Professional Documents
Culture Documents
Supplement A
Content:
A01 Drafting details
A02 Injection filling
A03 Basics on the design of anchorage and lapped bars
A04 Summery of the relevant design provisions of Eurocode 2 (ENV 1992-1-1 : 1992)
A05 Basics on bond behaviour of ribbed bars in concrete
A06 Interaction of splitting and bond
A07 Hilti HIT-Rebar deign and ACI 318-99 approach
A08 Serviceability limit state
A09 Corrosion behaviour of Hilti HIT-Rebar connections
A10 Fire resistance design
A11 Fatigue of Hilti HIT-Rebar connections
A12 Guide specifications for bonded-in connections
A13 List of approvals
Issue 09/2003
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A01: Drafting details
1. Symbols
The definition and terminology used in this section are in accordance with European Standard EC (ENV 1992-1-
1 : 1992) where ever applicable.
The relevant clauses from EC 2 are in {brackets} for easier reference.
Supplementary symbols for bonded-in bars are in bold letters.
Anchorage:
cs,2 ≥ 2.5∅ 1)
If c s,3 < 0.5 s or c s,4 < 0.5 s:
l b,ef ≥ 10∅ adequate links (stirrups) to prevent
cs,3 ≥ 2.5∅
1)
s ∅ splitting at edge should be provided.
≥ 0.5s s ≥ 5∅
s
c1 s
l inst Note that minimum anchorage is
cs,1 ≥ 2.5∅ D0 10∅ according to the standard.
cs,41) ≥ 2.5∅
≥ 0.5s
Lapped splice:
edge of member
ls cf
l inst
edge of member
s ≥ 5∅ ∅
≥ 30mm D 0
ls cf
l inst
linst
Issue 09/2003
1/1
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A02 Approximate filling volume of adhesive and marking distance
1. Approximate filling volume
The necessary injection volume Vm to fill the gap between bar and hole perimeter is shown in table 1.
Sufficient allowance should be provided for deeper drilling, cavities in the base material, overflow and others.
Rule of the thumb: fill 2/3 of the hole.
Calculated volume Vm [ml], with allowance in the formula of 20% compared to the nominal volume using linst in
[cm] and D0, and ∅ in [mm]: Vm = 0,0094 x lb, inst x (D02 - ∅ 2)
Adjust according to site conditions, e.g. pneumatic drilling needs more material.
Recommendation: add 15% for cost estimation.
Table 1: Approximate filling volume of adhesive
∅ 10 12 16 20 25 28 32 36 40
Drill bit size 12 14 16 18 20 22 25 28 30 32 35 37 39 42 42 46 48 52
l inst lm lm lm lm lm lm lm lm lm lm lm lm lm lm lm lm lm lm
[cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm] [cm]
10 5 10 - - - - - - - - - - - - - - - -
12 5 11 - - - - - - - - - - - - - - - -
14 6 13 15 24 - - - - - - - - - - - - - -
16 7 15 17 28 22 35 - - - -- - - - - - - - -
20 9 19 22 34 28 43 43 73 - - - - - - - - - -
22 10 20 24 38 30 48 47 80 57 83 - - - - - - - -
25 11 23 27 43 34 54 53 91 65 94 104 138 - - - - - -
28 12 26 30 48 38 61 60 102 73 106 117 154 131 195 - - - -
30 13 28 32 51 41 65 64 109 78 113 125 165 141 209 - - - -
32 14 29 34 55 44 69 68 116 83 121 133 176 150 223 141 247 - -
34 15 31 36 58 47 73 72 123 88 128 141 187 159 237 150 263 - -
36 15 33 38 61 49 78 77 130 94 136 150 198 169 251 159 278 - -
38 16 35 41 65 52 82 81 138 99 143 158 209 178 265 168 293 - -
40 17 37 43 68 55 86 85 145 104 151 166 220 187 279 176 309 265 416
45 19 41 48 77 61 97 96 163 117 169 187 248 211 314 198 347 298 467
50 21 46 53 85 68 108 106 181 130 188 208 275 234 348 220 386 331 519
55 23 50 58 94 75 118 117 199 143 207 228 303 257 383 242 424 364 571
60 25 55 64 102 82 129 127 217 156 226 249 330 281 418 264 463 398 623
65 27 59 69 110 88 140 138 235 169 244 270 358 304 453 286 502 431 675
70 29 64 74 119 95 151 149 253 181 263 291 385 328 487 308 540 464 727
75 32 68 79 127 102 161 159 271 194 282 311 413 351 522 330 579 497 779
