Turkey with two tie-lines (fixed OHL Dubrovo – Stip (internal line in Macedonia)
injection to SEE region of 300 MW). In the considered and transformer 400/110 kV 300 MVA in SS Stip
network model all injection goes to Maritza 400 kV node (Macedonia) [5]
and power exchange from Italy to Greece over DC cable is
• Scenario II: new 400 kV tie-line Podgorica 2(CG) –
held on constant value (100 MW).
Tirana(AL) [6]
Overview of the analyzed scenarios: • Scenario III: new 400 kV tie-line Fillipi(GR) – Maritza
• Scenario I: two 400 kV tie-lines that are already put into East 3(BG)
operation (with additional necessary network elements • Scenario IV: all network elements from Scenarios I-III
that have been constructed): assumed to be in operation as well as the new
o Ia) Bitola(MK) – Florina(GR), and transformer generation capacities (Table I).
400/160 KV in SS Florina [4]
3

TABLE I
NEW GENERATION CAPACITIES (POWER PLANTS) IN SEE REGION

Power Plant Country Installed Power (MW) Commissioning Date Comments

TPP Maritsa East 3 Bulgaria 2x300 2010 Rehabilitation and modernization of the facility

On Drin river – HPP node is connected to 220


HPP Skavica Albania 300 2011
kV node Burrel
TPP Kosovo C Serbia-UNMIK 500 2011 Fuel: lignite
5 km from the capital Skopje – connected to
CHPP Energetika Macedonia 200 2012
110 kV network, but modeled on 220 kV side

As it can also been seen from the Fig. 2, construction of a


III. CHANGE IN POWER FLOWS OVER THE MOST IMPORTANT newly planned tie-lines (400 kV tie-line Podgorica 2 –
TIE-LINES IN SEE REGION: SCENARIOS I-III Tirana (Scenario II) and Fillipi – Maritza East 3 (Scenario
In the Fig. 2 (Scenarios Ia and Ib), change in power flows III) will have high influence on power flows over the most
over the most important tie-lines in SEE region (year 2008 important tie-lines in SEE region (year 2012 winter model).
winter model) due to influence of recently built tie-lines, is Construction of 400 kV tie-line Podgorica 2 – Tirana, would
shown. It is obvious that construction of 400 kV corridor have the highest influence on reliving loading of 220 kV
Chervena Mogila – Stip – Dubrovo (displayed in Fig. 2 as parallel-line Podgorica 1 – Vau Dejes and Albanian
Scenario Ib) will decrease power flows over 400 kV OHL interconnector towards Greece (400 kV OHL Zemlak –
Kosovo B – Skopje 5, 400 kV OHL Blagoevgrad – Kardia), but very low influence on the other important
Thessaloniki and 400 kV Dubrovo – Thessaloniki. On the interconnections in the SEE region. New tie-line between
other hand, construction of 400 kV tie-line Bitola – Florina Greece and Bulgaria, 400 kV OHL Fillipi – Maritza East 3,
and 400/160 KV transformer in SS Florina (Scenario Ia) will would mainly influence power flows over 400 kV OHL
have very low influence on the important regional tie-lines Blagoevgrad – Thessaloniki (reliving loading of the line) but
(except on the parallel line Bitola – Meliti). It is important to would also contribute to power flow decrease between the
notice that all abovementioned investments have a positive following profiles: Serbia – Macedonia and Bulgaria –
influence on flow reduction (around 130 MW in total) over Macedonia.
400 kV OHL Blagoevgrad – Thessaloniki.

