You are on page 1of 19

PIPE FITTINGS

Size Rate(Rs/ft)
S# Description No Dia Unit (Rs/No) Cost Rs.
1 Socket 50 1" Inch 22 1100

2 Union 20 1" Inch 55 1100

3 Socket 52 3/4" Inch 18 936

4 Union 26 3/4" Inch 50 1300

5 Socket 125 1/2" Inch 16 2000

6 Tee 2 1"-1/2" Inch 30 60

7 Tee 14 3/4"-1/2" Inch 26 364

8 Union 62 1/2" Inch 50 3100

9 Taps 20 1/2" Inch 90 1800

10 Ball Valve 2 3/4" Inch 150 300

11 Reducer 3 3/4-1/2 Inch 32 96

11760.00

Total 11760.00
Bar Bending Schedule :-
Size No of Cut No of Total weight/ft Total Wt Remarks
S# Description (dia) item Length Bar Length (lbs) (lbs)

1 Spring Cappiang Tank


(4'x4'x4') 2No
Main Bar @ 6" C/C Both way's 1/2" 2 7.33 30 439.8 0.667 293.35 3" 6-10"

2 Storage Tanks
( 8' x 8' x 7.5' ) 1No
Main Bar @ 6" C/C Both way's 1/2" 1 11.33 46 521.18 0.667 347.63 3" 10-10"

640.97 lbs

Total 291 Kg
QUANTITIES OF MATERIAL & LABOUR REQUIRED

MATERIAL LABOUR

SN DESCRIPTION QTY UNIT CEMENT SAND CRUSH STONE Cover STEEL Water Pipe SKILLED UNSKILLED

BAG CFT CFT CFT No KG Ltrs RFT NO's NO's

1 Excavation of tanks (in soft rock) 272.00 Cft - - - - - - - 14.32

2 P.C.C (1:4:8) in foundation of tanks 136.00 Cft 12.92 64.60 129.20 - - 582.08 - 0.45 8.00

3 Stone masnory (1:4) in walls of tanks 749.31 Cft 50.20 254.77 - 936.64 - - 3207.05 - 49.95 92.51

4 P.C.C (1:2:4) in flooring of tanks 4" thick. 31.68 Cft 5.58 13.94 27.88 - - - 135.59 - 0.11 1.86

5 1/2" thick Plastering (1:3) in wall of tanks 748.00 Sft 10.47 39.64 - - - - 3201.44 - 5.34 6.93

