Professional Documents
Culture Documents
Acknowledgements
We would like to sincerely acknowledge Ministry of Local Development, Department of Local Infrastructure
Development and Agricultural Roads (DoLIDAR) for providing this opportunity.
We hope that the study truthfully reflect to solve the present solid waste problem of Phhhikal VDC, Illam District and
their desire to implement the proposed project. This Landfill site project will create better environmental condition
within the Area.
The Consultant would like to express their gratitude to Senior Divisional Engineer Kumar Thapa, Er. Raju Shrestha
for their valuable suggestion and cooperation. The Consultant would like to express their gratitude to, Local
Development Officer, District Technical Officer, Secretary of Phikal VDc and other members of Illam District office
for their kind support and cooperation during the field survey and providing additional data during design stage.
This report has been prepared and submitted by Engineering and Educational Services Pvt. Ltd. This report is an
outcome of the Detailed Survey, Design and Cost Estimate of Infrastructure Development Works at
Proposed Phikal Landfill Site at Illdam istrict. This report is produced from the team works of e2 services team
and hopes same in future. Special thanks for survey and design team members Dr. Shaphal Subedi, Er.Niranjan
Pudasaini, Er. Shambhu Sharan Baral and other team members for their great and sincere effort.
……………..
Mr. Rajeeb Baral
Contents
Acknowledgement ……………………………………………………………………………………………………………………………………………….i
Sailent Features........................................................................................................................................................v
1 THE PROJECT.........................................................................................................................................................1
1.1 Background.....................................................................................................................................................1
1.3 Objective........................................................................................................................................................2
4 METHODOLOGY...................................................................................................................................................11
5.13.5 Design..................................................................................................................................................27
5.14 Landscaping................................................................................................................................................30
5.15 Fencing.......................................................................................................................................................30
5.21 Precaution Measures for Bird Hazard Control at the SLF – site...................................................................33
Sailent Features
General :
o Base Year Population: 5000 in Phikkal and 9885 in VDC(base year 2011)
o Population for next 20 yrs : 12313
o 3days waste production(35 house): 71.5kg
o 3days waste production(hotel): 77.5kg
o 3days waste production(office): 7.5kg
o Waste generation: (156.5/317)=/0.16 kg/person/day.
o Daily Waste Production: 2 ton ( approax).
Structure :
1 THE PROJECT
1.1 Background
Phikkal Bazar Village Development Committee is situated in Mechi Zone, Illam district in the mountainous region
of Eastern part of Nepal. It is one of the most Municipality oriented V.D.C.s of Nepal. Phikkal Bazar VDC covers an
area of 28.1 sq.km , and PhikkalBazar with area around 3.77 sq.km is one of the major town in Illam which is on the
process of gradual expansion. This town area with basic infrastructures comprises one out of nine wards of the
V.D.C.
Phikkal currently generates about 2 tons of wastes every day. Main ingredients of such wastes are organic wastes,
plastics and papers. Households and hotels are the key to generate the wastes. Because of absence of practice of
4-R (Refuse, Reduce, Reuse, and Recycle) activities almost all the collected wastes are transported to the dumping
site at Bandevi 2km from Phikkal bazar. Due to strong opposition from local residents and lack of enough area for
further dumping, Phikkalis currently facing a problem of solid waste disposal. Realizing this fact, district office had
identified the landfill site (LFS) at Phikkal-5 Dhode at a distance of 6.5 km from core town
Upon the request of Illam District, Department of Local Infrastructure Development and Agricultural Roads
(DoLIDAR), under the Ministry of Federal Affairs and Local Development is entrusted for planning and
management of solid waste including sanitary landfill site for disposal of solid waste of Phikkal. For this purpose,
DoLIDAR has initiated works of the solid waste landfill site with all mitigating measures regarding the environmental
aspects of the entire area. The purpose of this project is to develop a long-term sanitary landfill site within the
selected area of about 7 ropani at Fikkaal-5, Dhode, Illam including a leachate collection tank and primary treatment
plant (Constructed wetland) and other necessary infrastructures.