80 34 73 85 136 109 172 170 289 207 301 332 440 374 557 352 617 530 831
85 36 77 90 144 116 183 180 307 220 319 353 468 398 592 374 656 563 883
90 38 82 95 153 122 193 191 325 233 338 374 495 421 627 396 694 596 934
100 42 91 106 170 136 215 212 361 259 376 415 550 468 696 440 771 662 1'038
110 - - 116 187 149 236 233 398 285 413 456 605 514 766 484 848 728 1'142
120 - - 127 204 163 258 254 434 311 451 498 660 561 835 528 925 795 1'246
130 - - 137 220 176 279 275 470 337 488 539 715 608 905 572 1'003 861 1'350
140 - - - - 190 301 297 506 362 526 581 770 655 974 616 1'080 927 1'453
150 - - - - 204 322 318 542 388 563 622 825 701 1'044 660 1'157 993 1'557
160 - - - - - - 339 578 414 601 664 880 748 1'113 704 1'234 1'059 1'661
180 - - - - - - 381 650 466 676 747 990 841 1'253 792 1'388 1'192 1'868
200 - - - - - - 423 722 517 751 830 1'100 935 1'392 880 1'542 1'324 2'076
Issue 09/2003
1/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
2. Marking distance l m
The mark with distance lm from tip of injection extension is used to
achieve exact filling volume during the injection of the adhesive (see
setting instruction for deep holes). linst
lm = linst x (∅ 2 / D02 – 0.2) where 20% allowance is included
Note: - lm represents the length of the hole that is not filled during injection.
- suitable build-up plugs are available.
Table 2: Marking distance l m
∅ 10 12 16 20 25 28 32 36 40
Drill bit size 12 14 16 18 20 22 25 28 30 12 14 16 18 20 22 25 28 30
l inst Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm Vm
[cm] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml] [ml]
10 4 3 - - - - - - - - - - - - - - - -
12 5 3 4 2 - - - - - - - - - - - - - -
14 6 4 5 3 - - - - - - - - - - - - - -
16 7 4 5 3 7 5 - - - -- - - - - - - - -
20 9 6 7 4 8 6 8 6 - - - - - - - - - -
22 10 6 7 5 9 7 9 6 - - - - - - - - - -
25 12 7 9 6 11 8 11 7 12 10 - - - - - - - -
28 13 8 10 6 12 9 12 8 13 11 12 10 - - - - - -
30 14 9 10 7 13 9 13 9 14 12 13 11 - - - - - -
32 15 9 11 7 14 10 14 9 15 13 14 11 15 12 - - - -
34 16 10 12 8 14 11 14 10 16 13 14 12 16 12 - - - -
36 17 11 13 8 15 11 15 11 17 14 15 13 17 13 19 14 - -
38 18 11 13 9 16 12 16 11 18 15 16 14 17 14 20 15 - -
40 19 12 14 9 17 13 17 12 19 16 17 14 18 15 21 16 19 15
45 22 13 16 11 19 14 19 13 22 18 19 16 21 17 24 18 22 17
50 24 15 18 12 22 16 22 15 24 20 22 18 23 19 26 20 24 19
55 27 17 19 13 24 18 24 17 27 22 24 20 26 20 29 22 27 21
60 29 18 21 14 26 19 26 18 29 24 26 22 28 22 32 24 29 23
65 32 20 23 15 28 21 28 20 32 26 28 24 30 24 34 26 32 25
70 34 21 25 17 30 23 30 21 34 28 30 26 33 26 37 28 34 27
75 37 23 27 18 33 24 33 23 37 30 33 27 35 28 40 30 37 29
80 39 24 29 19 35 26 35 24 39 32 35 29 37 30 42 32 39 31
85 42 26 30 20 37 27 37 26 42 34 37 31 40 32 45 35 42 33
90 44 27 32 22 39 29 39 27 44 36 39 33 42 34 48 37 44 35
100 49 31 36 24 44 32 44 31 49 41 44 37 47 38 53 41 49 39
110 - - 39 26 48 36 48 34 54 45 48 40 52 41 58 45 54 43
120 - - 43 29 52 39 52 37 59 49 52 44 56 45 64 49 59 47
130 - - 47 31 57 42 57 40 64 53 57 48 61 49 69 53 64 50
140 - - - - 61 46 61 43 69 57 61 52 66 53 74 57 69 54
150 - - - - 66 49 66 46 74 61 66 55 70 57 80 61 74 58
160 - - - - - - 70 49 79 65 70 59 75 60 85 65 79 62
180 - - - - - - 79 55 89 73 79 67 85 68 96 74 89 70
200 - - - - - - 88 62 98 82 88 74 94 76 106 82 98 78
Issue 09/2003
2/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A03 Basics on design for anchorage and lapped bars
Figure.1a: Strut-and-tie-model
1.4 Shear friction model or saw tooth model for shear transfer
The shear friction model is also based on the assumption of a rough interface.