6 R.C.C (1:2:4) in slab of tanks 30.11 Cft 5.30 13.25 26.50 - - - 0.28 2.51

7 Shuttering of R.C.C slab of tanks 110.52 Sft - - - - - - - 4.25 4.25

8 M.S Cover in slab of tanks 3.00 No - - - - 3.00 - - 1.00 1.00

9 Steel Fabrication 291 Kgs - - - - - 291 - 2.91 2.91

10 Distribution System/Pipe Fixing

Laying /Fixing of pipe

G-I Pipe 1" Dia 740.00 Rft 740.00 4.23 5.92

G-I Pipe 1/2" Dia 3690.00 Rft 3690.00 49.20 73.80

G-I Pipe 3/4" Dia 1530.00 Rft 1530.00 13.54 20.40

TOTAL 84 386 184 937 3 291 7126 5960 131 234

TOTAL C/O. 91 404 219 937 3 291 7126 5960 132 238
CAPITAL COST OF DRINKING WATER SUPPLY SCHEME

LABOUR COST

ManDays
SN Item Quantity Unit Skilled Unskilled

1 Excavation of tanks in soft rock 272.00 cft 0.00 14.32

2 P C C 1: 4: 8 in foundation of tanks 136.00 cft 0.45 8.00

3 Stone Masonry 1:4 in walls of tanks 749.31 cft 49.95 92.51

4 P C C 1: 2:4 in flooring of tanks 31.68 cft 0.11 1.86

5 Plaster 1/2 " 1:3 in walls of tanks 748.00 sft 5.34 6.93

6 R C C 1: 2:4 in slab of tanks 30.11 cft 0.28 2.51

7 Shuttering of R.C.C slab of tanks 110.52 sft 4.25 4.25

8 M.S Cover in slab of tanks 3.00 No 1.00 1.00

9 Steel Febracation 290.82 Kg 2.91 2.91

10 G.I Pipe 1" Dia 740.00 Rft 4.23 5.92

11 G.I Pipe 1/2" Dia 3690.00 Rft 49.20 73.80

12 G.I Pipe 3/4" Dia 1530.00 Rft 13.54 20.40

TOTAL 131 234

TOTAL C/ O 132 238

S.No. COST: Estimated (Rs)

1 Skilled @ 300/-per no. 132.00 39600.00

2 Unskilled @ 180/-per no. 238.00 42840.00

TOTAL 82440.00
CAPITAL COST OF DRINKING WATER SUPPLY SCHEME

MATERIAL COST

SN Item Quantity Unit Unit Rate Amount


Rs Rs

1 Cement 91 Bags 335 30485

2 Sand 404 Cft 23 9292

3 Crush 219 Cft 24 5256

4 Stone 937 Cft 10 9370

5 1/2" dia Steel 291 Kgs 42 12222

6 Pipe (G.I 1" Dia) 740 Rft 48 35520

7 Pipe (G.I 3/4" Dia) 1530 Rft 36 55080

8 Pipe (G.I 1/2" Dia) 3690 Rft 26 95940

9 Pipe Fittings - - 11760

10 M.S cover 3 No 1000 3000

11 Transportation - - - 21330.16

TOTAL 289,255

TOTAL C/O 289,255.000


CAPITAL COST OF DRINKING WATER SUPPLY SCHEME
Transportation Charges

S.# Item Qty Unit Unit Rate Amount


Rs Rs

1 Cement 91 bag 20 1820


2 Sand 404 cft 10 4040
3 Crush 219 cft 10 2190
4 Stone 937 cft 3 2811
5 1/2" dia Steel 291 kg 5 1455
6 Pipe and Fitting 5220 rft 1.5 7830
7 Shuttering 111 sft 8 884

8 M.S cover 3 no 100 300

Total 21330
SUMMARY OF COST

Name of Region Rawalpindi District Rawalpindi

Field Unit Murree U.Council Sehr Bagla

Thesil Murree Village Daniota

Name of CO. Daniota Type of Scheme DWSS

S.# DESCRIPTION ESTIMATED CONTRIBUTION CONTRIBUTION


COST Rs OF CO Rs OF PPAF Rs
A LABOUR

1 Skilled 39,600 32,160 7,440

2 Unskilled 42,840 42,840 0

SUB TOTAL (A) 82,440 75,000 7,440

B MATERIAL

1 Cement 30485 0 30485

2 Sand 9292 0 9292

3 Crush 5256 0 5256

4 Stone 9370 0 9370

4 Pipes &Fittings 198300 0 198300

5 Steel 12222 0 12222

9 M.S cover 3000 0 3000

10 Transpoartion 21330 0 21330

SUB TOTAL (B) 289,255 0 289,255

TOTAL A+B 371,695 75,000 296,695

COST OF SIGN BOARD 4,000 0 4,000

GRAND TOTAL 375,695 75,000 300,695

Contribution OF PPAF 300,695

Percentage 20% 80%

Field Engineer: ……………………………. Regional Engineer:………………………


Hydraulic Statement Chart
S# LINE Length No Of Maximum Design Velocity Size of Head Loss HGL
(ft) Household Demand Demand Ft/Sec Pipe (ft) Upper End Lower End Ground
6am-8am Cusec (Ft) (Ft) Level

