HVAC PENDING MATERIAL AS OF 22-03-2018-THRDNSHB

S. No. Name of Material Status Remarks

1 Fans (Ventillation and Smoke Extract) 31-Mar-18

Dispatch clearance to be given by To be delivered within 3 days


2 HVAC Control Panel, Field devices and Instruments
L&T after DC
3 Electric Duct Heaters 25-Apr-18
4 Air Terminals (Diffuser, Grille, Sand trap louvers)-
5 11 kV Rooms 28-Mar-18
6 132kV GIS Room 05-Apr-18
7 Capacitor bank 12-Apr-18
8 Balance 15-Apr-18
Pump room louvers, motorized dampers, NRD & fire To be confirmed by M/s Jamaheer
9
rated ducting
10 GI Ducts Partially Delivered
11 Nitrogen Room 04-Apr-18
12 Battery Rooms 04-Apr-18

LSP & HVAC Related Electrical Works Material Pending status

1 Passive Infra red Sensor 28-Apr-18

2 Wiring Devices -Balance 15-Apr-18

3 Heavy Duty Sockets 31-Mar-18

4 All Distribution Boards 02-Apr-18

5 4-pin Ceiling Rose 31-Mar-18

6 Cable Tray & Trunking with Accessories 29-Mar-18


HVAC PENDING MATERIAL AS OF 22-03-2018-THRDNSHB

S. No. Name of Material Status Remarks

7 Cable Glands,Lugs and ferrules 31-Mar-18

8 Fuse Spur Units 29-Mar-18

9 Cables

a Cables for Dampers 11 kV Rooms 29-Mar-18

b Cables for Dampers 132 kV GIS Room 31-Mar-18

c Balance Cables for Dampers 08-Apr-18

d 110 V DC cables -Emergency Lighting 29-Mar-18

e Power Cables 05-Apr-18

f Control Cables To be confirmed by M/s Jamaheer

14 Junction Box/Enclosure To be confirmed by M/s Jamaheer


Installation
Start Finish
1 Roof pent house clearence (13 Nos ) 25.03.2018 05.04.2018

11kV Rooms balance works including 29.03.2018 04.04.2018


2 fixing of grills, damper cabling etc

132 kV GIS Room balance works


3 including fixing of grills, damper 29.03.2018 05.04.2018
cabling etc
Capacitor Bank balance works
4 including fixing of grills, damper 12.03.2018 15.04.2018
cabling etc
First Floor balance works including
5 fixing of droper ,diffuser fixing, 16.04.2018 25.04.2018
damper cabling,sensor cabling etc.

Roof HVAC and Related Electrical


6 WIP 20.04.2016
works except control cabling
HVAC MATERIAL STATUS UPDATED ON 23.12.17

JUMSOUTH THRDNSHB
Material
S. No. Name of Material Status Revised Delivery Date on Revised Delivery Date on Remarks
ID
23/12/2017 23/12/2017
Air Conditioning - Roof top packaged AC - (Weight - Awaiting Despatch
1 77 Awaiting DC 25-Dec-17 25-Dec-17
2200 Kg) Clearance

2 78 Fans (Ventillation and Smoke Extract) Approved 15-Feb-18 15-Feb-18 -

15/2/2018 (From Approval 15/2/2018 (From Approval


3 79 HVAC Control Panel, Field devices and Instruments REV-0 submitted to DEWA -
8-10 Weeks) 8-10 Weeks)

4 80 Electric Duct Heaters Approved 15-Jan-18 15-Jan-18 -

Sample to be Submitted to 1/15/2018 (From Approval 1/15/2018 (From Approval


5 81 Air Terminals.(Diffuser, Grille, Sand trap louvers). GIS Room Criti1cal
DEWA 8-10 Weeks) 6-8 Weeks)

6 83 Duct Insulation(Thermal & Accoustic) Approved 90% - Delivered 90% - Delivered -

7 283 HVAC Miscellaneous Items (Canvas Cloth) Approved 90% - Delivered 90% - Delivered -

8 84 Vapour Barrier Coating & Sealant Approved 90% - Delivered 90% - Delivered -

9 84 Aluminum Cladding Sheet Approved 28/12/2017 28/12/2017

First Floor (28/12/2017) First Floor (28/12/2017)


10 84 Access Doors Approved
& Roof (01.01.2018) & Roof (01.01.2018)
GIS (28/12/2017) & First GIS (28/12/2017) & First
11 85 Volume control damper, Approved
floor (28/12/2017) floor (28/12/2017)

12 85 Motorised damper Approved Roof (01.01.2018) Roof (01.01.2018)

13 85 Non Return Damper Approved Roof (01.01.2018) Roof (01.01.2018)

14 173 Flexible Duct Connector Approved Roof (01.01.2018) Roof (01.01.2018)

First Floor (28/12/2017) First Floor (28/12/2017)


15 86 Fusible link Fire Dampers Approved
& Roof (01.01.2018) & Roof (01.01.2018)

Capacitor Bank (18.12.17)


16 86 Motorized Fire Smoke Dampers (MSFD) Approved 18-Dec-17
& Roof (01.01.2018)

17 114 Insulation for split units refrigerant piping Approved 15-Feb-18 15-Feb-18

18 115 Split Units - Decorative type Approved 15-Feb-18 15-Feb-18

19 82 Refrigerant Copper Piping Approved 15-Feb-18 15-Feb-18