Due to the parallel displacement induced by the shear force, the interfaces are
forced to separate. As a result the bars are subjected to a tensile force and
simultaneously to a bending moment depending on the roughness of the
interface surfaces. Tests show that due to the combined load only 50% of the
yield tensile force of the bar can be activated for friction (see actual Hilti FTM,
Appendix 2)
Additional interlocking effects and cohesion can take up part of the shear force
at the rough interface.
Figure 1c
Issue 9/2003
1/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
2. Anchorage of reinforcement
At places where the reinforcement it is no longer needed, it has to be anchored. These situations may occur:
• when load path of the tensile force has ended (e.g. support, figure 2a)
• at curtailment of reinforcement (see figure 2b)
• compression bar anchorage (fig. 2c).
Figure 2b Figure 2c
Figure 2a: Tensile force has ended Compression bars
Support, truss model
3. Lapped splice of reinforcement:
Lapped splices are used to achieve continuity in the tensile tie of the truss
model at construction joints. The load from one bar to the other bar is
transferred by means of compressive struts in the concrete. A 45°-truss model
is assumed.
The resulting splitting forces are controlled by sufficient concrete cover,
spacing of bar and by the transverse reinforcement
Figure 5: Doweling
Issue 09/2003
2/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A04 Summery of the relevant design provisions of to EC 2 (ENV 1992-1-1 : 1992)
Design Requirements {2.3}
Combination of actions:
Design situation Permanent actions Variable actions Accidental
Gd Qk actions Ak
One with its Other with their
characteristic value combination value
Persistent and Transient γG Gk γQ Qk ψ0 γQ Qk -
Accidental * γGA Gk ψ1 Qk ψ2 Qk γA Ak**
* If not specified differently elsewhere
** if Ad is not specified directly
combination expression: Σ γG,j Gk,j + γQ,1 Qk,1 + Σ γQ,i ψQ,i Qk,I {2.7(a)}
i>1
accidental design situation: Σ γGA,j Gk,j + Ad + ψ1,1 Qk,1 + Σ ψ2,i Qk,I {2.7(b)}
i>1
where
Gk,j [kN] characteristic values of permanent actions (e.g. dead load, i.e. the weight of structure
complete with finishes, fixtures and partitions)
Qk,1 [kN] characteristic value of one of the variable actions
Qk,1 [kN] characteristic value of the other variable actions
Ad [kN] design value (specified value) of thr accidental action
γG,j partial safety factor for permanent action j
γGA.j as γG,j but for accidental design situation
γQ,i partial safety factor for variable action i
ψ0, ψ1, ψ2 coefficients defined in {2.2.2.3}
* Where according to {2.2.2.3 P(3), favourable and unfavourable parts of a permanent action need to be
considered as individual actions, the favourable part should be associated with γG,inf = 0,9 and the
unfavourable part with γG,sup = 1,1.