1 A-B 40.00 29 0.00247 0.0082 2 0.083 3.73 4358 4354.27 4346


2 B-C 700.00 29 0.00176 0.0059 2 0.083 101.07 4346 4244.93 4224
3 C-D 400.00 28 0.00194 0.0065 2 0.040 33.68 4224 4190.32 4176
4 D-E 300.00 27 0.00212 0.0071 2 0.040 30.06 4176 4145.94 4129
5 C-F 200.00 27 0.00212 0.0071 2 0.083 41.58 4129 4087.42 4073
6 F-G 100.00 26 0.00176 0.0059 2 0.060 10.44 4073 4062.56 4055
7 F-H 250.00 25 0.00212 0.0071 2 0.040 25.05 4055 4029.95 4014
8 H-I 150.00 24 0.00318 0.0106 3 0.040 33.82 4014 3980.18 3966
9 J-K 150.00 22 0.00159 0.0053 2 0.040 2.25 3966 3963.75 3947
10 L-M 40.00 20 0.00212 0.0071 2 0.040 15.03 3947 3931.97 3925
11 M-N 150.00 19 0.00106 0.0035 1 0.060 7.51 3925 3917.49 3903
12 C-O 200.00 16 0.00229 0.0076 2 0.060 88.20 3903 3814.80 3799
13 P-Q 500.00 15 0.00212 0.0071 2 0.060 42.08 3799 3756.92 3731
14 Q-R 280.00 14 0.00247 0.0082 3 0.040 81.83 3731 3649.17 3635
15 R-S 600.00 13 0.00212 0.0071 2 0.040 60.12 3635 3574.88 3552
16 S-T 300.00 12 0.00176 0.0059 2 0.040 20.87 3552 3531.13 3512
17 U-V 100.00 12 0.00212 0.0071 2 0.040 10.02 3512 3501.98 3487
18 W-X 120.00 11 0.00106 0.0035 1 0.040 3.01 3487 3483.99 3470
19 X-Y 240.00 10 0.00106 0.0035 1 0.040 6.01 3470 3463.99 3447
20 V-K' 400.00 9 0.00106 0.0035 1 0.040 10.02 3447 3436.98 3421
21 K'-L' 200.00 8 0.00106 0.0035 1 0.040 5.01 3421 3415.99 3400
22 Z-A' 40.00 7 0.00106 0.0035 1 0.060 1.50 3400 3398.50 3387
23 B'-C' 20.00 6 0.00106 0.0035 1 0.040 0.50 3387 3386.50 3369
24 D'-E' 80.00 5 0.00106 0.0035 1 0.060 3.01 3369 3365.99 3350
25 D'-F' 20.00 4 0.00106 0.0035 1 0.040 0.50 3350 3349.50 3340
26 G'-H' 80.00 3 0.00106 0.0035 1 0.040 2.00 3340 3338.00 3327
27 I'-J' 300.00 1 0.00106 0.0035 1 0.040 7.51 3327 3319.49 3301
Terminal
Head
(ft)

8.27
20.93
14.32
16.94
14.42
7.56
15.95
14.18
16.75
6.97
14.49
15.80
25.92
14.17
22.88
19.13
14.98
13.99
16.99
15.98
15.99
11.50
17.50
15.99
9.50
11.00
18.49
DESIGN CRITARIA

Proposed Scheme :- DWSS

Total House Hold 50 No's


Beneficiary house hold 29 No's
Average Population per House Hold. 7 Persons
Total population of the community 203 Persons
Design period 10 Years
Let annual growth rate is 3%
Thus Design Population 203(1+0.03)^10 273 Persons
Let
Average per capita water consumption is 10 gallons per capita per day
Then average daily daman 2728 Gpd
Let Demand for cattel 30 Gpd
Demand for mosque 0 Gpd
For other utility services 50 Gpd
Thus total daily demand 2808 Gpd
Requird water tank capacity 2808 Gpd
0.033 Gps
450 cft/day
Free board= 6"

Thus provide a storage tank of size 8'x8'x7.5'


WATER DEMAN
MAND AND TAP FLOW CACULATION SHEET

Project Name :.