Fig. 2. Change in power flows over the most important tie-lines in SEE region: Scenarios I-III
4

• all 400 kV and 220 kV lines in the modeled region


IV. SENSITIVITY ANALYSIS: NEW NETWORK ELEMENTS AND except lines which outage cause “island” operation.
GENERATION CAPACITIES (SCENARIO IV) Additional exchange is simulated in the SEE region on
the starting base case Scenario IV (displayed in Table II) as
A. Load-flow and (n-1) contingency analysis
sensitivity cases.
The system reliability is checked using (n-1) contingency Results of the security (n-1) analysis show the potential
criterion. List of predefined critical contingencies includes:
problems in SEE regional network. It should be noted that
• all tie-lines in modeled SEE region except tie-lines
the change in area totals (simulation of additional exchange
toward the non-modeled area (“non-breathing” lines), between SEE control areas) is obtained by generation shift
• all 400/220 kV and 400/110 kV transformers in the up/down in the respected areas proportionally to the
modeled region, engagement in the base case (i.e. starting Scenario IV).

TABLE II
ADDITIONALLY SIMULATED EXCHANGES ON BASE CASE SCENARIO IV (SENSITIVITY ANALYSIS)

Exchange UCTE1 CEE Ukraine Turkey Romania Bulgaria IT_cable Albania Greece
1 -200 200
2 -500 300 200
3 300 300 -300 -100 -200
4 -650 200 200 250
5 -200 100 100 100 100 -100 -100

Insecure system operations for given generation and load lead to overload of Bulgarian internal line Maritza East
patterns are detected in the power systems of Serbia and – Plovdiv. This clearly shows that with the analysed
Bulgaria for the winter model, year 2012 (Fig. 3): 400 kV network reinforcement in Bulgaria and Greece
(new 400 kV lines Maritza East 3 – Fillipi, 400 kV
a) All disturbances on 220 kV side in control area of lines Maritza East 3 – Babaeski and 400 kV lines
Serbia-UNMIK have relatively high influence on Maritza East 3 – Hamitabat) export of Turkey should
transformer 400/220 kV Nis. For example, outage of be limited to 350 MW. Internal network of Bulgaria
220 kV line Kosovo B – Podujevo will lead to should be reinforced in order to support additional
overload of mentioned transformer up to 111% Snom in energy exchange from Turkey towards Balkan area
the simulated Exchanges 2 and 4 (high export of (planned new 400 kV OHL Zlatisa – Plovdiv) but also
Romania and Bulgaria toward the non-modeled UCTE link between Greece and Turkey should be considered
region). In those Exchange cases Serbian 400 kV (400 kV tie-line Nea Santa – Babaeski).
network is loaded higher than usual (power flow over
400 kV Sofia – Nis is increased up to more than 100
Analysis made on the winter model clearly shows the
MW).
importance of node Nis in Serbia (sub-station 400/220 kV)
and also necessity to install an additional transformation unit
b) Loss of the 220 kV line Feronikl – Prizren can cause
400/220 kV, to reconstruct destroyed double 220 kV tie-line
overloading of 220 kV tie-line between Serbia-UNMIK
Kosovo A – Skopje 1 between Serbia-UNMIK and
and Albania (Prizren – Fierze). Problem is caused by
Macedonia (or to replace them with the 400 kV OHL on the
high distributive consumption which is supplied from
same route) or to build new 400 kV tie-line Nis (SR) –
node Prizren (214 MW) and lower Iterm value of OHL
Skopje (MK) [7]. In all analyzed cases transformer 400/220
Fierze – Prizren (720 A compared to 1290 A of OHL
kV in SS Nis is highly loaded (more than 80% Snom).
Feronikl – Prizren). In order to avoid electricity supply
Problem could be temporary solved with the bus coupler in
cuts, 110 kV network inside Serbia-UNMIK area
SS Nis (400 kV side) and with the grouping some of 400 kV
should be reconfigured and part of consumption should
lines to the other bus system (in order to constrain power
be supplied from the other 220 kV stations (if
flow over transformer 400/220 kV). In this case one should
possible). On the other hand, this critical contingency
be careful in order not to shift the existing problem to the
will not have influence on the interconnected high-
other part of the network (by solving problems in node Nis).
voltage network.
Described sensitivity analysis on the winter model has been
performed with the 3rd transformer 400/220 kV in SS
c) In the simulated Exchange cases 1 and 5 (additional
Kosovo B in operation (disconnected in the starting base
Turkey export of 200 MW and 100 MW, respectively)
case model).
tripping of 400 kV tie-line Fillipi – Maritza East 3 can