** See EC 1; in normal cases for building structures γQ,inf = 0.
*** See relevant clauses EC 2.
Issue 09/2003
1/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Partial safety factors for actions in building structures {Cl. 2.3.3.2}
Table 2.3 from EC 2 is reproduced below:
Combination Concrete γc Steel reinforcement γs
Fundamental 1,5 1,15
Accidental (except earthquakes) 1,3 1,0
Strength class C12/15 C16/20 C20/25 C25/30 C30/37 C35/45 C40/50 C45/55 C50/60
of concrete
fck 12 16 20 25 30 35 40 45 50
fctm 1.6 1.9 2.2 2.6 2.9 3.2 3.5 3.8 4.1
fctk 0.05 1.1 1.3 1.5 1.8 2.0 2.2 2.5 2.7 2.9
fctk 0.95 2.0 2.5 2.9 3.3 3.8 4.2 4.6 4.9 5.3
fctk characteristic cylinder compressive strength of the concrete
fctm ( = 0.30 fck 2/3) mean value of the tensile strength
fctk 0.05 ( = 0.7 fctm) lower characteristic tensile strength (5%-fractile)
fctk 0.95 ( = 1.3 fctm) upper characteristic tensile strength (95%-fractile)
The coefficient of thermal expansion may be taken as 10 x 10-6 /°C {Cl 3.1.2.5.4}
For modulus of elasticity Ecm see {Table 3.2, EC 2} (for normal cases assume 30 kN/mm2)
For creep coefficient φ see {Table 3.3, EC 2}.
For shrinkage strains ε see {Table 3.4, EC 2}. (for normal cases assume: inside –60 %0; outside –30 %0)
Density: ρ = 2400 kg/m3 for plain (unreinforced) concrete {Cl 4.2.1.2}
ρ = 2500 kg/m3 for reinforced or prestressed concrete of normal percentage of reinforcement
Issue 09/2003
2/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
2. Detailing Provisions
2.1 Bond {5.2.2.1 - 4}
Bond Conditions
For cast in bars bond conditions are considered good or poor depending on the situation of the bar when
concrete is cast. The Definition of bond condition is specified in {figure 5.1, EC 2}
Direction of concreting
Design values fbd (N/mm2) for good bond conditions and high bond bars where ∅ ≤ 32 mm {Table 5.3}
These values incorporate a partial material safety factor γc equal to 1.5
For poor bond conditions the values in the table should be multiplied by a coefficient 0.7.
Strength C12/15 C16/20 C20/25 C25/30 C30/37 C35/45 C40/50 C45/55 C50/60
class of
concrete
fck 12 16 20 25 30 35 40 45 50
fbd 1.6 2.0 2.3 2.7 3.0 3.4 3.7 4.0 4.3
Issue 09/2003
3/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Anchorage {5.2.3}
The reinforcing bars shall be anchored in a way that the forces are fully transmitted to the concrete but that
longitudinal cracking or spalling of concrete is avoided. If necessary, transverse reinforcement shall be provided.
Anchorage methods {5.2.3.2}
For post installed bars only straight bars are used. ⇒ αa = 1.0
Transverse reinforcement parallel to the concrete surface {5.2.3.3}
In beams transverse reinforcement should be provided:
• for anchorages in tension, if there is no transverse compression due to the support reaction
(as is the case for indirect supports, for example).
• for all anchorages in compression
a) slab b) beam
The minimum total area of the transverse reinforcement (legs parallel
to the layer of the longitudinal reinforcement) is 25 % of the area of
one anchored bar (figure 5.3).
Splices {5.2.4}
The detailing of splices between bars shall be such that:
• the transmission of the forces from one bar to the next is assured;
• spalling of the concrete in the neighbourhood of the joints does not occur;
• the width of cracks at the end of the splice does not significantly exceed the values given
in {section 4.4.2.1, EC 2}
Lapped splices for bars
Arrangement of lapped joints:
As far as possible:
• laps between bars should be staggered and
should not be located in areas of high stress,
{see also Section 2.5.3, EC 2, Analysis}
• laps at any one section should be arranged
symmetrically and parallel to the outer face of
the member
Clauses {5.2.3.2 (1) to (4)} are also applicable to * otherwise the lap length shall be increased by the amount
by which the clear space exceeds 4 ∅.
lap splices.
Transverse reinforcement Fig. 5.4: Adjacent laps
{5.2.4.1.2}
If the diameter ∅ of the lapped bars is less than 16 mm, or if the percentage of lapped bars in any section is
Issue 09/2003
4/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
less than 20%, then the minimum transverse reinforcement provided for other reasons (e.g. shear
reinforcement, distribution bars) is considered as sufficient.
If ∅ ≥ 16 mm, then the transverse reinforcement should:
• have a total area (sum of all legs parallel to the layer of the spliced reinforcement, see figure 5.5) of not less
than the area As of one spliced bar (ΣAst ≥ As).
• be formed as links if a ≤ 10 ∅ (see figure 5.6) and be straight in other cases.
