TENSION
Metode Pengujian
Introduction
This test is performed to confirm the design load calculations and to provide guidelines for setting up
the limits of acceptance for routine tests. Initial Test on piles are to be carried out at one or more
locations depending on the number of piles required. The static loading test involves the direct
measurement of pile head displacement in the response to a physically applied load test.
Scope of Work
The static loading test may be carried out for the following load configurations:
1. Axial compressive test
2. Lateral test
3. Axial tension test (uplift)
Testing Apparatus
1. Hydraulic Jack cap
Fabricator : Enerpac
2. Manometer/Pressure Gauge
Fabricator : ENERPAC
Capacity : 10.000 Psi
3. Electric Pump
Fabricator : ENERPAC
Capacity : 10.000 Psi
1 of 10
PT. Hume Sakti Indonesia
4. Dial Indicator
Fabricator : MITUTOYO
Capacity : 50 mm
5. Beam
Main Beam : H Beam
6. Reference Beam
7. Welding Machine 400 Ampere
8. Plate and Casing
9. Other tools and accessories
Method
a. Land clearing and digging the soil to prepare the working area depends on the position of pile
head,
b. The pile head shall be prepared usually with casing (for cast in situ piles) to be above t
he ground by a sufficient length or a minimum of 300mm. Prior to grouting the pile, anchor
strands are embedded and tied to the last reinforcement cage of pile at the top,
c. A hydraulic jack and reacting against a set of steel beams tied to anchor piles is placed,
d. Fix dial gauges on an independent ‘frame’ to measure the pile head displacement,
e. Movement of the pile head shall be measured using the dial gauge and checked with a leveling i
nstrument and scale rules fixed to their holders, and
f. The loading sequence shall follow the client’s specification including the step and duration,
records shall be kept promptly throughout the testing period.
2 of 10
PT. Hume Sakti Indonesia
Diagram of Compression Load Test Setup on a Single Pile Using Weighted Platform
3 of 10
PT. Hume Sakti Indonesia
Loading Sequence
The test may follow to the modified ASTM D 1143-07 (Reapproved 2007) of either item:
8.1.2 “Procedure A: Quick Test”, or
8.1.8 “Procedure G: Cyclic Loading Test”
with load sequence in percentage of design load.
250%
% of Designed Minimum time Reading
Load of load holding Interval
0
5 5 min. 2.5 min.
200%
10 5 min. 2.5 min.
15 5 min. 2.5 min.
20 5 min. 2.5 min.
25 5 min. 2.5 min.
150%
Increments of
5% BEBAN (%)
LOAD (%)
4 of 10
200% of the designed load Quick Test 0 1 hr. 10 min
% of Designed Minimum time Reading
Load of load holding Interval
0
25 20 min. 10 min
250%
50 2 hr 10 min
25 20 min. 10 min
0 1 hr. 10 min
50 20 min. 10 min
75 2 hr 10 min
200%
100 2 hr 10 min
75 20 min. 10 min
50 20 min. 10 min
0 1 hr. 10 min
BEBAN (%)
125 2 hr 10 min
150 2 hr 10 min
125 20 min. 10 min
100 20 min. 10 min
50 20 min. 10 min
0 1 hr. 10 min
50 20 min. 10 min
50%
Lateral Test
This test method covers procedures for testing vertical and batter piles either individually or in group
s to determine the load/deflection relationship when subjected to lateral loading. It is applicable to a
lldeep foundation units regardless of their size or method.
The actual lateral load capacity of the pile-soil system can best be determined by lateral testing. The
test system refer to the ASTM D 3966 – 07.
Method
1 of 10
PT. Hume Sakti Indonesia
Diagram of Lateral Load Test Typical Setup with Conventional Hydraulic Jack
Loading Sequence
The test may follow to the modified ASTM D 1143-07 (Reapproved 2007) item 8.1.4 “Procedure C:
Cyclic Loading Test”.
2 of 10
PT. Hume Sakti Indonesia
Tension
Field tests provide the most reliable relationship between the axial load applied to a deep fo
undation and the resulting axial movement. Test results may also provide information used to
assess the distribution of side shear resistance along the pile shaft and the long‐term load
deflection behavior. A foundation designer may evaluate the test results to determine if, after ap
plying an appropriate factor of safety, the pile or pile group has an ultimate static capacity and a de
flection at service load satisfactory to support a specific foundation. Test system refer to the
ASTM D 3689 – 07.
Method
3 of 10
PT. Hume Sakti Indonesia
a. Prior to grouting the pile, anchor strands are embedded and tied to the last reinforcemen
t cage of the pile at the top,
b. Install structural tension connectors extending from the test pile or pile cap, constructed of steel
straps, bars, cables, and/or other devices bolted, welded, cast into, or otherwise firmly affixed to
the test pile or pile cap to safely apply the maximum required tensile test load without slippage, r
upture, or excessive elongation,
c. Place the hydraulic jack(s), hemispherical bearing(s), and bearing plates on top of the test
beam(s). Center a reaction frame over the jack(s), and anchor it to the tension connections
extending from the test pile or pile group. Design and construct the test beam(s), reaction f
rame, and reaction piles or cribbing, and arrange the jack(s) symmetrically so as to
apply the resultant tensile load at, and parallel to, to the longitudinal axis of the test pile or pile gr
oup,
d. Fix dial gauges on an independent ‘pipe frame’ to measure the pile head displacement,
e. The loading sequence shall follow the client’s specification including the step and duration,
records shall be kept promptly throughout the testing period.
Loading Sequence
The test may follow to the modified ASTM D 1143-07 (Reapproved 2007) item 8.1.4 “Procedure C:
Cyclic Loading Test”.
4 of 10
PT. Hume Sakti Indonesia
5 of 10