Professional Documents
Culture Documents
BRE329
D
Department
t t off Building
B ildi andd Real
R l Estate
Et t
The Hong Kong Polytechnic University
Hong Kong SAR
Introduction
Variations
Thinkk about
Thi b
• If there is no express term in dealing with variation in a
contract what will be the contractual situation if one of the
contract,
contract party wants to make a change to the scope of works
in a contract?
Certificates
Think about
• What is the contractual position of the Employer if she does
not agree with the Architect’s certificate?
• As a client of the Architect,
Architect can the Employer request for a
change of judgement in a certificate?
Expected
p learningg outcome
• Able to interpret and apply the general principles in relation to contract
administration under the Standard Form of Building Contract
• The learning focus is to develop your critical thinking skill and domain
specific knowledge in the context construction contract administration.
Approach
• Introduction of key terms and concepts
• Outline of key provisions in the SFBC
• Develop the skill in the interpretation of contract by analysis of specific
clause in class
The learning focus
• Variations: The stipulated procedure, the rules of valuations
• Certificates: The stipulated
p p
procedure and their implications
p
• Discussion of the differences between the old and the new SFBC
Variations
• “The disadvantage of such a clause is that it allows the architect, or the other designers,
to delay making some decisions almost until the last possible moment. This can have
serious repercussions on the planning of the project and in executing the works
efficiently by the contractor.”
• “The
The building owner (Employer )will be bound by any variation give by the architect as
long as the architect does not exceed the powers under the terms of contract.”
Think
Th k about
b
• What constitute a variation? How do we known the limit of the power?
• What if the nature of the variation is substantially different from the contract
document?
– to set out the procedures to deal with the complexity and uncertainties in
construction contract, and
– to set out the rules governing the adjustment of the contract sum with
reference to the original contract works and contract price.
1. The definition
2 The
2. Th administration
d i i i
3 The rules of valuations
3.
4. The provisions for direct loss and / or expenses
Variations under
V d the Standard
d d Form
Architect’s Instruction
(1) “The MC shall …comply with all instructions issued to him by the Architect in
regard to any matter in respect of which the Architect is expressly empowered by
these Conditions to issue instruction.”
 MC’s obligation to comply
 The Architect’s authority and the subject matter are defined and limited by the
express provisions stated in these Conditions
See Hills (2001) p.89 for a detailed list of provisions
Variations under the Standard Form
The definition
“The term “variation” … means
• The alternation or modification of the design, quality or quantity of the Works as shown
upon the Contract Drawings and described by or referred to in the Contract Bills, and include
• The addition, omission or substitution of any work,
• The alteration of the kind or standard of any of the materials or goods to be used in the
Works, and
• The removal from the site of anyy work, material or goods
g executed or brought
g thereon
by the MC … other than work, material or goods which are not in accordance with this
Contract.”
The Works = The contract works defined byy the Contract Document
• Therefore, under a “Contract with Quantities”, it refers to the
Contract Drawings and the Contract Bills
Removal of works, material not in accordance with Contract is not a
variation. Why?
• Cl. 6(4) “The Architect may issue instruction in regard to the removal from the site of
any work, materials or goods which are not in accordance with this Contract.”
The following three questions help to select the appropriate rules to be applied.
1. Can the work be properly measured and valued?
2. Is the works of a similar character?
3. Is the works being executed under similar conditions?
START
Yes
No
Is the work the same in character but Contract bill rates are to be used as a basis
Yes for valuation i.e. pro rata rates
executed under different conditions?
No
No
The critical issue is the knowledge of the operations and the application of reasonable
professional
f i l judgment
j d supportedd by
b sensible
ibl analysis
l i andd iinformation..
f i
e.g. Allow
ll for
f the
h design
d i andd construction
i off temporary working
ki platform
l f
Loss and expense in regard to Variations
Cl.11(6) If upon written application being made to him by the MC, the Architect is of
p
the opinion that a variations or … has involved the MC in direct loss and //or direct
expenses for which he would not be reimbursed by payment in respect of a
valuation made in accordance with the rules contained in sub-clause (4) of this
pp
Condition an dif the said application is made within a reasonable time of the loss
and expense have been incurred, then the Architect shall either himself ascertain or
shall instruct the QS to ascertain the amount of such loss or expenses.
( l 11(6) removedd from
(cl.11(6) f the
h 2005 edition)
di i )
• Wh iis the
What h ground
d ffor entitlement?
il ?
• How to apply?
• H to assess??
How
• Who will assess?
• Wh t iis th
What the difference
diff from
f 11(4)?
Think about
Are there any change in aspects of
((1)) the definition of variation,
(2) the administrative procedure, and
(3) the rules of valuation, in the new version of SFBC?
REFERENCE
F NC
Contractual Procedures in the Construction Industry, 2006, Allan
Ashworth, Pearson Education Ltd. Ch.23