• The transverse reinforcement should be placed between the longitudinal reinforcement and the concrete
surface.
For the distribution of the transverse reinforcement {5.2.3.3} applies (see anchorage).
with:
lb,net according to equation (5.4)
l s,min ≥ 0.3 αa α1 l s
≥ 15 φ
Fig. 5.5 Transverse reinforcement
≥ 200 mm
for lapped splices
the coefficient α1 takes the following values:
% of spliced bars < 30 % All > 30%
Bar spacing a > 10 ∅ other < 10 ∅
Edge distance b >5∅ cases <5∅
α1 = 1.0 1.4 2.0
Ls,min = 0.3l b 0.42l b 0.6lb
MAX 15Φ MAX 15Φ MAX 15Φ
200 mm 200 mm 200 mm
The table is valid for splices in tension and in compression Figure 5.6 Evaluation of α1
Issue 09/2003
5/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Structural Members {5.4}
Columns {5.4.1}
The minimum amount of total longitudinal reinforcement As,min should be derived from the following condition:
0 .15 ⋅ NSd
A s,min = ≥ 0 .003 ⋅ A c
f yd
fyd is the design yield strength of the reinforcement
NSd is the design axial compression force
Ac is the cross-section of the concrete
Even at laps, the area of reinforcement should not exceed the upper limit of 0.008 Ac.
The longitudinal bars should be distributed around the periphery of the section. For columns having a polygonal
cross-section, at least one bar shall be placed at each corner. For columns of circular cross-section the
minimum number of bars is 6.
Beams {5.4.2}
Minimum and maximum reinforcement
The effective cross-sectional area of the longitudinal
tensile reinforcement should be not less than that
required to control cracking, see: {4.4.2, EC 2} (see also
Limit States of Cracking).
Nor less than:
b ⋅d
A s,min = 0 .6 ⋅ t ≥ 0.0015 ⋅ b t ⋅ d
f yk
where:
bt denotes the mean width of the tension zone (for a
T-beam with flanges in compression use web)
Issue 09/2003
6/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Anchorage of bottom reinforcement at end support {5.4.2.1.4}
Over supports with little or no end fixity, it is necessary to retain not less than ¼ of the steel section present in
the span.
The anchorage of the reinforcement should be capable of resisting a tensile force of:
Fs = VSd a1 / d + NSd
{eq. 5.15} a) direct support b) indirect support
where :
VSd is the shear force and NSd the design axial tensile force
Issue 09/2003
7/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Corbels {5.4.4}
For details see {5.4.4, EC 2}
Where:
As = area of minimum reinforcement within tensile zone.
Act = area of concrete within tensile zone (calculated just before formation of the first crack).
σs = the maximum stress permitted in the reinforcement immediately after formation of the crack:
for normal cases σs = fyk,
unless otherwise specified by the design engineer to satisfy other crack width limits.
fct,eff = the tensile strength of the concrete effective at the time when the cracks may first expected to occur:
for normal cases assume fct,eff = 3 N/mm2,
unless otherwise specified by the design engineer to satisfy for special conditions.
kc = a coefficient which takes into account of the nature of the stress distribution within the section prior
to cracking (loading and restrained imposed deformations).
= 1.0 for pure tension
= 0.4 for bending without normal compressive force
(for sections subjected to normal force or prestress, see {4.4.2.2 (7), EC 2}
k = a coefficient which allows for the effect of non-uniform self-equilibrating stresses
= 0.8 generally for tensile stresses due to restraint of intrinsic deformations
= 0.8 for rectangular sections h ≤ 30 cm
= 0.5 for rectangular sections h ≥ 80 cm
= 1.0 for tensile stresses due to restraint of extrinsic deformations
Issue 09/2003
8/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Issue 09/2003
9/9
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A05 Basics on bond behaviour of ribbed bars in concrete
1. Cast-in ribbed bars
Generally, for load transfer in reinforced concrete only tensile or compressive forces in the bar are considered.
For ribbed bars, the load transfer in concrete is governed (approx. 90%) by the bearing of the ribs against the
concrete (figure 1). The force reaction in the concrete is assumed to form a compressive strut in the direction of
45°.