1.2 Introduction to Solid Waste Management
Since the beginning, human has been generating waste. With the progress of civilization, the waste generated
became of a more complex nature. The increase in population and urbanization was largely responsible for the
increase in solid waste. Each household generates garbage or waste. Items that we no longer need or do not have
any further use fall in the category of waste, and we tend to throw them away. The wastes generated in solid state
as a result of various human activities and normally described as useless and unwanted material are known as
solid waste. Solid wastes are those waste materials that are not easily carried by water or air flows (solid or semi
solid). Solid waste may be defined as any discarded material that is not especially of solid waste. Discarded means
that the material is abandoned recycled or considered inherently waste like. Solid waste is relative and subjective.
This is the most seeable and the ignored problem of today’s world. World is finite, if this uncontrolled pollution of
solid waste is not ratified in time, this is going to bring a big disaster in our society. The subject of Solid Waste
Management (SWM) is timely and important .Population growth, rapid urbanization, establishment of commercial
and industrial Sectors, change in living Standard, and several other factors have changed the solid waste status
and composition. Waste management involves the collection, transportation, processing (waste treatment) and
disposal of waste materials, usually ones produced by human activity, in an effort to reduce their effect on human
health, and natural world and its environmental balance .In recent decades waste management has been focusing
in recovery of resources from the wastes. Waste management practices differ for urban and rural areas and for
household, industrial, and commercial producers.
Solid wastes can be broadly classified into three types: municipal solid waste, Bio-medical solid Waste and
Industrial solid Waste. The different techniques practiced in solid waste management are crude dumping, controlled
dumping, sanitary land filling, incineration, and deep well disposal. Crude dumping is often seen in the
municipalities of the developing nation which has a harsh environmental impact. These all methods of the waste
management are the methods of managing the waste once it comes out from the household or commercial and
institutional periphery. Apart from the management of the waste at the disposal site, source reduction and utilization
is another prospect of management. There is a universal formula for the source reduction of the solid Waste
i.e. 4-R (Refuse, Reduce, Reuse, Recycle). Instead of buying new containers from the market, use the one that is
Engineering and Educational Services Pvt. Ltd Page 1
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
already in the house. Refuse to buy new items though you may think they are prettier than the one you already
have. This example easily illustrates the concept of refuse. Reduce refers to reduction of the waste at the source so
that the waste load at the disposal site get reduced. Composting is the best practice for the reduction of the organic
waste at the household level. The process of extracting resources or value from waste is variously referred to as
recycle. Reuse is the term for maximum utilization of the resource that otherwise be the part of the municipal waste.
Some waste management experts have recently incorporated a 'fifth R': "Rethink", with the implied meaning that the
present system may have fundamental flaws, and that a thoroughly effective system of waste management may
need an entirely new way of looking at waste.
In context of Nepal, Irrigation, River Control & Other Infrastructure Development Section of Department of Local
Infrastructure Development and Agricultural Roads (DoLIDAR) is also acting as the Governmental agency
responsible for solid waste management. However, The Local self-governance act 1999 allocated most of the
operational level function of solid waste management to the municipality and Solid Waste Management and
Resource Mobilization Centre (SWRMC) under the Ministry of Federal Affairs and Local Development (MoFALD) is
now responsible for developing policies, identifying and developing landfill/waste disposal site.
1.3 Objective
The main objective of the Project is to improve the overall urban environment and the sanitary living conditions of
people of the Phikkal.
1.4 Specific Objective
The specific objective of the Project is to develop a long-term sanitary landfill site at Dhode ward no-5 Phikkal Illam
for better management of the solid waste generated in the city area of Phikkal.
1.5 The Assignment
The core component of the project is to develop an environmentally safe sanitary landfill site and waste treatment
plant for the sustainable management of the solid waste generated in the Phikkal.
DoLIDAR has decided to develop a long-term landfill site at Dhode about 6.5km far from core city area of the
Phikkal. The landfill site is like a small bowl shaped basin with limited drainage catchment. Proposed landfill site is
surrounded by hard rock side slope from northern, eastern and western parts, hence it seems geologically stable.
Two retaining structures at southern and eastern part of landfill site are proposed to retain the wastes.
Major components of the project are:
A sanitary landfill area with provisions of mineral liner basement.
With the provision of leachate collection tank and primary leachate treatment pond, this will dry up the
landfill area..
1.6 Scope of Work
The major scope of work comprised developing of sanitary landfill site and a leachate collection tank at Dhode for
the sustainable management of the solid waste generated from the Phikkalas a long term alternate. The specific
areas of activities under the assignment were:
• Assessment of various mitigation measures as identified by the Initial Environmental comprising physical,
chemical. Biological. Socio-economic and cultural baseline conditions in the proposed development area.
