16. The following one is not the fixed point of the 210 MW KWU turbine supports
a) Front bearing pedestal of LP turbine
b) Rear bearing Pedestal of LP turbine
c) Thrust bearing housed in the rear bearing pedestal of HP turbine
d) Front bearing pedestal of HP turbine
17. The purpose of providing a journal bearing to support the turbine rotor is
a) They are having high loading capacity
b) It employs a hydrodynamic lubrication
c) They are having high reliability and absence of wear
d) All the above
18. The main purpose of booster pump in series at main BFP suction is to
a) add more flow or capacity
b) to increase NPSH available at main pump suction.
c) to utilize or conserve the motor free end power
d) to maintain supply of water to boiler drum in case of main pump fails
19. The speed of boiler feed water pump is
1] 5000 rpm
2] 1500 rpm
3] 30 – 85 rev per sec
4]1500 rev per sec
20. The type of 210 MW boiler feed water pump is of
a) multistage double volute casing design
b) cartridge – barrel casing design
c) double suction vertical can design
d) multistage radial piston design
21. The following statement is not true regarding the compounding of turbines
a) The compounding of steam turbine is done to allow greater heat drop without increasing the
speed
b) In pressure compounded turbine, the pressure
c) Pressure compounded turbines are having higher efficiency than velocity compounded turbines
d) Velocity compounded turbine costs lesser than pressure compounded turbine of same capacity
22. In which turbine velocity compounding is utilized?
a. Parson turbine
b. Curtis turbine
c. Rateau Turbine
d. None of the above
23. The following statement is not true regarding barrel type casing
a) It consists of two shells (inner and outer)
b) Inner shell is spilit and carries the guide blades
c) Outer shell is not spilit and have uniform wall thickness
d) None of the above
24. In IP turbine (KWU), the gap between the inner and outer shell is filled with
a) Exhaust steam of the turbine
b) Inlet steam of the turbine
c) PRDS steam
d) Steam is not filled
25. __________________ type of rotors are generally used in high pressure end
a) Built-up type rotor
b) Welded disc type rotor
c) Integral rotor
d) None of the above
26. Generally turbine rotors are made up of _______________ material
a) Carbon steel
b) Chromium, molybdenum, vanadium steel
c) Copper
d) Stainless steel
27. In moving blades of the steam turbine, the following energy transfer takes place
a) Potential energy to kinetic energy
b) Kinetic energy to mechanical energy
c) Thermal energy to mechanical energy
d) None of the above
28. The reason for making the LP turbine as double flow
a) To make the layout easier
b) Steam can be distributed uniformly into the condenser
c) It decrease the size of last stage blades by decreasing the volume of steam
d) To allow for free expansion of the casing
29. The axial force on the turbine rotor will be more for
Reaction turbine
Impulse turbine
Radial flow turbine
Tangential turbine
30. In 210 MW KWU unit the main oil pump is driven by
a) 6.6 KVA 3 phase A.C motor
b) HP turbine though gear coupling
c) Separate steam driven turbine
d) It is directly driven by turbine through rigid coupling
31. The purpose of a injector in the turbine lub oil system is
a) To provide a low pressure oil to bearings
b) To provide the lubricating oil during the turbine tripping
c) To provide the oil supply to bearings incase of failure of DC pump
d) To provide the necessary suction pressure to main oil pump
32. The following one is not true in case of main oil pump
a) Main oil pump is located in the front pedestal of HP turbine
b) It is connected with HP turbine
c) It is wanted over the cover plate of the main oil tank
d) It is the pump which will be in service when the turbine is an load
33. The purpose of a jacking oil steam is
a) To provide necessary lubrication when main oil pump fails
b) To provide necessary lubrication when auxiliary oil pump fails
c) To lift the rotor when the turning gear is in service
34. The function of a governor in a steam turbine is
a) only to regulate the mean speed of the turbine during changes in the loading
b) only to vary the load on the machine as per the requirements of the operator
c) To control the speed of the turbine during speed raising only
d) All the above
35. The following statement is not true regarding by-pass governing
a) It consists of main and by-pass valve
b) By pass valve admits the steam after the first few stages of the turbine
c) Main and by-pass valve each having 50% capacity
d) When the load is more than 80% of the load will be control by by-pass valve alone
36. The following one is not true in case of Nozzle control governing
a) The first stage of the nozzle is divided into number of nozzle groups
b) Each nozzle group is supplied with steam by separate valves
c) Depending upon the load variation the system is throttled in pre-arranged sequence one after
other
d) The steam input is varied by simultaneous operation of control valves.
37. In hydro mechanical governing system _________ is the speed sensing element
a) Halls probe
b) Hydraulic speed transmitter
c) Speed governor
d) Governor impeller
38. In case of hydro mechanical governing system the following component does not take part in the
normal governing process
Intermediate pilot valve
Control valve servo motor
Differentiator
Summation pilot valve
39. In 210 K.W.U Governing system the auxiliary trip oil circuit is connected between the following
components
a) Stop valve servomotor and control valve servo motor
b) Main trip valve and stop valve servo motor
c) Hydraulic protective devices and Main trip valve
d) Startup & and load limiting device and control valve servo motor
40. During the ATT test for over-speed, the fly bolt operation is checked by
a) Reducing the trip oil pressure
b) Actually raising the turbine speed to the overspeed set value
c) Both a & b
d) Increasing the test oil pressure
41. In _____________ the steam is ejected at a pressure higher than atmospheric pressure
a) Condensing turbine
b) Back pressure turbine
c) Pass out turbine
d) Low pressure turbine
42. In cold reheat (CRH) line reversal of steam flow from reheater to HP turbine is prevented by
a) Control valve
b) Stop valve
c) Non return valve
d) Any of the above
43. In a210 MW KWU unit , the rotor of the individual cylinders are connected by
a) Flexible coupling
b) Welding
c) Solid coupling
d) Any of the above
44. The following one is the fixed point of the turbine rotor
a) Front bearing pedestal of HP turbine
b) Front bearing pedestal of LP turbine
c) Rear bearing pedestal of LP turbine
d) Thrust bearing housed in the rear bearing pedestal of HP turbine
45. In 210 MW KWU unit the thrust bearing is kept
a) In between HP and LP turbine
b) In between IP and LP turbine
c) Rear end of LP turbine
d) Front pedestal of HP turbine
46. The leak off steam from the external glands of the turbine cylinder goes to
a) Deaerator
b) LP heaters
c) Condenser
d) Gland steam cooler
47. When by-pass system is required
a) during startup
b) during turbine trip
c) higher steam pressure
d) all the above
48. From the following which one is not true with respect to regenerative feed heating system?
a) It improves cycle efficiency
b) Decreasing pumping power
c) Less cooling water required
d) Bigger condenser required
49. Air lines from HP heater side is connected to
a) Deaerator
b) Condenser
c) Ejector
d) None of the above
50. BFP balancing drum/piston is located at ___________
a) Suction side of the BFP
b) At 3rd stage of BFP
c) Discharge side of the BFP
d) All the above
ELECTRICAL
1. Turbo Generator Rotor is of
a. Salient pole laminated type
b. Non-salient pole laminated type
c. Non-salient pole solid type
d. Salient pole solid type.