You are on page 1of 11

LABOUR COST ESTIMATE AND MATERIAL ESTIMATE FOR 2BED AND 1BEDROOM FLAT 6F

S/NO DESCRIPTION QUANTITY RATES AMOUNT

Foundation to Dpc material

1 sand 13 17000 221000

2 laterite 40 13000 520000

3 chippings 84 6400 537600

4 cement 319 2500 797500

5 binding wire 2 7500 15000

6 16mm rod 67 2880 192960

7 12mm rod 47 1620 76140

8 8mm rod 63 800 50400

9 2*2*16 hard wood 35 400 14000

10 1*12*12 board 100 850 85000

11 3" nail (bag) 1 9000 9000

12 9" vibrated blocks 2880 160 460800

13 pegs 6 400 2400

14 water tanker 7 6000 42000

TOTAL 3023800

LABOUR COST FOUNDATION TO DPC


1 setting out 1 40000 40000

2 excavation of foundation strips 1 100000 100000

3 excavation of column base 45 400 18000


carpentry formwork for starter
4 columns and dpc 1 40000 40000
Fabrication of starter columns and
5 basket 45 1500 67500
Casting of foundation, columns,
6 German floor 278 500 139000

7 Brickwork 2880 50 144000

8 Filling/Compaction/back fill 1 80000 80000

9 fabrication of foundation beam 1 15000 15000

10 supervision 1 150000 150000

TOTAL 628500

GROUND FLOOR TO SLAB(DECK) MATERIAL ESTIMATE

1 Sand 13 17000 221000

2 Chippings (tonnes) 76 6400 486400

3 Cement 316 2500 790000

4 Binding wire 5 7500 37500

5 16mm rod 145 2880 417600

6 12mm rod 317 1620 513540


7 8mm rod 190 800 152000

8 2*4*16 hard wood 244 750 183000

9 1*12*12 board (for deck) 540 1200 648000

10 1*12*12 board (lintel&columns) 240 850 204000

11 Nail 4 9000 36000

12 bamboo stick(for deck) 280 200 56000

13 9" vibrated blocks 4534 160 725440

14 Electrical Material 1 350000 350000

TOTAL 5527880

LABOUR COST GROUND FLOOR TO SLAB

1 Brickwork 4534 50 226700

2 Fabrication of Column 45 800 36000

3 Fabrication of Lintel 1 50,000 50000

4 Fabrication of slab/staircase 1 150000 150000

5 Carpentry 1 100000 100000


Construction of formwork for deck
6 and staircase 1 220000 220000

7 Electrical piping 1 50000 50000


8 Casting of slab 190 600 114000

9 casting of lintel&column 62 500 31000

10 supervision block work 1 100000 100000

11 supervision slab 1 100000 100000

TOTAL 1177700

FIRST FLOOR TO ROOF BEAM MATERIAL ESTIMATE

1 Sand 6 17000 102000

2 Chippings 30 6400 192000

3 Cement 1 2500 2500

4 Binding Wire 1 9000 9000

5 16mm Rod 47 2880 135360

6 12mm Rod 96 1620 155520

7 8mm Rod 128 800 102400

8 Nail 2 9000 18000

9 1*12*12 board 200 850 170000

10 9" vibrated blocks 4508 160 721280

11 Plumbing Materials(lump sum) 1 353040 353040

TOTAL 1961100

LABOUR ESTIMATE FROM FIRST FLOOR TO ROOF BEAM

1 Brickwork 4508 50 225400


2 Moving of blocks upstairs 4508 30 135240

3 Fabrication of Lintel 1 50000 50000

4 Fabrication of Roof beam 1 20000 20000

5 Fabrication of columns 45 800 36000

6 form work lintel and columns 1 140000 140000

7 Form work for roof beam 1 70000 70000

8 Plumber Piping 1 160000 160000

9 Casting of lintel/columns 75 600 45000

10 supervision 1 80000 80000

TOTAL 961640

GRAND TOTAL FOR LABOUR COST ESTIMATE/MATERIAL ES 13280620


AND 1BEDROOM FLAT 6FLAT BUILDING

REMARKS

rough estimate

You might also like