• Field verification of topographical map and assessment of various components proposed preliminarily in the
Map.
• Detailed survey, design and cost estimate of LFS and leachate collection tank at Phikkal. Covering an area
of about 6 ropani 12 anna based on the data provided by Illam District office.
Finalization of all components of the LFS required for long term solid waste management of the Dhode, ward
no-5, ,Phikkal, Illam.
The sources of generation of wastages are household, hotels, offices, industries, hospitals, etc. Phikkalcurrently
generates about 2 tons of waste everyday which are collected from city area once in a day and disposed at
dumping site. The sources of generation of wastages are household, hotels, offices, industries, hospitals, etc.
Phikkalcurrently generates about 2 tons of waste everyday which are collected from city area once in a day and
disposed at dumping site. The Illam district office has provided solid waste collection services only in city area
which comprises three ward . The averarage per capita household waste generation rate in the city area of
Phikkalwas found as 0.16kg/persoon/day
Compositions of solid wastes in Phikkalare kitchen waste, plastics, papers, agriculture waste, metals, textile, wood,
bones, medical waste and others also. Throwing of waste elsewhere in road ,streets valley areas are likely to
cause nuisance and proper management of waste is most important in Phikkal.Some of the solid waste of the
health post is managed by them at small pit.
Solid waste management has e emerged as a major issue in the city area of Phikkal bazar. In present practice
wastes are disposed in haphazard way. The search for a well planned long g term sanitary land fill site for the final
disposal of wastes at Dhode was identified and surveyed.
2.2 Profile of Phikkal
Illam district is situated in Mechi zone of Eastern Development Region of Nepal. Phikkal a small growing city at
hilltop .It has nine wards among them three wards are connected with city area. Which is expanded to 9 hector is
increasing day by day. Now, Phikkal has fulfilled almost all criteria to be a municipality. About 9900 people lives in
PhikkalV.D.C. among them 5000 people with 800 households’ live in the city area. The Phikkal bazzar is 37km far
from districtt headquarter and there is paved road in three wards.
Figure 2: PhikkalVDC
Background Information:
PhikkalVDC
No: of wards: 9
wards Connected to city area: 4 (3,5,2,6)
Rural wards: 5
Population at city area: 5000
Population growth rate: 1.00%
Built up area of city: 4.5 Sq.km
Religions: Hindu, Buddhist ,Kirat, Christian
Occupation: Agriculture, Animalhusbandrybusiness, service
Principal language: Nepali, Rai , Tamang, Lepcha , Newari
Main rivers and ponds: Jogimai , Siddhi khola, Myau Khola
Solid waste produced/ day: 2 Tones
Radio station : 1 Nos
Local news papers: 1 Nos
Hospitals and clinics: 7(PSC +6 clinic +1 Private hospital) Nos
College: Under construction
Higher secondary schools: 1 Nos
Schools: 16 Nos
Banks: 3 Nos
Small industries: 5(Furniture, dairy, Tea etc.) Nos
Organic Tea industry: 1 Nos
Police camp 1 Nos
Traffic Police camp 1 Nos
From above tables, the total generation in 3 days is 156.5kg from 317 waste generators. So the Waste generation
per capita is 0. 16 kg/person/day.
3.3 Waste Collection, Transfer and Transport
Wastes are collected in weekly basis from Phikkal city area which is transported through a single tractor to the
dumping site at Bandevi situated about 2km far from m the city area. Buckets are kept in various pa art of the city
for collecting wastes. Approximate weekly waste collection is about 14 tons. The s staffs involved and equipment
are given as follows
Table 4 : No Of Staffs Involved At Solid Waste Management
S.n Staff Nos.
1 Supervisor 1
2 Sweeper 5
3 Driver 2
4 METHODOLOGY
4.1 Literature review
The relevant literatures, regulations and laws were reviewed after signing the contract and based on the advanced
principals team was mobilized for further study. The previous reports of similar job were also reviewed.
4.2 Data Collection
Data were collected from primary as well as secondary source. The meteorological data were collected from
Department of Hydrology and meteorology.
