List of Upcomi

Sr. # Name of Project Agency Fuel

Existing Installed Capacity: 28, 603 MW

1 M/s Layyah Sugar Mills Ltd. AEDB Baggase

2 Almoiz Industries Limited AEDB Baggase

3 Ranolia HPP PEDO Hydro

4 Machai Canal HPP PEDO Hydro

5 Golen Gol HPP Unit-I WAPDA Hydro

6 AJ Power Pvt. Lt.d AEDB Solar

7 LNG Based Plants at Balloki (1*ST) PPDB Imp. LNG

8 LNG Based Plants at Haveli Bahadur Shah (1*ST) PPDB Imp. LNG

9 Tarbela 4th Ext. Unit-I WAPDA Hydro

10 Neelum Jhelum Hydro Unit-I WAPDA Hydro


Sr. # Name of Project Agency Fuel

11 Neelum Jhelum Hydro Unit-II WAPDA Hydro

12 Karora HPP PEDO Hydro

13 Golen Gol HPP Unit-II WAPDA Hydro

14 Tarbela 4th Ext. Unit-II WAPDA Hydro

15 Neelum Jhelum Hydro Unit-III WAPDA Hydro

16 Neelum Jhelum Hydro Unit-IV WAPDA Hydro

17 Tarbela 4th Ext. Unit-III WAPDA Hydro

18 Golen Gol HPP Unit-III WAPDA Hydro

19 Port Qasim Power Project (Unit-II) PPIB Imp. Coal

20 Daral Khwar HPP PEDO Hydro

21 Jabori HPP PEDO Hydro

22 M/s Hartford Alternative Energy (Pvt.) Limited AEDB Wind


Sr. # Name of Project Agency Fuel

TOTAL ADDITION ENDING 2017-18

23 M/s Three Gorges Second Wind Farm Pvt. Ltd. AEDB Wind

24 M/s Three Gorges Third Wind Farm Pvt. Ltd. AEDB Wind

25 Engro Powergen Project (Unit-I) PPIB Dom. Coal

26 RLNG based power plant at Trimun, Jhang (GT NO.1 & 2) PPDB Imp. LNG

27 M/s Tricon Boston (Pvt.) Limited (A) AEDB Wind

28 M/s Tricon Boston (Pvt.) Limited (B) AEDB Wind

29 M/s Tricon Boston (Pvt.) Limited (C) AEDB Wind

30 M/s Zephyr Power Pvt. Ltd. AEDB Wind

31 HUB Power Company Ltd. (Unit-I) PPIB Imp. Coal

32 Chanar Energy Limited AEDB Baggase


Sr. # Name of Project Agency Fuel

33 Shahtaj Sugar Mills Ltd. AEDB Baggase

34 Hunza Power (Pvt.) Ltd. AEDB Baggase

35 Koto HPP PEDO Hydro

36 Etihad Power Generation Limited. AEDB Baggase

37 Indus Energy Limited. AEDB Baggase

38 Bahawalpur Energy Ltd. AEDB Baggase

39 Kashmir Power Private Ltd AEDB Baggase

40 Hamza Sugar Mills Ltd. AEDB Baggase

41 RYK Energy Limited. AEDB Baggase

42 Two Star Industries Pvt Ltd. AEDB Baggase

43 Faran Power Ltd. AEDB Baggase

44 Ittefaq Power (Pvt.) Ltd. AEDB Baggase


Sr. # Name of Project Agency Fuel

45 Mirpurkhas Energy Ltd. AEDB Baggase

46 Alliance Sugar Mills Ltd. AEDB Baggase

47 Sheikhoo Power Ltd. AEDB Baggase

48 Engro Powergen Project at Thar (Unit-II) PPIB Dom. Coal

49 Safina Sugar Mills Ltd. AEDB Baggase

50 Alman Seyyam (Pvt.) Ltd. AEDB Baggase

51 Solar Power Projects (QA Solar) PPDB Solar

TOTAL ADDITION ENDING 2018-19

52 HUB Power Company Ltd. (Unit-II) PPIB Imp. Coal

53 Grange Holding PPIB Imp. Coal

54 RLNG based power plant at Trimun, Jhang (ST NO.1 ) PPDB Imp. LNG
Sr. # Name of Project Agency Fuel

55 Gulpur Poonch river PPIB Hydro

56 Mehran Energy Ltd. AEDB Baggase

57 Habib Sugar Mills Ltd. AEDB Baggase

58 Sadiqabad Power Pvt Ltd. AEDB Baggase

59 Gotki Power Pvt Ltd. AEDB Baggase

60 Solar Power Projects (Competitive Bidding) AEDB Solar

61 Matiltan HPP PEDO Hydro

62 Kathai/Rialia AJK Hydro