1
UCTE virtual zone is consisted from CEE region with IT region (only OHLs between Slovenia and Italy, without DC
cable between Greece and Italy) and Ukraine.
5

Fig. 3. Scenario IV – security (n-1) analysis for the 3rd week of January (10:30 a.m.) / winter model – year 2012

Insecure system operations for given generation and load means of redispatch action with the following HPPs:
patterns are detected in the power systems of Serbia, Visegrad (on Bosnian side – cross-border redispatch
UNMIK, Bulgaria, Romania and Greece for the summer necessary) and B. Basta, but also with the HPPs
model, year 2012 (Table III): connected to the 110 kV network in Serbia (Kokin
Brod, Bistrica and Uvac). On the other hand, Exchange
a) All exchange programs have relatively high-impact on cases 2 and 4, have counter-effect on problems related
already congested Bulgarian internal network. The to transformer in SS Nis which can be overloaded up to
weakest link is 220 kV OHL Plovdiv – Aleko which is 115% Snom (problems with transformer 400/220 kV Nis
overloaded after the different (n-1) outages in range are also present in sensitivity analysis performed on the
from 103% Iterm to 124% Iterm. The highest average winter model).
loading of critical internal line is achieved in exchange
cases 1 and 5, i.e. in the situations when the additional c) Critical outage of one transformer 400/220 kV Slatina
export of Turkey has been simulated. in Romania will lead to overloading of the second
transformer (115% Snom).
b) In internal Serbian network, outage of 220 kV OHL B.
Basta – Pozega will lead to overloading of 220 kV d) In internal Serbian network, outage of 400 kV OHL
OHL Pozega – Vardiste and vice versa. It is important Mladost – S. Mitrovica will lead to overloading of 220
to notice that this problem is present only in summer kV OHL Novi Sad – Srbobran in all Exchange cases
model and can be slightly relived in the Exchange cases except Exchange 3 (when additional flows are oriented
2 and 4 (i.e. additional export of Bulgaria and Romania in direction from North to South).
to the rest of UCTE which will cause flows in direction
East-West). Temporary, problem could be solved by

TABLE III
SCENARIO IV – SECURITY (N-1) ANALYSIS FOR THE 3RD WEEK IN JUNE (10:30 A.M.) / SUMMER MODEL – YEAR 2012

BC EX1 EX2 EX3 EX4 EX5


Critical outage Critical line
Line/transformer loading (%)

400 kV Fillipi - Maritsa East 104 114 111 103 110 113

400 kV Plovdiv - Maritsa East 220 kV Plovdiv - Aleko 112 124 120 113 122 121
400 kV C. Mogila - Vetren 105 115 112 105 113 113
220 kV B. Basta - Pozega 220 kV Pozega - Vardiste 118 119 115 118 106 117
220 kV Pozega - Vardiste 220 kV B. Basta - Pozega 105 105 * 105 * 105
400/220 kV TR Slatina (1) 400/220 TR Slatina (2) 115 116 113 115 118 115
400 kV Mladost - S. Mitrovica 220 kV N. Sad - Srbobran * 102 105 * 105 103
400/220 kV TR Nis 220 kV Kosovo B - Podujevo * * 110 * 115 *
6