Field survey was carried out for topographic detail and other relevant data collection. The survey team was lead by
engineer with overseer and other helping member. Consultation with client was also carried out by the team.
6.75
Total Area used for Landfill site 3435.22 100.00%
The site has been designed for safe and environmentally sound disposal of the city waste (i.e. not
for special wastes of hazardous nature) by the method of sanitary land filling. The detailed master plan is shown in
Annex- VI Drawings
5.3 Landfill Area: Life Span and Usage
Life span of the proposed long-term landfill site shall be calculated with due consideration of the
existing waste collection figures provided by the local people of Phikkaland district office of Illam. Based on the
topographical, geotechnical condition and other consideration, the life span of the proposed landfill site is estimated
as 20 years. It is however to be noted that this calculation sets its basic assumption of managing the waste disposal
by the method of sanitary land filling and not by haphazard dumping.
Calculation of Lifespan:
Volume of Accumulated
Waste Disposal
` Soil Cover Waste and soil Volume of Waste
Year Quantity
No cover and soil cover
Population
m³/y(density
t/d t/y m³/year m³ m³
= 1t/m³)
2012 9984 2 730 365 73 438 438
2013 10084 2.01 733.65 366.83 73.366 440.196 878.196
2014 10185 2.03 740.95 370.48 74.096 444.576 1322.772
2015 10287 2.05 748.25 374.13 74.826 448.956 1771.728
2016 10390 2.07 755.55 377.78 75.556 453.336 2225.064
2017 10494 2.08 759.2 379.6 75.92 455.52 2680.584
2018 10599 2.1 766.5 383.25 76.65 459.9 3140.484
2019 10705 2.11 770.15 385.08 77.016 462.096 3602.58
2020 10813 2.14 781.1 390.55 78.11 468.66 4071.24
2021 10922 2.15 784.75 392.38 78.476 470.856 4542.096
2022 11032 2.17 792.05 396.03 79.206 475.236 5017.332
2023 11143 2.18 795.7 397.85 79.57 477.42 5494.752
2024 11255 2.21 806.65 403.33 80.666 483.996 5978.748
2025 11368 2.22 810.3 405.15 81.03 486.18 6464.928
2026 11482 2.24 817.6 408.8 81.76 490.56 6955.488
2027 11597 2.26 824.9 412.45 82.49 494.94 7450.428
2028 11713 2.28 832.2 416.1 83.22 499.32 7949.748
2029 11831 2.29 835.85 417.93 83.586 501.516 8451.264
2030 11950 2.32 846.8 423.4 84.68 508.08 8959.344
2031 12070 2.33 850.45 425.23 85.046 510.276 9469.62
2032 12191 2.36 861.4 430.7 86.14 516.84 9986.46
2033 12313 2.37 865.05 432.53 86.506 519.036 10505.5
2034 12437 2.39 872.35 436.18 87.236 523.416 11028.91
2035 12562 2.41 879.65 439.83 87.966 527.796 11556.71
Year Average y
Return
Periods p w Log-Normal Log-Pearson III
T z y X KT y X
Engineering and Educational Services Pvt. Ltd Page 15
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
1 1 0 -2.516 1.764 58.076 -2.462 1.77 58.884
2 0.5 1.177 -0.001 2.039 109.396 -0.011 2.038 109.144
5 0.2 1.794 0.841 2.131 135.207 0.838 2.131 135.207
10 0.1 2.146 1.282 2.179 151.008 1.288 2.18 151.356
20 0.05 2.448 1.646 2.219 165.577 1.663 2.221 166.341
50 0.02 2.797 2.054 2.264 183.654 2.087 2.267 184.927
80 0.013 2.947 2.226 2.282 191.426 2.266 2.287 193.642
100 0.01 3.035 2.327 2.294 196.789 2.372 2.298 198.609
200 0.005 3.255 2.576 2.321 209.411 2.576 2.321 209.411
300 0.003 3.409 2.749 2.34 218.776 2.816 1.632 42.855
500 0.002 3.526 2.879 2.354 225.944 2.954 2.362 230.144
1000 0.001 3.717 3.091 2.377 238.232 3.179 2.387 243.781
1
p
t
1
w ln 2
p
( 2.51557 0.802585w 0.010328w 2 )
Z w
(1 4.32788w 0.189269w 2 0.001308w3 )
y y z
x 10 y
KT Z Z 2
1
C
s
6
1 3
3
C
C
C 1C
Cs 6 s Z 2 1 s Z s s
6 6 6 3 6
y y K T
x 10 y Figure 8: Calculation of flood
using Pearson III Method
The summary of maximum rainfall of return period 1 to 1000 years is presented in table 8
Hydrological study of the area has been done to design the surface water cut-off drain, which is anessential