TOTAL ADDITION ENDING 2019-20

63 Karachi Coastal (UNIT-I),K-2 PAEC Nuclear

64 Wind Power Projects (Competitive Bidding) AEDB Wind


Sr. # Name of Project Agency Fuel

65 TPS Jamshoro (Phase-I) GENCOs Imp. Coal

66 Thar Energy Limited (HUBCO Ltd.)Thar Block-II PPIB Dom. Coal

67 Thal NOVA , Thar Block-II PPIB Dom. Coal

68 Shanghai Electric Power Project (Unit-I) PPIB Dom. Coal

69 TPS Jamshoro (Phase-II) GENCOs Imp. Coal

70 Lucky Electric Power Company Ltd. PPIB Dom. Coal

71 Keyal Khwar WAPDA Hydro

72 Lawat AJK Hydro

TOTAL ADDITION ENDING 2020-21

73 Siddiqsons Limited PPIB Dom. Coal

74 Shanghai Electric Power Project (Unit-II) PPIB Dom. Coal


Sr. # Name of Project Agency Fuel

75 Karachi Coastal (UNIT-II),K-3 PAEC Nuclear

76 Lawi HPP PEDO Hydro

77 Oracle Coal Power Project PPIB Dom. Coal

78 Karot HPP PPIB Hydro

79 Coal Based Power Plant at Gawadar PPIB Imp. Coal

80 CASA GoP Import

81 Jagran-III AJK Hydro

TOTAL ADDITION ENDING 2021-22

82 RYK Coal Power Plant PPDB Imp. Coal

83 Dasu HPP (Phase-I) WAPDA Hydro

84 Suki Kinari HPP PPIB Hydro


Sr. # Name of Project Agency Fuel

85 Gomat Nar AJK Hydro

TOTAL ADDITION ENDING 2022-23

86 Asrit Kedam PPIB Hydro

87 Kohala HPP PPIB Hydro

88 Sehra HPP PPIB Hydro

89 Kalam Asrit HPP PPIB Hydro

90 Kaigah Hydropower Project PPIB Hydro

91 Azad Pattan HPP PPIB Hydro

92 Tarbela 5th Ext. Project WAPDA Hydro

TOTAL ADDITION ENDING 2023-24


Sr. # Name of Project Agency Fuel

93 Shontar AJK Hydro

94 Sharda-II AJK Hydro

95 Changan AJK Hydro

96 Doarian AJK Hydro

97 Nagdar AJK Hydro

98 Lower Spat Gah WAPDA Hydro

99 Phandar WAPDA Hydro

100 Harpo WAPDA Hydro

101 Madian HPP PPIB Hydro

102 Lower Palas Valley WAPDA Hydro

103 Nekhurdum Pur PPIB Hydro

104 CHASHNUPP-V PAEC Nuclear


Sr. # Name of Project Agency Fuel

105 Basho WAPDA Hydro

106 Chakothi-Hattian PPIB Hydro

TOTAL ADDITION ENDING 2024-25

GRAND TOTAL ENDING 2025


References:
i) As per data provided by WAPDA Hydro, GENCOs, AJKPDO, PEDO, PPIB, AEDB, PPDB, TCEB and PAEC.
t of Upcoming Generation Additions
Installed Capacity
Location Comissioning Date Status
(MW)

2017-18

41 Mar. 2018 Under Construction

36 Mar. 2018 Under Construction

17 Mar. 2018 Under Construction

3 Mar. 2018 Under Construction

35 Mar. 2018 Under Construction

12 Mar. 2018 Under Construction

420 Mar. 2018 Under Construction

420 Mar. 2018 Under Construction

470 Mar. 2018 Under Construction

242 Mar. 2018 Under Construction


Installed Capacity
Location Comissioning Date Status
(MW)

242 Mar. 2018 Under Construction

12 Apr. 2018 Under Construction

35 Apr. 2018 Under Construction

470 Apr. 2018 Under Construction

242 Apr. 2018 Under Construction

242 Apr. 2018 Under Construction

470 May. 2018 Under Construction

35 May. 2018 Under Construction

660 Jun. 2018 Under Construction

37 Jun. 2018 Under Construction

10 Jun. 2018 Under Construction

49.3 Jun. 2018 Under Construction


Installed Capacity
Location Comissioning Date Status
(MW)

