This document explains how we can do the mass update for a BOM.I feel that this is a basic
question asked in the forum for many times .
1. Tcode CS20
2) Delete material
3) Add Material
4) Add Document
5) Add class
After that you can update following field Quantity
Item Text
But it is difficult to remove costing relevancy indicator through CS20 if it is defined as blank in the
system .
Step 1
Go to item tab in the component field give the component code ( for which user wants to do the
changes in all Bom)
Step 3
Select Bom for which user wants to do the changes & click on Edit/Lock Button
Step 4
After that Field will became Editable user have to change the fields & save
Now BILL OF MATERIAL has changed as per requirement massly.