component of the landfill site to divert the surface run-off of the uphill from landfill area. Flood Flow For diversion
purpose it is required to know the maximum flood discharges that flow on the uphill side of the Landfill site. One of
the most common methods of qualifying run-off from small watersheds is with empirical formula widely known as
the rational formula, which is based on the criterion that for storms of uniform intensity, distributed evenly equal to a
certain percentage of therainfall intensity occurs when the entire basin area is contributing at the outlet. In the
equationfrom the quantity of flood flows is expressed as follows:
Q = 278 CIA
Where,
Q : Design discharge in l/s
C : Runoff coefficient, which can be taken as 0.4 here,
A : Catchment area in sq.km
I : Rainfall intensity in mm/hr
Catchment Area of Drain (A) = 0.010 Km2
Runoff coefficient (C) = 0.4
Rainfall Flood
Intensity Discharge
S.n Year mm/hr L/sec
1 1 2.437 2.71
2 2 4.553 5.063
3 5 5.634 6.265
4 10 6.299 7.004
5 20 6.915 7.689
6 50 7.679 8.539
7 80 8.022 8.92
8 100 8.237 9.16
9 200 8.725 9.702
10 300 5.451 6.062
11 500 9.502 10.566
Design of drain
1
velocity(V ) * R 2 / 3 * S 1/ 2
n
Field capacity (Capacity of the soil and the MSW to retain moisture) The volume of leachate depends basically on
the rainfall. Leachate is produced not only by runoff but also by rainfall in the area of the landfill, which increases
the quantity, either by direct precipitation on the waste deposited there or by increasing the amount of filtration
through cracks in the terrain
Owing to the different conditions of operation and location of each landfill, the expected rates can vary, so they will
need to be calculated for each individual case. Since it is difficult to obtain local climatologic information, the volume
of leachate produced is often determined by using coefficients that correlate the previously mentioned factors.
Q =l/t P x A x K…………….[1]
8 Adapted from: Lima, Luiz Mario Queiroz. Tratamento do lixo. São Paulo. Hemus. 1991.
Where:
For strongly compacted landfills with a specific gravity > 0.7 t/m 3, the estimated Production of
leachate is between 15 and 25 % (K = 0.15 to 0.25) of the mean Annual precipitation for the
landfill area.
Observations made at several small landfills have confirmed that leachate generation occurs chiefly during rainy
periods and for several days afterwards, and stops during dry periods. It would therefore be a good idea to use an
adaptation of the above method to calculate leachate generation from precipitation during the rainy months and not
during the whole year. This criterion is important when estimating the leachate drainage or storage system for
manual sanitary landfills. Therefore, it is suggested that in equation [1] the precipitation records used be those of
the month of maximum rainfall, expressed in mm/month. This method will give a good approximation of the flow:
Qlm =PmxA xK [2]
Where:
Qlm = Mean leachate flow generated (m3/month)
P = Maximum monthly precipitation (mm/month)
A = Surface area of the landfill (m2)
K = Coefficient that depends on the degree of waste compaction
P = 165.959.0 mm/month
A = 2465.53 m2
K = 0.2 (average of 0.15 and 0.25)
Qlm = 2.73m3/day
Characteristics of leachate from above sources are tabulated in the Table 9. Leachate composition is characterized
by relatively low BOD, TSS and heavy metals and high TDS and Ammonia nitrogen (Sloop et al, 1996) Leachate
also may have high concentrations of heavy metals, pesticides, chlorinated and aromatic hydrocarbons, and other
toxic chemicals, depending on what materials were originally placed in the landfill (Staubitz, 1989).