B. Voltage profiles in the SEE region: Scenario IV


Voltage profiles in the SEE region (400 kV and 220 kV
nodes) after the reinforcement in the transmission network
and after the construction of new power plants is displayed
in Fig. 4. As it can be observed, voltage profile is
satisfactory as all nodes (except the voltage in 220 kV node
Skopje1(MK) which is also under allowed value in the
starting base case scenario and four nodes in Croatia
including Zakucac and Konjsko which are slightly above
allowed limits) are within requested range, i.e. between 0.95
p.u. and 1.1 p.u.. Bus voltage magnitudes below permitted
limits are not found in the analyzed scenario and, in general,
average increase of bus voltage levels can be recorded (after
network reinforcement) all over the SEE electricity network
compared to the starting scenario. Fig. 4: Histogram of 400 kV and 220 kV bus voltages in SEE region in the
Network reinforcement as well as the change in analyzed Scenario IV
generation/consumption patterns in interconnected power
systems have the highest influence on voltage level increase It should be emphasized that the network analysis has not
(winter model) in power systems of OST (Albania) in 220 been performed with the additional voltage controlling
kV SS Tirana and SS Burrel (change of 2.7 and 2.4 kV, devices in operation (transformer tap changers, switched
respectively). This is mainly caused by reinforcement made shunts, etc.), but rather on the starting model (also, only
in 400 kV Albanian network. consumption of active power has been scaled in Scenario
IV). Therefore, more detailed analysis is needed in order to
access possibilities for the voltage regulation in SEE region
after the proposed reinforcements.

TABLE IV
CHANGE IN BUS VOLTAGE: SCENARIO IV (400 KV NODES) – WINTER MODEL / YEAR 2012

Bus Voltage [kV] Bus Voltage [kV] Change in bus Bus voltage (p.u.)
Bus Name
Scenario IV Starting Base Case voltage [kV] Scenario IV
Fillipi (GR) 406,4 402,6 3,8 1,016
Hevic (HU) 407,3 405,5 1,8 1,018
Divaca(SI) 396,9 395,1 1,8 0,99
Zerjavinec (HR) 403,8 402,4 1,4 1,009
Meline (HR) 402,3 401,0 1,3 1,00

TABLE V
CHANGE IN BUS VOLTAGE: SCENARIO IV (220 KV NODES) – WINTER MODEL / YEAR 2012

Bus Voltage [kV] Bus Voltage [kV] Change in bus Bus voltage (p.u.)
Bus Name
Scenario IV Starting Base Case voltage [kV] Scenario IV
Tirana (AL) 216,2 213,5 2,7 0,980
Burrel (AL) 220,7 218,3 2,4 1,002
Urechesti (RO) 234,0 231,9 2,1 1,060
Rovinari (RO) 234,0 231,9 2,1 1,063
Mizia (BG) 240,7 238,7 2,0 1,094
Rashbull (AL) 211,9 210,0 1,9 0,960
Pleven (BG) 236,4 234,9 1,5 1,075
Targu Jiu (RO) 232,4 230,9 1,5 1,056
Elbasan 1 (AL) 217,4 216,0 1,4 0,988
Elbasan 2 (AL) 217,8 216,5 1,3 0,990
Fierza (AL) 212,3 211,1 1,2 0,960

consumption centers in Albania are located in the Southern


C. Analysis Summary
part of the country, in case when Albanian power system
In the starting analyzed scenario, in a balanced situation imports around 200 MW, the voltage profile in the Albanian
of the Albanian system, there is a loop flow of about 100 network goes down from the North part to the South part of
MW from Greece to Serbia-UNMIK (just small part goes to the country. Voltage profile in Albania is drastically
Montenegro). Due to this reason and the fact that the main improved with the construction of 400 kV Podgorica 2 –
7