For higher bond stress values, the concentrated bearing forces in front of the ribs cause the formation of cone-
shaped cracks starting at the crest of the ribs. The resulting concrete keys between the ribs transfer the
bearing forces into the surrounding concrete, but the wedging action of the ribs remains limited. In this stage
the displacement of the bar with respect to the concrete (slip) consists of bending of the keys and crushing of
the concrete in front of the ribs.
The bearing forces, which are inclined with respect to the bar axis, can be decomposed into directions parallel
and perpendicular to the bar axis. The sum of the parallel components equals the bond force, whereas the
radial components induce circumferential tensile stresses in the surrounding concrete, which may result in
longitudinal radial (splitting) cracks.
Figure 1 Figure 2
Load transfer from ribbed bars into concrete [Goto]
Failure of bond may occur due to pull-out (crushing of the concrete between the ribs, (fig.1) or, if the
encasement of the surrounding concrete is not sufficient, due to splitting of the concrete (fig.3). Splitting is
controlled by the concrete cover, the transverse reinforcement, the spacing of the bar, size of the bar and the
force in the bar (normally yield).
Issue 10/2002
1/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
2. Lapped bar splices
Issue 10/2002
2/2
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A06 Interaction of splitting and bond
1. General notes
Anchorage and splice lengths of cast-in reinforcement bars are defined by the applicable structural concrete
design codes. In many cases these anchorage lengths are multiples of the bar diameter. The multiplying factor
usually depends on the state of stress around the anchorage and also on the concrete cover and bar spacing
dimensions. Splitting and pullout failures, as well as displacement conditions, are covered by the prescribed
anchorage lengths.
For post-installed bars, the same failure and serviceability criteria must be met. Splitting is the failure of the
concrete surrounding the anchorage because of excessive radial stresses. While standard design procedures
for post-installed anchors prevent splitting failure by specifying minimum edge distances and spacing, this limit
should be omitted for post-installed reinforcement bars, because their structural efficiency generally depends on
their being placed close to the concrete cover. Since splitting is a pure concrete failure, the design of post-
installed bars should respect the same splitting criteria as cast-in bars. The American Building Code
Requirements for Reinforced Concrete (ACI 318-02) gives an explicit formula for the anchorage length of cast-in
bars taking into account the concrete quality and the geometry of the anchorage.
The other failure criterion for reinforcement bars is bond failure (pullout). If spacing and edge distances have no
influence, the bond strengths of cast-in and post-installed bars may differ considerably. With cast-in bar, the
bond strength is mainly a function of the rib geometry while post-installed bars take their pullout resistance from
the characteristics of the bonding agent. These characteristics vary from one product to another.
300
600
600
40 40 60 40 40 40 40 120 40 40
220 280
Failure Loads
The failure load of all three combinations (both bars cast-in / one bar cast-in, one Hilti HIT-HY150 / one bar
cast-in, one Hilti HIT-RE 500) were comparable, within a scatter of 10%.
Failure Loads specimen
220x300 280x300
both bars cast-in 209.5kN 259.4kN
one side with HIT HY 150 234.0kN 271.9kN
one side with HIT RE 500 234.1kN 267.3kN
Issue 09/2003
1/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Spieth [11], [12] has demonstrated that a uniform distribution of the load transfer along the embedment land a
stiffness comparable to that of the cast-in bar are important to obtain a good splice behavior and high ultimate
loads. Table 2 shows, that the ultimate loads with post-installed splices with the Hilti HIT-Rebar system have
even higher failure loads than the specimens with cast-in splices.
Therefore it has been shown that post installed lapped splices with the adhesive Hilti HIT-HY 150 and
Hilti HIT-RE 500 have equal performance compared to cast-in splices.
Spieth [12] also made comparative splice tests with other adhesives. The dimensions of the specimens were
similar to the 220x300mm specimen as shown in figure 3, but they additionally had transverse reinforcement.
Figures 3a shows the maximum steel stresses at failure load for, from left to right, cast-in splices, then splices
with a hybrid mortar, with a cement system, with a stiff epoxy mortar and with a soft polyester mortar.
In these tests, cast-in, hybrid system and cement system achieved similar failure loads. The failure load with
the stiff epoxy system was 5-10% lower and that with the soft polyester mortar even approximately 25% lower.