Variable 1 2 3 4 5
pH 6.8 6.8 7 8 6.7
Ms/
Conductivity cm 2180 165 452 525 20
Dry susbstance g/ l 21.6 2.1 4029 6.18 0.59
Volatile solids Mg/L 12.9 1.36 1.99 0.36 0.39
BOD 7 Mg/L 24000 58 49 <3 46
COD Mg/L 35000 668 1181 <30 165
TOC Mg/L 11200 170 375 1 44
Phosphate-P Mg/L 22 2.6 0.41 0.53 0.003
Tot-P Mg/L 30 4 3 0.56 0.107
Ammonia-N Mg/L 1600 32 470 0 <0.08
Nitrite-N Mg/L 0.12 17.6 0.014 0.015
Nitrite-N Mg/L 0.073 200 3.5 0.008
Tot-N Mg/L 2000 51 690 5.2 1.2
Ca Mg/L 1600 71.6 504 403 22
K Mg/L 2250 170 58.6 958 3.28
Mg Mg/L 292 12.4 59.3 443 3.35
S Mg/L 54.5 23.6 482 1210 4.03
Bule et al
(1997) Urban-Beric O. Sloop et al, Shuckrow et
Parameters Slovenia 1994, Slovenia (1996) USA al,. (1980)
Average daily flow (m3) 26
TSS mg/L 400 173 27.2
TSS mg/L 3944
pH 8 3-7.9
N-NO3 mg/L 89.4
N-NH3 mg/L 88 113 0.01-1000
TKN mg/L 35.5
TN mg/L 245
BOD5 60 98 32.6 42-10,900
COD mg/L 1264 849 484
Basically the design models are characterized by BOD or COD removal of biodegradable organic matters for the
both FWS and SF system constructed Wetlands (USEPA, 1988). The model are designed as an attached growth
biological reactor using the plug flow equation
Ce
e ( ktT )
Co .......................................(i) Where Ce are effluent BOD or COD concentration Co is the influent BOD
or COD concentration K is the temperature dependent first order rate constant T is the hydraulic retention time
The temperature dependence of the rate constant in eq (i) can be defined as
Kt= K20 (θ) T-20
Where K20 is the rate constant at 20o C. USEPA proposed 1.104 per day value for the rate constant. θ is the
temperature constant. USEPA proposed 1.06 value for the temperature constant. Its value has been found to vary
1.056 in the temperature between 20-30 o C to 1.135 in the temperature rang 4-20 o C (Metcalf and Eddy, 1999).
The inlet system is designed so that the influent flow is distributed uniformly over the length of the entry zone. The
typical devices used for influent distribution are gate pipes, slotted pipes or trough with V-notch weir. In the first few
feet of the entry zone is usually filled with large rock (2 to 4 inches or 50 to 100 mm) to minimize clogging. If the
Engineering and Educational Services Pvt. Ltd Page 25
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
step feed operation is desired, a second influent distributor can be placed parallel to the entry zone distributor at a
distance (50 ft or 15 m or more) down of the flow path (Crites and Tchobanoglous, 1998).
Outlet Structures:
Outlet device should consist of perforated pipes submerged to the bottom of the bed with valves or adjustable-level
outlet pipes to control the water depth (Crites and Tchobanoglous, 1998).
Bed liners:
If the soil is permeable, a bed liner will usually be required to prevent loss of water to ground water. The liner may
consist of native clay bentonite, asphalt or geomembrane liners. A smooth surfaced 30-mil plastic membrane liner is
used typically (Crites and Tchobanoglous, 1998).
Bed Media:
The Subsurface flow wetland medium is usually gravel although in early systems sand is usually used. The gravel
size has varied from 0.12 in to 1.25 in (3 to 32 mm), with inlet zone gravel size as large as 2 in (50 mm). The inlet
zone usually has the largest-diameter medium to minimize the clogging potential (Crites and Tchobanoglous, 1998).
Pradhan (2005) reported that there would be no significant change in performance of CWs for removal of BOD with
the change in media size. Significant change in performance would be found with the small change in media size
for removal of COD in HF bed and there will be decrease in performance for removal of COD with decrease in
media of Vertical flow bed. Significant change in performance would be found with the small change in media size
for removal of NH4-N, NO2-N both in HF bed and VF bed.
The depth of media selected will depend on design intentions for the system. If the vegetation is intended as a
major oxygen source for nitrification in the system, then the depth of the bed shouldn't exceed the potential root
penetration depth of the plant species to be used. This will ensure availability of some oxygen throughout the bed
profile, but many require management practices, which assure root penetration to these depths (USEPA, 1988).
