DEMOLITION METHODOLOGY

DISMANTLING SEQUENCE
Before commencing any dismantling operation, priority is given to the setting up of support facilities such as, changing rooms and storage units, giving
necesarry required services to the work force.

Once “work Units” have been erected, Mostaloy will identify zones to be protected, prior to commencement of any works as follows:-

1. Metal sheeting will be used to separate and protect outsiders from the site.
2. Hoarding will be provided inorder to act as a temporary wall while demolitions are ongoing.

All utilities connected to the site eg, water, electricity and plumbing have to be correctly identified and securely disconnected during the demolition and
dismantling process.

NON-LOAD BEARING STUD PARTITION WALLS:

The internal walls of the building are generally plasterboard on timber stud. Such partitions will be removed by hand by operatives using suitable hand held
tools, namely electric screw drivers, crow bars, picks and hammers. Timber stud partitions will be de-erected by removing the coverings using the hammers
and bars. Once exposed the remaining timber stud work is to be prized free and denailed.

WASTE DISPOSAL
Once the site has been checked an confirmed worthy for the cleaning iperation to commence, the operators will start packing and securing the “Residual
Waste” identified and catalogued as “Dangerous” first. These will be removed to an identified secure storage area to be dealt with appropriately. Dangerous
residual waste must be securely removed followed by Non-dangerous residual waste. Any material required to be disposed of off-site will be taken off site
in bin containers and delivered to suitably licensed disposal and/or recycling centres. Any hazardous or suspected hazardous materials will be removed
from site by a licensed waste disposal contractor in accordance with the COSHH Regulations. All relevant Duty of Care arrangements and waste transfer
notes will accompany each bin consignment taken off site. All items of salvage value will be removed from site promptly to prevent the temptation for
unauthorized access onto the site.
GROUND EXISTING LAYOUT GROUND- SCOPE OF WORKS

No. Existing Space Demolition work

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Masonry wall to be carefully demolished.
1 X-Ray/Ultrasound - All tiles to be removed.

- Doors and windows to be carefully removed.


- All electrical fittings to be removed carefully for reuse.
- Decommission AC units.
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Masonry wall to be carefully demolished.
2 Observation Room - All tiles to be removed.

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Masonry wall to be carefully demolished.
3 Dark Room - All tiles to be removed.
- All electrical fittings to be removed carefully for reuse.
- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Masonry wall to be carefully demolished.
4 Consulation room - All tiles to be removed.

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Door to be removed.
5 Doctor’s room - Masonry wall to be carefully demolished.

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Door to be removed.
6 Reception - Masonry wall to be carefully demolished.

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Door to be removed.
8 Corridor - Masonry wall to be carefully demolished.

- All electrical fittings to be removed carefully for reuse.


- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Door to be removed.
9 Kitchen and Storage area - Masonry wall to be carefully demolished.
- All electrical fittings to be removed carefully for reuse.
- Decommission AC units
- Plumb fittings to be removed and all water pipes to be plugged.
- Glass windows to be removed carefully.
- Door to be removed.
10 Waiting Area - Masonry wall to be carefully demolished.

GROUND FLOOR-PROPOSED NEW WALLS LAYOUT


No. Proposed Space Construction work to be done
- New walls constructed
- Replacing tiles with clients approved tiles
- New leaded door to the exam room
- Ceiling to be done to clients aproval
- Desk added to client’s spproval
- Counter top for equipment
- Counter top with sink,base and wall cabinets added to clients approval
- Lead glass window
- X-Ray on warning light
- Casework for storage of service materials
1 CT Exam Room - Main disconnect control to be added

- Replace tiles with clients approved tiles.


- Leaded door to be added
2 recovery Room - Ceiling to be done to the clients approval

- Table to be added
- Wallstand to be added
- Control console
- Counter top for eqiupment to clients specifications
- Control wall to ceiling with lead glass viewing window
- Leaded door to clients specifications
- Warning light indicating X-Ray on
- X-Ray room warning light control panel,reference, junction point
- Emergency off switch
3 X-Ray Room - Main disconnect

- Leaded door to be included


- Replacing tiles with clients approved tiles
- Demarcate doors and new walls
- Apply three coats of semi-gloss Crown Silk Vinyl paint with a roller on one coat of Crown Vinyl
Matt emulsion of the same shade to plastered surfaces or approved equivalent to walls
- Create new cabinetry with a granite top
4 Control Room - Ceiling to be done to the clients approval
- Include dado rail.
- Replacing tiles with clients approved tiles
- Apply three coats of semi-gloss Crown Silk Vinyl paint with a roller on one coat of Crown Vinyl
Matt emulsion of the same shade to plastered surfaces or approved equivalent to walls
5 Corridor - Ceiling to be done to the clients approval

- Ensure all floor ducts are filled with concrete and tiles on top
- New leaded door
- Apply three coats of semi-gloss Crown Silk Vinyl paint with a roller on one coat of Crown Vinyl
Matt emulsion of the same shade to plastered surfaces or approved equivalent to walls
5 UPS room - Ceiling to be done to the clients approval

- Replacing tiles with clients approved tiles


- Apply three coats of semi-gloss Crown Silk Vinyl paint with a roller on one coat of Crown Vinyl
Matt emulsion of the same shade to plastered surfaces or approved equivalent to walls
- Ceiling to be done to the clients approval
- Install security CCTV
6 Reception/Cashier - Security glass to be installed at the cashier section

- Replacing tiles with clients approved tiles


- Apply three coats of semi-gloss Crown Silk Vinyl paint with a roller on one coat of Crown Vinyl
Matt emulsion of the same shade to plastered surfaces or approved equivalent to walls
7 Waiting Area - Ceiling to be done to the clients approval