4199.7

2018-19

49.5 Sep. 2018 Under Construction

49.5 Sep. 2018 Under Construction

330 Oct. 2018 Under Construction

830 Nov. 2018 LOS Stage

50 Nov. 2018 Under Construction

50 Nov. 2018 Under Construction

50 Nov. 2018 Under Construction

50 Nov. 2018 Under Construction

660 Dec. 2018 Under Construction

22 Dec. 2018 Under Construction


Installed Capacity
Location Comissioning Date Status
(MW)

32 Jan. 2019 LOS Stage

49.8 Feb. 2019 LOS Stage

41 Feb. 2019 Under Construction

74.4 Feb. 2019 LOS Stage

31 Apr. 2019 LOS Stage

31.2 Apr. 2019 LOS Stage

40 Apr. 2019 LOS Stage

30 May.2019 LOS Stage

25 May. 2019 LOS Stage

48.9 May. 2019 LOS Stage

26.5 May. 2019 LOS Stage

31.2 May. 2019 LOS Stage


Installed Capacity
Location Comissioning Date Status
(MW)

26 May. 2019 LOS Stage

30 May.2019 LOS Stage

30 May.2019 LOI Stage

330 Jun. 2019 Under Construction

20 Jun. 2019 LOI Stage

34.5 Jun. 2019 LOI Stage

600 Jun. 2019 Planned

3,672

2019-20

660 Aug. 2019 Under Construction

163 Sep. 2019 FC in progress

420 Oct. 2019 LOS Stage


Installed Capacity
Location Comissioning Date Status
(MW)

102 Nov. 2019 Under Construction

26.5 Dec. 2019 LOI Stage

27 Dec. 2019 LOI Stage

45 Dec. 2019 LOI Stage

45 Dec. 2019 LOI Stage

600 Mar. 2020 Planned

84 Jun. 2020 Under Construction

15 Jun. 2020 -

2,188

2020-21

Karachi 1,100 Nov. 2020 Under Construction

1224 Dec. 2020 Planned


Installed Capacity
Location Comissioning Date Status
(MW)

660 Dec. 2020 Planned

330 Dec. 2020 Under Construction

330 Dec. 2020 FC in progress

660 Mar. 2021 FC in progress

660 Jun. 2021 Planned

660 Jun. 2021 FC in progress

128 Jun. 2021 Under Construction

49 Jun. 2021 -

5,801

2021-22

330 Sep. 2021 FC in progress

660 Sep. 2021 FC in progress


Installed Capacity
Location Comissioning Date Status
(MW)

Karachi 1,100 Sept. 2021 Under Construction

69 Nov. 2021 Under Construction


Project proposal yet to
1,320 Dec. 2021
be submitted
720 Dec. 2021 Under Construction
Tariff determination in
300 Dec. 2021
progress
1,000 Jun. 2022 Planned

35 Jun. 2022 -

5,534

2022-23

1320 Jul. 2022 Planned

2,160 Dec. 2022 Contractor Mobilized

870 Dec. 2022 Under Construction


Installed Capacity
Location Comissioning Date Status
(MW)

50 Jun. 2023 -

4,400

2023-24

215 Dec. 2023 To be advertised

1,124 Jun. 2024 FC in progress

130 Jun. 2024 Planned

197 Jun. 2024 To be advertised


Feasibility study
548 Jun. 2024
completed
701 Jun. 2024 FC in progress
Detail Design
1,410 Jun. 2024
Completed
4,325

2024-25
Installed Capacity
Location Comissioning Date Status
(MW)

45 Jul.2024 -

21 Jul.2024 -

9 Jul.2024 -

40 Jul.2024 -

35 Jul.2024 -
Feasibility study
665 Dec. 2024
completed
Detailed design
80 Dec. 2024
completed
35 Dec. 2024 Feasibility completed

157 Dec. 2024 To be advertised


Feasibility study
496 Dec. 2024
completed
80 Jun. 2025 To be advertised
Chashma,
1,100 July. 2025 EPC Contract Signed
Mianwali
Installed Capacity
Location Comissioning Date Status
(MW)
Feasibility study
40 Jun. 2025
completed
500 Jun. 2025 To be advertised

3,303

33,422
ons
Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

LOI Issued.

LOI Issued.

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

NTDC has a Plan of Power Evacuation/ Dispersal from the


Unit
-
Remarks

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G


Remarks

NTDC has a Plan of Power Evacuation/ Dispersal from the


Unit
-

Consent of Power Purchase given by CPPA-G

Consent of Power Purchase given by CPPA-G

Tarriff determination in progress

Consent of Power Purchase given by CPPA-G


Remarks

-
Remarks

-
Request of Power Evacuation Planning sent to
NTDC(Planning)
Remarks