Description of tap Domestic and Institutional Water demand


Cluster Name numbers of Present pop. Design period Growth rate Design Pop.(pn) Per capita Demand
Tap nos or locality families (p) (n) (%) ( r ) [p(1+r)^n] (lpcd)
1 2 3 4 5 6 7 8

TOTAL

NOTE:
1.Use Minimum Peak factor of 3 in col,15;
2. For Design Tap Flow (Col. 17) ,adjust peak flow of (col.16)by rounding off to nearest 0.01lps.
3.If flow is less than 0.1 lps then then adjust to 1lpsand if flow is greater than 0.25 lps increase the number of tapsand
Other Institutional water Demand totel water demand
Totel Domestic Demand No of pupil in Demand per pupil Total other Institutional (lpd)
(lpd) institutional (lpcd) demand ( lpd)
9=7*8 10 11 12=10*11 13=9+12

e the number of tapsand


Tap Flow calcultion
Awerarge peak factor peak flow Design flow Adjustid peak
tap flow in lps (lps) (lps) Facter Remarks
14=13/86400 15 16=14*15 17 18=17/14 19
DESIGN OF STROAGE TANK
6"
18"

in let

Size 6"
8'x8'x7.5' 12'
out let
A A
M.S Cover
1.5'x1.5'

PLAN

1/2" bar @ 6" c/c b/way R.c.c 1:2:4


. 4"slab thick

in let

18" 8 feet 18" (1:4) Stone masnry

7.5'

Plaster (1:3) 1/2" thick

(6" thick P.c.c 1:4:8)


(4" thick P.c.c 1:2:4) N.S.L
out let
1'

Size : 8'x8'x7.5'
X - SectionA A
DESIGN OF CAPPING TANK
6"
18"

in let

6"
Size
4'x4'x4' 8'
out let
A A
M.S Cover
1.5'x1.5'

PLAN

1/2" bar @ 6" c/c b/way R.c.c 1:2:4


. 4"slab thick

in let

18" 4 feet 18" (1:4) Stone masnry

4'

Plaster (1:3) 1/2" thick

(6" thick P.c.c 1:4:8)


(4" thick P.c.c 1:2:4)
out let

Size : 4'x4'x4'
X - SectionA A
QUANTITIES

SN DESCRIPTION NO L B D/H QTY UNIT

FT FT FT

1 Stroage tank 8'x8'x7.5' = 1 Nos

1.1 Excavation of tanks (in soft rock)

1 12 12 1 144 cft

Sub Total 144 cft

1.2 P.C.C (1:4:8) in foundation 6" thick.

1 12 12 0.5 72 cft

Sub Total 72 cft

1.3 Stone masnory (1:4) in tanks Wall

L.walls 2 11 1.5 7.75 255.75 cft

S.walls 2 8 1.5 7.75 186.00 cft

Sub Total 442 cft

1.4 P.C.C (1:2:4) in flooring of tank 4" thick.

1 8 8 0.33 21.12 cft

Sub Total 21 cft

1.5 1/2" Plastering (1:3) in walls of tanks.