5.13.5 Design
1.0) Existing Design Models:
The principle design parameter for the Constructed Wetland system includes organic loading rate
(OLR), Hydraulic loading rate (HLR) and Hydraulic retention time (HRT) and water depth (for
FWS only). The typical design criteria and expected effluent quality for SF constructed wetlands
are shown in Table 11.
Table 11 : Typical design criteria and expected effluent quality for SF constructed Wetlands
Item Unit Values
Design Parameter
Detention time d 04-Mar
BOD loading rate lb/ac.d <100
TSS entry loading rate lb/ft2.d 0.008
The simplest of the design model for treatment of domestic wastewater is adopted in UK where the
CWs is mostly designed as Subsurface flow system. For horizontal flow system, the surface area
(Ah) is calculated using the cooper model.
Where
Qd- Average daily flow rate of wastewater, m3/d (ft3/d)
Co- Average influent BOD or COD (mg/L)
Ce- Average effluent BOD or COD (mg/L)
KBOD - Reaction rate constant (m/d)
The factor KBOD has been adopted 0.083 ± 0.017 (Brix et al., 1989), 0.067 to 0.1 in UK (Cooper,
1999)
2.0) Estimation of Hydraulic Retention Time
The hydraulic retention time (HRT) of Leachate in the wetland bed is defined as useable wetland
volume to flow rate of Leachate. Theoretically, HRT can bed estimated by using the average flowthrough the
system, the system dimensions and the porosity of the media.
L *W * D * n
HRT
Q
Where,
HRT- hydraulic retention time (days)
L- Length of bed (m)
W- width of bed (m)
D- depth of bed (m)
n- porosity of filter media (as decimal fraction)
Q- discharge (m³/d)
Q max: 3 m³/day
Wastewater Quality
Average BOD5 of landfill leachate = 3500 mg/ L (Analysis performed with Gokarna Landfill leachate by NESS,
1996)
Excepted effluent of BOD5 (Ce) = < 100 mg/L
Sizing of CW
5.14 Landscaping
For stabilization of the waste mass, topping of outside slopes of the waste bordering dams with clayey soil in 2
layers of 25cm thickness each has been proposed. With the view of making the site more environmental friendly,
about 1 Ropani of the land will be planted with local species of trees. They will also act as a buffer zone around the
site. The species that will be planted ate bamboo, “Chilaune/ sissoo”, “Khaniyo” and eucalyptus. After the landfill
area is complete,“khaniyo” and chilaune/ sisoo” will be planted on top of the landfill. The subjective of planting
eucalyptus is that the fragrance emitted from it will help neutralize the odor emanating from the landfill area.
5.15 Fencing
Because of the cost factor, simple barbed wire fencing has been designed for a length of about 220m to demarcate
the office. 2 m long wooden post of 100×75 mm will be erected at an interval of 3-m c/c with 0.65 m under the
ground. The underground portion of the wooden pole will be painted with bitumen for safety. 5 layers parallel and 2
diagonal barbed wire will be hooked along the wooden post to serve as fence for the complex.
Guard House-cum-Counter
One room, single storey building has been designed and the guard house-cum,-counter room. The average plinth
area of the proposed room is 4.5×4.4m. The walls will be constructed the brick masonry and CGI roofing. The
design criteria of the foundation and walls of the building is the same as per the standard practices.
Landslides
The site is topographically and geologically stable, due to the presence of hard rock. So, there is least danger of
landslides. However, efforts are made in the design concept to stabilize the site through preventive measures such
Engineering and Educational Services Pvt. Ltd Page 30
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
as by selecting the appropriate landfill area in order to avoid the cut and fill, plantation in site protection / buffer
zone. To prevent landslides which may occur during site operation period, cutting of trees and bushes anywhere in
and around the SLF shall be strictly prohibited. Taking soil from the hills at the boundary of the SLF inside or outside
without special permission shall also be prohibited.
Surface Water
The surface water cut-off drain (174m) constructed in the upper terrain next to the landfill area not only cuts off the
surface run-off from entering into the landfill area and thus preventing the relatively pure water from getting polluted,
but also diverts it through a surface water collection basin to the existing natural drain line.
Special Remark:
As innovative methods for the control of bird hazard at waste landfill sited are still being investigated at various
landfills in the world, the Phikkalis eager to adapt any other appropriate measure, which shall prove to be more
effective.