Figure 3a) Steel stresses in cast-in splice (from [11]) Figure 3b) Steel stresses in splice with cast-in
(left) Hilti HIT-HY 150 (right) bar (from [11])
cast-in-place Hilti HIT-RE 500
450
400
350
steel stress [Mpa]
300
F=20kN
250
F=40kN
200 F=60kN
150 F=100kN
100 Fmax=116kN
50
0
0 100 200 300 400 500 600
embedment depth [mm]
Figure 3c) steel stress in splice, bar set with Hilti HIT-RE 500
Figure 3a shows that the stresses in both cast-in bars are symmetrical; in the splice with Hilti HIT-HY 150 (fig.
3b) there is a slight eccentricity of the stresses, but, as demonstrated by the ultimate loads, this non
symmetry is not critical, since loads of the same range are obtained. Figure 3c shows that the stresses in the
bar set with Hilti HIT-RE 500 are almost identical to those in cast-in bars or bars set with Hilti HIT-HY 150.
Thus, it can be affirmed that the load introduction from bars set with Hilti HIT RE-500 or with Hilti HIT HY-150
into concrete is equal to that from cast-in bars into concrete.
Issue 09/2003
2/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Other tests performed by Spieth [12] demonstrated that mortars not providing similar overall stiffness as cast-in
bars, such as soft polyester or stiff epoxy resins based mortars, are unsuitable for such applications. The load
transfer was clearly unsymmetrical and it resulted in premature splitting failure (fig. 3d,e).
Bibliography
[2] Building Code Requirements for Reinforced Concrete (ACI 318-02) and Commentary 318R-02 American
Concrete Institute, Michigan. ISSN 0065-7875.
[3] Darwin, D., Idun, E.K. et al.: Reliability-Based Strength Reduction Factor for Bond. ACI Structural
Journal, V. 95, No. 4, July-August 1998
[4] Darwin, D., Zuo M.L., et al.: Development Length Criteria for Conventional and High Relative Rib Area
Reinforcing Bars. ACI Structural Journal, V. 93, No. 3, May-June 1996.
[5] Pullout and Direct Shear Tests of Deformed Reinforcement Using Product A. Final Test Report for Hilti.
Prof. D.-U. Choi, Hankyong National University, Korea. December 1999.
[6] Pullout Tests with Product B. Hilti internal test report. Not published.
[8] Chinn, Ferguson, Thompson, Neils, 1955. Lapped Splices in Reinforced Concrete Beams. ACI Journal,
Proceedings V. 54, No. 8, Feb., pp. 689-698
[9] Spieth, Eligehausen, Fuchs: Eingemörtelte Bewehrungsstäbe (Verbundmörtel HIT-HY 150), Auszugs-
versuche an Einzelstäben mit großer und kleiner Betondeckung. Bericht FH1/1 – 97/1 vom 18.8.1997
[10] Kuster: Zur Verankerung von Bewehrungsstäben. Diplomarbeit ETH Zürich, 2001.
[11] Tragverhalten von Übergreifungsstössen eingemörtelter Bewehrungsstäbe. Diplomarbeit von A. Quasem,
Universität Stuttgart, März 1999
[12] Spieth, Ozbolt, Eligehausen, Appl: Numerical and Experimental Analysis of Post-Installed Rebars
Spliced with Cast-in-Place Rebars. International Symposium on Connections between Steel and
Concrete. RILEM, Stuttgart, Sept. 2000.
Issue 09/2003
3/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A07 Hilti HIT-Rebar design and ACI 318-99 approach
1. ACI 319-99 approach
The American Standard ACI 318-02 gives an explicit formula for the design of anchorages and splices that
considers splitting as a function of concrete cover and bar spacing. This function is adapted and extended for
post-installed bars for the Hilti HIT-Rebar design concept. The embedment length of an anchorage or splice is
defined as a function of steel yield, concrete strength, the bar diameter, the minimum edge distance or spacing
and a coefficient taking into account the transverse reinforcement.
Figure 1 shows the bond stress as a function of the parameter c/∅ or s/2∅. The splitting bond stress is defined
by an inclined line and it augments with larger values of c/∅ or s/2∅. The increase in splitting bond stress is
limited by the maximum pull-out bond stress, which is a value given by the standards for cast-in bars and by
the product supplier for post-installed bars. For example, in ACI 318-02 and a concrete C30 the bond stress is
limited to 3.9 N/mm2.