Tirana and the new SS Kashar on its route. In this paper only This is mainly caused by power plant investments (NPP
one new power plant project is considered in Albania (HPP Cerna Voda, unit no.2 with 706 MW of installed power) and
Skavica with installed 300 MW), but according to the study flows (direction from East to South-West) which have high
made by Institute of Hydroelectric Studies and Design [8], influence on transformers 400/220 kV in Slatina node
the new possible power plants to be constructed in Albania (transformer loading 244 MW in Scenario IV compared to
are: HPP Bushati (84 MW, Drin River), HPP Kaludha (75 170 MW in the starting base case scenario – summer
MW, Vjosa River), HPP Dragot-Tepelena (130 MW, Vjosa model).
River), HPP Kalivaci (100 MW, Vjosa River), HPP Bratila The main problems in control area of ESO (Bulgaria) are
(115 MW, Devoll River) and HPP Banja (80 MW, Devoll present after the investment in power plants (especially TPP
River). It is also predicted that TPP Vlora 1 (100 MW) Maritsa East 3) which are not followed with the
should be put in operation until 2012. All of the mentioned reinforcements of the internal network and the radial
investments have to be followed with the proper network connection with Turkey (import of 300 MW). Better
reinforcement, especially strengthening the Vlore and Fieri distribution of the “incoming” power flows from Turkey
nodes and their upgrade to 400 kV level. New 400 kV tie- (import) has been achieved with the splitting of incoming
line between Elbasan and Bitola is also planed as the future flows between Bulgaria and Greece after the construction of
network project. 400 kV tie-line Fillipi (GR) – Maritza East 3 (BG), together
During the analysis it was clearly shown that additional with already constructed 400 kV OHL Fillipi – N.Santa
transformer is needed in SS 400/220 kV Nis (problem could (GR) – Babaeski (TUR). Anyway, network problems in the
be temporary solved with 400 kV bus bar coupler in SS Nis) central part of Bulgaria could be solved with the internal
since the existing transformer is very sensible to 220 kV network reinforcement – new 400 kV OHL Plovdiv –
network situation in Serbia-UNMIK area and also to Zlatitsa (149 km, project investment of 25 mil. €) which is
additional export of Bulgaria towards West. Also, problems one of the most important project for the future synchronous
are located in internal EMS network in the grid near the interconnection of Turkey with UCTE.
following nodes: B.Basta, Vardiste and Pozega. Loading of
the 220 kV OHLs B.Basta – Pozega, Vardiste – Pozega and V. CONCLUSIONS
B.Basta – Vardiste is highly dependent on energy transfer in The Southeast Europe region is faced with new
direction North to South as well as the current engagement challenges related to organization of electricity market. In
of PSHPP B.Basta, HPP Bistrica and HPP Visegrad (Bosnia the process of deregulation, new production companies,
and Herzegovina). Transmission System Operators, supply companies and
In the summer network model, problems are also located traders appeared. Present electricity infrastructure is not
in the Northern part of the country. Namely, outage of 400 fully designed to serve market activities properly and some
kV OHL Mladost – S.Mitrovica would lead to problems in investments in transmission systems internally, as well in
220 kV network (OHL Novi Sad – Srbobran). Future interconnection lines are necessary in order to support
reinforcement in this region are foreseen on 400 kV voltage competition and expected market activities.
level: 400 kV Sombor – S.Mitrovica. New power plant Southeast Europe transmission network operates on
projects (beside TPP Kosovo C) are not considered inside 750 kV, 400 kV, 220 kV, 150 kV and 110 kV voltage levels.
EMS control area since the first one is foreseen for 2015 Power systems are mostly strongly interconnected through
(TPP Kolubara B). many 400kV and 220 kV lines. Analysis has shown that
Some of the problems present in internal transmission some insecure operational conditions are expected in some
network of EMS are also caused by changing thermal limit parts of Romanian, Serbian, Bulgarian and Albanian
of 220 kV lines from the winter to the summer regime (i.e. network so additional network reinforcement activities will
changes in relay-system protection settings) [9],[10]. be necessary in order to minimize network congestions.
There were no problems located in Montenegrin network, Balkan area is the new investment frontier for
except in the starting base case model: critical outage of international power companies. Although, numerous power
400/110 kV transformer in SS Podgorica 2 could lead to plant project that have been planned are not yet constructed
slight overloading of the second parallel transformer 300 and therefore high level of uncertainty is present also when it
MVA in the same substation. The problem is solved after the comes to high-voltage power transmission system extension
construction of 400 kV OHL Podgorica 2 – Tirana. Problem planning.
which is present in the starting base case model highly It is important to underline that the influence of global
depends on configuration of internal Montenegrin network economic crisis on power consumption level in SEE region
as well as on current consumption level. Temporary solution (decrease of energy consumption for industrial consumers)
for relieving congestion and solving network problems and on delay of generation investment projects have to be
would be to use the internal redispatch measures with HPP taken into consideration, as well as influence of other
Perucica or (in some cases when consumption supply from ongoing infrastructure transmission investment projects (for
110 kV substations is not that high, i.e. off-peak hours) example: 400 kV OHL Nis – Leskovac – Vranje (Serbia)
disconnection of the double 110 kV line between SS with the connection point Stip/Skopje in Macedonia) in
Podgorica 1 and SS Podgorica 2 would be necessary in order some future similar analysis.
to avoid parallel operation of 110 kV network (loop flows).
Transformer in Romanian SS 400/220 kV Slatina has
appeared as the weak point during the performed analysis.
8

