Professional Documents
Culture Documents
very stringent rule and as such there are exceptions to the rule, first being the
is divided into several parts and payments for the parts that have been completed
can be claimed. In the case Richie v Atkinson where by contract the claimant
agreed to carry a cargo of specified quantity of hemp and iron. The price agreed
was £5 per ton for the hemp and 5 shillings per ton of iron. The claimant only
carried part of the agreed quantity. The defendant argued the contract had not been
fully performed and therefore no payment was due. It was held that the contract
could be divided into separate parts as the parties had agreed a price per ton. The
claimant was thus entitled to payment for the amount carried although the
where one party freely agrees to accept partial performance, then a sum is payable
for the work completed, the main focus being on free or willing acceptance by the
party. In the case Sumpter v Hedges, the claimant agreed to build two houses and
stables for the defendant. It was agreed that £565 would be payable on completion.
The claimant began performance and then ran out of money and was unable to
complete. He had performed just over half of the contract, after which the
defendant decided to complete the work himself. The claimant sought to recover
£333 which is the value of the work that had been completed. He argued that in
completing the work himself, the defendant had thereby accepted partial
performance and prevented the claimant from completing the contract. It was held
that the claimant's action failed. The court held that the defendant had no choice
but to accept partial performance as he was left with a half completed house on his
land therefore it was not a free or willing acceptance of the part performance.
the performance then the other party is entitled to payment for the work which has
claimant agreed to write a book on costume and armor for the defendant as part of
a series called 'the Juvenile Library'. The agreed contract price was £100 to be
great deal of it when the defendant cancelled the series. The defendant refused to
pay the claimant despite his undertaking and the fact that the claimant was still
held that claimant was entitled to recover £50 because the defendant had prevented
perform and tries to tender performance but the other party does not accept the
performance then the party seeking to tender performance is discharged from the
contract and the non accepting party is liable in damages for non acceptance.