Notes :
Door to door collection of household waste by municipal waste collection vehicles practically minimizes the
possibility of such wastes being collected. However, private vehicles carrying such wastes, after being
rejected for entry to the landfill site shall be strictly instructed either to get special occasional service offered
by the metropolis or to recycle/ manage themselves in their own premises without polluting the
surroundings (e.g. without attracting birds) , but never to dispose of in public open space. Enforcement as
per recently approved sanitation by-laws of municipality shall be strictly followed.
Additionally, big and thick plastic sheets shall be kept ready to cover the active area in emergency cases;
It is reported that out of many innovative methods tested so far at various landfill sites in
the world (e.g. spraying refuse with a foul tasting vegetable extract, foam cover in the active face, using a whipman,
use of toxic chemical " 4 amino pyridine"), the best result in reducing the number of birds at the landfill is expected
when using a person at the active face (whipman) man baiting as reinforcement.
Where Wtot is the resultant of the wall's weight and the weight of the 'boxed" soil above the heel
and la, lw, lp are the lever arm for the forces Sa Wtot and Sp respectively.
The safety factor against overturning is given by n1 = Ms/M1 and its minimum value is taken to be 1.5.
Check on Overall Stability
Engineering and Educational Services Pvt. Ltd Page 32
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
A retaining wall may fail on semi-circular slip surface located within soil below and behind the wall. The condition
has been checked for a minimum valve of 1.2 check on foundation bearing pressure. The bearing pressure on the
soil beneath the foundation is computed using the relevant values of M and N, and eccentricity -M/N
For e< B/6 the maximum pressure is
N 6e
max 1
B B
When e > B/6 part of the section adjacent to the back will be in tension and
where u = B/2-e,
The value of max is lower than the braking pressure. So the proposed design is safe for both the revetment and
spur.
The proposed landfill site for PhikkalV.D.C. ward no. 5 Dhode Illam district has been designed after a detailed
study of the existing site situation on topographical, hydro-geological and ecological/environment conditions and
given constraints. The life span is estimated as 20 years and estimated total cost of the project is Nrs.
21,204,811.96 . Infrastructures for the landfill area development have been proposed so as to make optimum use
of the site for a safe and environmentally sound disposal of municipal waste. It is therefore to be seen as a
municipal sanitary landfill, which means that it is not suitable for special wastes of hazardous nature, e.g.hospital
waste, industrial waste, slaughter waste, dead animals etc. The site should be constructed under strict
supervision, with due consideration of its sensitivity to maintain its quality.Following recommendation however
deserve due consideration for Landfill site at Phikkal:
1. All infrastructures such as retaining wall at bottom side, side earth bund, guard house, road and drain are to
be complete before start of the land filling. However, it is advisable to lay the jute mat ( top layer ) during
operation period only, but necessarily before the start of dumping waste in the completing the total
construction work at a time, following options could be followed:
a. The retaining wall can be constructed as per drawings.
b. The landfill basement has to be prepared in defined line and slope at a time. As the land filling
starts from the lowest point i.e. from the waste bordering dam and proceeds upwards, other landfill
area development items such as laying of mineral liners; construction of under drain; laying of
gabion mat, drainage carpet, jute mat, etc. could be completed step-wise, depending upon its
requirement so as to cover the landfill area to be filled within a stipulated time period. But however,
it is to be strictly noted that all required items have to be completed prior to the start of land filling of
the area under consideration.
2. For a safe and environmentally sound waste disposal management an operation manual is a must, which
should be strictly followed by the operation unit in charge of the site. Daily waste recording and
environmental monitoring has to be carried out on routine basis.
Engineering and Educational Services Pvt. Ltd Page 36
Survey ,Design and Cost Estimate of Phikkal Landfill site Illam
3. Buffer zone with appropriate plantation/greenery in and around the site is a must and so far the site
protection is concerned, bio-engineering measures have to be preferred to substitute the massive physical
structures wherever possible.
4. It is worthwhile to be noted that any landfill, however good as expected unless and until it is properly
operated, no matter how simple operation and maintenance might be.
5. The landfill waste is transported only by tractors at present. Additional tippers should be arranged for easy
transporting of the waste and to meet the future demand.
6. Social issues should be incorporated from the initial stage of the project construction and operation for
smooth operation of the landfill site.