ID Task Name Duration Start Finish Predecessors 21 Nov '17 28 Nov '17 05 Dec '17 12 Dec '17 19 Dec '17 26
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 Proposed Interior works to be carried out at Delhi 29 days Wed 23-11-16 Sun 25-12-16

2 Dismantling and carting away from site 1 day Wed 23-11-16 Thu 24-11-16

3 Airconditiong Lowside works 6 days Thu 24-11-16 Wed 30-11-16 2

4 Tile flooring 5 days Mon 28-11-16 Sun 04-12-16 3FS-2 days

5 Partitions (without glass) 5 days Sun 04-12-16 Fri 09-12-16 4

6 Ceiling 6 days Thu 01-12-16 Thu 08-12-16 3,4FS-2 days

7 Glass paritions + Doors 2 days Wed 07-12-16 Fri 09-12-16 5FS-2 days

8 Painting 1 wk Tue 06-12-16 Tue 13-12-16 6FS-2 days

9 Furniture Delivery 2 wks Thu 24-11-16 Wed 07-12-16 2

10 Furniture Assembly 5 days Wed 07-12-16 Tue 13-12-16 9

11 Existing systems check (Fire alarm + Light fixture) 5 days Sun 04-12-16 Fri 09-12-16 4

12 Toilet Fixtures 3 days Sun 11-12-16 Wed 14-12-16 8FS-2 days

13 Snaglist 10 days Wed 14-12-16 Sun 25-12-16 12

Project: Gant Chart-23-11-2016 Task Progress Summary External Tasks Deadline


Date: Wed 23-11-16 Split Milestone Project Summary External Milestone