APPENDIX 1

Computations

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

Signalized Intersection Computations

Cycle Time for all Movement, C = 195 sec

Adjustment Factor for Pre Timed Intersections, k = 0.5

Period of Analysis, T = 1 hr

Phase 1 Movement 1

Given Values:

g = 42 sec SFR = 6800 pcu/hr

V = 2585

c = SFR (g/C)

c = 6800(42/195)

c = 1464.62

X = V/c

X = 1.76

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

42
0.5 (195) ( 1- 195)
d1 =
1.76(42)
1- ( 195 )

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

d1 = 123.42 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(1.76)
d2 = 900(1) [(1.76-1) + √(1.76-1)2 + ]
1550.77(1)

d2 = 1379.77 sec

Total Delay, TD = d1 + d2 = 1503.29 sec - LOS F

Phase 1 Movement 4

Given:

g = 109 sec SFR = 6800 pcu/hr

V = 2984

c = SFR (g/C)

c = 6800 (109/195)

c = 3801.03

X = V/c

X = 0.79

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

109
0.5 (195) ( 1- 195 )
d1 =
0.79(109)
1- ( 195 )

d1 = 76.62 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.79)
d2 = 900(1) [(0.79-1) + √(0.79-1)2 + ]
3801.03(1)

d2 = 1.72 sec

Total Delay, TD = d1 + d2 = 78.35 sec - LOS E

Phase 2 Movement 6

Given:

g = 37 sec SFR = 5250 pcu/hr

V = 546 pcu/hr

c = SFR (g/C)
c = 5250(37/195)
c = 996.15 pcu/hr

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

X = V/c

X = 0.55

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

37
0.5 (195) ( 1- )
d1 = 195
0.55(37)
1- ( 195 )

d1 = 88.17 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.55)
d2 = 900(1) [(0.55-1) + √(0.55-1)2 + ]
996.15(1)

d2 = 2.19 sec

Total Delay, TD = d1 + d2 = 90.36 sec - LOS F

Phase 2 Movement 7

Given:

g = 37 sec SFR = 5250 pcu/hr

V = 722 pcu/hr

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

c = SFR (g/C)

c = 5250(37/195)

c = 996.15 pcu/hr

X = V/c

X = 0.72

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

37
0.5 (195) ( 1- 195)
d1 =
0.72(37)
1- ( )
195

d1 = 91.60 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.72)
d2 = 900(1) [(0.72-1) + √(0.72-1)2 + ]
996.15(1)

d2 = 4.71 sec

Total Delay, TD = d1 + d2 = 96.31 sec - LOS F

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

Phase 3 Movement 9

Given:

g = 35 sec SFR = 5250 pcu/hr

V = 462 pcu/hr

c = SFR (g/C)
c = 5250(35/195)

c = 942.31 pcu/hr

X = V/c

X = 0.49

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

35
0.5 (195) ( 1- 195)
d1 =
0.49(35)
1- ( 195 )

d1 = 87.72 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.49)
d2 = 900(1) [(0.49-1) + √(0.49-1)2 + ]
942.31(1)

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

d2 = 1.83 sec

Total Delay, TD = d1 + d2 = 89.55 sec - LOS F

Phase 3 Movement 10

Given:

g = 35 sec SFR = 5250 pcu/hr

V = 919 pcu/hr

c = SFR (g/C)
c = 5250(35/195)
c = 942.31 pcu/hr

X = V/c

X = 0.98

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

35
0.5 (195) ( 1- )
d1 = 195
0.98(35)
1- ( 195 )

d1 = 96.98 sec

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.98)
d2 = 900(1) [(0.98-1) + √(0.98-1)2 + ]
942.31(1)

d2 = 39.78 sec

Total Delay, TD = d1 + d2 = 136.75 sec - LOS F

Phase 4 Movement 3

Given:

g = 67 sec SFR = 6800 pcu/hr

V =741 pcu/hr

c = SFR (g/C)

c = 6800(67/195)

c = 2336.41 pcu/hr

X = V/c

X = 0.32

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

g
0.5 C ( 1- C)
d1 =
Xg
1- ( C )

67
0.5 (195) ( 1- 195)
d1 =
0.32(67)
1- ( 195 )

d1 = 72.18 sec

8kIx
d2 = 900T [(X-1) + √(X-1)2 + ]
c𝑇

8(0.5)(1)(0.32)
d2 = 900(1) [(0.32-1) + √(0.32-1)2 + ]
2336.41(1)

d2 = 0.36 sec

Total Delay, TD = d1 + d2 = 72.18 sec - LOS

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

Proposed Unsignalized/Freeway Computations

Minimum design speed for freeway, Umin = 80kph

Freeway Movement 7

Given:

q = 959 veh/hr

u = 80 km/hr

q
k=
u

959
k=
60

k = 15.98 veh/km - LOS C

Freeway Movement 10

Given:

q = 673 veh/hr

u = 80 km/hr

q
k=
u

673
k=
60

k = 11.23 veh/km - LOS C

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

U turn Capacity
qc
c=1545-790e3600 pcu/hr per lane

qc = 0

c = 1510 pcu/hr for two lanes

U turn Capacity Movement 9

Given:

V = 546 pcu/hr

c = 1510 pcu/hr

V/c = 0.36 - LOS B

U turn Capacity Movement 6 and 3

Given:

V = 1347 pcu/hr

c = 1510 pcu/hr

V/c = 0.89 - LOS D

COLLEGE OF ENGINEERING, COMPUTER STUDIES AND ARCHITECTURE


LYCEUM OF THE PHILIPPINES UNIVERSITY - CAVITE

Weaving/Merging Movements

Given:

Umin = 37.2823 mi/hr = 60 kph N = 2 lanes

Umax = 49.7097 mi/hr = 80 kph

Uave = 43.496 mi/hr = 70 kph

Merging Movement 1 and 6

V = 526 pcu/hr + 2585 pcu/hr

V = 3111 pcu/hr

V⁄
k= N
Uave

3111⁄
k= 2
62.1371

k = 31.49 pcu/mi LOS D

Merging Movement 4 and 9

V = 462 pcu/hr + 2984 pcu/hr

V = 3446 pcu/hr

V⁄
k= N
Uave

3446⁄
k= 2
62.1371

k = 34.66 pcu/mi LOS D