VI. REFERENCES
[1] Ministerial Council of the Energy Community, “Decision No. 2008-
02 on Implementation of EC Decision amended Annex Regulation
1228/2003”
[2] UCTE, European Interconnections: State of the Art, Annual report of
the joint EURELECTRIC - UCTE Working Group "SYSTINT",
2002.
[3] ETSO, Winter Outlook Report, Detailed country analysis, June 2007.
[Online]. Available: http://www.etso-net.org/.
[4] D. Bajs, G. Majstorovic, M. Majstorovic, “Uticaj izgradnje novih
interkonektivnih dalekovoda u ovom dijelu Europe na rad EES
Hrvatske”, Energetski Institut Hrvoje Pozar, Zagreb 2001.
[5] UCTE, System Adequacy Forecast 2006-2015, 2005. [Online].
Available: http://www.ucte.org,
[6] E. Radheshi, “Priority Infrastructure Investments, Tehnical Workshop
on Priority Infrastructure Investments in Power Sector”, Vienna, April
2008.
[7] MEPSO, Study for optimization of connection point of new 400 kV
interconnection to Serbia, 2008. [Online]. Available:
http://www.mepso.com.mk/,
[8] L. Mihailova, Imagine all renewables… Is There a Potential?,
available at http://www.seeurope.net, January 2006.
[9] SECI Interconnection Study Task Group, “Development of the
interconnection of the electric power systems of SECI member
countries for better integration with European systems: Project of
regional transmission network planning”, Study sponsored by
USAID, 2002.
[10] D. Bajs, "South-East Europe transmission system planning project”,
in Proc. IEEE PES General Meeting, Toronto, Canada, July 2003.

VII. BIOGRAPHIES
Milan Vukasovic (b. 1981) received his DI degree and M.Sc. in Electrical
Engineering, both from the Department of Power Systems, Faculty of
Electrical Engineering Podgorica, University of Montenegro (2004 and
2007). He works in Verbund – Austrian Power Grid AG, Market
Management Department, on issues related to flow-based coordinated
allocation and market coupling. Previously he worked with Electric Power
Company of Montenegro (2005/07). His main interests are in electricity
markets modeling/simulation, congestion management, load-flow analysis
and computer applications in power systems.

Mladen Apostolovic (b. 1975) received his DI degree and M.Sc. in


Electrical Engineering, both from Faculty of Electrical Engineering,
University of Belgrade, Serbia (2000 and 2005). Presently, he works in
Energy Financing Team, Portfolio Management Department. Previously, he
worked with Electricity Coordinating Center (2001/05) and Electric Power
Utility of Serbia (2005/07). His topics of research include congestion
management, optimization techniques in power systems and deregulated
electricity markets.

Sreten Skuletic (b. 1949) graduated from the Faculty of Engineering at the
University in Titograd, and holds Ma degree (Electrical Engineering
Faculty, Belgrade) and Ph.D. in Electrical Engineering (Electrical
Engineering Faculty, Titograd). He is Full Professor at University of
Montenegro. His main research interests and activities have been in the
field of Power Electric Systems, particularly: Reliability modeling,
assessment, evaluations and analysis, energy, high voltage problems in
power systems, grounding, rational usage of energy, conventional and new
energy sources... He has published 186 papers.

You might also like