PROJECT: PROPOSED THREE STOREY SCHOOL BUILDING

LOACTION: BRGY. PUNTA TABUC, , ROXAS CITY, CAPIZ


OWNER: CAPIZ COMMERCIAL SCHOOL
SUBJECT:BREAKDOWN OF LABOR COST

ITEM LABOUR PERCENT PERFORMANCE


DESCRIPTION OF MATERIALS (%)
NO.: COST WEIGHT (%)

1 MOBILIZATION/DEMOBILIZATION 50,000.00 1.24 0.62


2 BUIDING PERMIT PROCESSING 30,000.00 0.74 0.37
3 EXCAVATION 76,640.00 1.90 1.52
4 BACKFILLING 88,440.00 2.19 -
5 FOUNDATION 226,120.00 5.61 4.49
6 TIE BEAMS 51,760.00 1.28 0.51
7 WALL FOOTINGS 28,160.00 0.70 -
8 REINF. CONCRETE COLUMNS 322,720.00 8.01 6.01
9 2ND FLOOR BEAMS 232,760.00 5.78 -
10 3RD FLOOR BEAMS 232,760.00 5.78 -
11 ROOF BEAMS 101,680.00 2.52 -
12 GROUND SLAB 78,680.00 1.95 -
12 2ND FLOOR SLAB 224,880.00 5.58 -
3RD FLOOR SLAB 224,880.00 5.58 -
CONCRETE TOPPINGS 90,880.00 2.26 -
6" CHB WALLS 28,880.00 0.72 -

4" CHB WALLS 521,200.00 12.93 -

ROOF FRAMING 89,560.00 2.22 -

STEEL GRILLS 60,000.00 1.49 -

SCAFFOLDINGS 29,320.00 0.73 0.36

FORM WORKS 256,000.00 6.35 2.54

THIRD FLOOR CEILING 31,880.00 0.79 -

TILE WORKS 242,800.00 6.02 -

PAINTING WORKS 229,680.00 5.70 -

TINSMITHRY WORKS 71,920.00 1.78 -


ITEM LABOUR PERCENT PERFORMANCE
DESCRIPTION OF MATERIALS (%)
NO.: COST WEIGHT (%)

DOORS 58,400.00 1.45 -

WINDOWS 49,200.00 1.22 -

CONCRETE GUTTER 101,680.00 2.52 -

ELECTRICAL WORKS 139,120.00 3.45 -

PLUMBING WORKS 60,000.00 1.49 -

4,030,000.00 100.00 16.43

PREPARED BY:

RAMIL ARTATES