(in side) L.Walls 2 8 7.5 120 sft

(in side) S.Walls 2 8 - 7.5 120 sft

(out side) L.Walls 2 11 8.16 179.52 sft

(out side) S.Walls 2 11 - 8.16 179.52 sft

Sub Total 359 sft

1.6 R.C.C (1:2:4) in slab of tanks.

tank 8x8x7.5 1 11 0.33 0 cft

Deduction of M.S Cover

tank 8x8x7.5 1 1.5 1.5 0.33 1 cft

Net Total -1 cft

1.7 Shuttering of R.C.C slab of tanks.

tank 8x8x7.5 1 8 8 - 64 sft

Side Stopper L,side 2 11 0.33 7 sft

Side Stopper S.side 2 11 0.33 7 sft

Sub Total 79 sft

1.8 M.S Cover in slab of tanks.

tank 8x8x7.5 (1.5x1.5) 1 - - - 1

Sub Total 1 No
SN DESCRIPTION NO L B D/H QTY UNIT

FT FT FT

1 Capping tank 4x4x4 = 2 Nos

1.1 Excavation of tanks (in soft rock)

capping tank 4x4x4 2 8 8 1 128 cft

Sub Total 128 cft

1.2 P.C.C (1:4:8) in foundation 6" thick.

capping tank 4x4x4 2 8 8 0.5 64 cft

Sub Total 64 cft

1.3 Stone masnory (1:4) in tanks Wall

Capping tank 4x4x4 L.walls 4 7 1.5 4.66 195.72 cft

S.walls 4 4 1.5 4.66 111.84 cft

Sub Total 308 cft

1.4 P.C.C (1:2:4) in flooring of tank 4" thick.

capping tank 4x4x4 2 4 4 0.33 10.56 cft

Sub Total 11 cft

1.5 1/2" Plastering (1:3) in walls of tanks.

capping tank 4x4x4 (in side) L.walls 4 4 - 4 64 sft

S.walls 4 4 - 4 64 sft

(out side) L.walls 4 7 - 4.66 130.48 sft

S.walls 4 7 - 4.66 130.48 sft

Sub Total 389 sft

1.6 R.C.C (1:2:4) in slab of tanks.

capping tank 4x4x4 2 7 7 0.33 32 cft

Sub Total 32 cft

Deduction of M.S Cover

capping tank 4x4x4 2 1.5 1.5 0.33 1 cft

Sub Total 1 cft

Net Total 31 cft

1.7 Shuttering of R.C.C slab of tanks.

tank 4x4x4 2 4 4 - 32 sft

Side Stopper 8 7 0.33 18 sft

Sub Total 32 sft

1.8 M.S Cover in slab of tanks.

tank 4x4x4 (1.5x1.5) 2 - - - 2

Sub Total 2 No
CAPITAL COST OF DRINKING WATER SUPPLY SCHEME

Schedule of Pipe's

SN Location Dia in Inch" Length in ft' Remark's

1 A-B 1.00 40.00 G.I Pipes

2 B-C 1.00 700.00 G.I Pipes

3 C-D 0.50 400.00 G.I Pipes

4 D-E 0.50 300.00 G.I Pipes


5 C-F 0.75 200.00 G.I Pipes

6 F-G 0.50 100.00 G.I Pipes

7 F-H 0.75 250.00 G.I Pipes

8 H-I 0.50 150.00 G.I Pipes


9 J-K 0.50 150.00 G.I Pipes

10 L-M 0.50 40.00 G.I Pipes

11 M-N 0.50 150.00 G.I Pipes

12 C-O 0.75 200.00 G.I Pipes

13 P-Q 0.75 500.00 G.I Pipes

14 Q-R 0.75 280.00 G.I Pipes

15 R-S 0.50 600.00 G.I Pipes

16 S-T 0.50 300.00 G.I Pipes


17 U-V 0.75 100.00 G.I Pipes

18 W-X 0.50 120.00 G.I Pipes

19 X-Y 0.50 240.00 G.I Pipes

20 V-K' 0.50 400.00 G.I Pipes


21 K'-L' 0.50 200.00 G.I Pipes

22 Z-A' 0.50 40.00 G.I Pipes

23 B'-C' 0.50 20.00 G.I Pipes

24 D'-E' 0.50 80.00 G.I Pipes


25 D'-F' 0.50 20.00 G.I Pipes

26 G'-H' 0.50 80.00 G.I Pipes

27 I'-J' 0.50 300.00 G.I Pipes

Dia of Pipe G.I Pipe HDPE Pipe


1" 740.00 0

3/4" 1530.00 0
1/2" 3690.00 0

You might also like