20
18 8
Effective bond stress fb,ef [N/mm2]
16
14
7
12 1
10
8 2
6 6
3
4 5
4
2
Minimum edge distance to centre line of bar
0
0 1 2 3 4 5 6 7
Relative edge distance c/φ or spacing s/2 ∅
Cast-in [8] and [9] Hilti HIT-RE 500, single bar [6,10]
Hilti HIT-RE 500 two bars [6,10] Hilti-HIT-HY 150 single bar tests [9]
1 Concrete splitting: mean ultimate 5 ACI 318-99, cast-in: design bond f b,d = 3.9 N/mm2
2 Concrete splitting: characteristic 6 Hilti HIT-RE 500: design bond f b,d = 6.0 N/mm2
3 Concrete splitting: design 7 Hilti HIT-RE 500: characteristic bond f b,k = 13.0 N/mm2
4 EC 2, cast-in: bond design f b,d = 2.7 N/mm2 8 Hilti HIT-RE 500 mean ultimate bond: f b,u = 17.3 N/mm2
Fig. 1 Splitting and bond interaction for concrete C30 (fcu = 30 N/mm2)
Tests show that transverse reinforcement improves the splitting capacity. Transverse reinforcement can be
taken into account by adding a substitute augmentation of the cover when reading the design tables for splitting
capacity.
The ACI 318-02 code explicitly takes into account the influence of transverse reinforcement able to prevent
splitting by means of the “transverse reinforcement index” Ktr .
Design splitting bond stress evaluated from design formula in ACI 318-02:
c + K tr A tr ⋅ f yt c + K tr
f bd = f cu ⋅ ; K tr = ; ≤ 2 .5 for cast - in bars (SI-units)
4⋅φ⋅ξ 10 .34 ⋅ s ⋅ n φ
with: Atr total cross-sectional area of all transverse reinforcement that is within the spacing s and that
crosses the potential plane of splitting through the reinforcement being developed [mm2]
fyt yield strength of transverse reinforcement [N/mm2]
s maximum spacing of transverse reinforcement within lb, center to center [mm]
n number of bars being developed along the plane of splitting [-]
ξ substitute for various adjustment factors
A s,t, f yt
A s,t , f yt
str
s tr
lb
lb
Figure 2 shows the influence of transverse reinforcement for two typical cases. With small concrete cover (fig.
2a) splitting is towards the concrete cover. The transverse reinforcement only once crosses the splitting plane;
therefore the total area of transverse reinforcement crossing the splitting plane is Atr = As,t and the number of
bars developed along the splitting plane is n = 1. With small spacing, spalling of the entire concrete cover
becomes critical as shown in fig. 2b. In this case, the stirrup crosses the splitting plane twice. Therefore we
have Atr = 2 As,t and n = 4. In a slab with horizontal transverse reinforcement instead of the stirrups shown in fig.
2b, values for figure 2a remain unchanged (A tr = As,t, n = 1), but for the case of spalling, there is no contribution
of the transverse reinforcement (A tr = 0).
For example, a transverse reinforcement of bar size 10 mm with spacing of 200 mm and a specified yield
strength of 460 N/mm2 results in a factor of Ktr = 17 mm in the case of fig. 2a and Ktr = 8.7mm in the case of
figure 2b. In a slab with horizontal transverse reinforcement, Ktr is 0 in the case of spalling.
The transverse reinforcement index Ktr is used as “additional” concrete cover with the value of Ktr.
A s,t, f yt Figure 2c shows a supported slab. Vertical spalling is
prevented by the support reaction and the shear strut.
The edge bar is critical for horizontal splitting at the side
face of the slab. Normally ties are provided at the face of
the slab and they can improve splitting conditions if
str taken into account in the design.
Issue 09/2003
2/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
3. Final design formulas for design by means of Hilti Excel Spread Sheets
c + K tr
for ≤ 2 .5 (bonded-in bars and cast-in bars):
φ
f ck c + K tr lb fy γ
f bd = ⋅ ; or : = ⋅
4⋅γ φ φ c + K tr
f ck
φ
c + K tr
for > 2 .5 (bonded-in bars only):
φ
f ck c + K tr l fy γ
f bd = ⋅ 2 .5 + 0.83 ⋅ − 2 .5 ; or : b = ⋅
4⋅γ φ φ 4⋅ f c + K tr
ck 2.5 + 0 .83 ⋅ − 2.5
φ
where:
fbd design bond strength
lb bond length
φ nominal bar size
fck characteristic concrete cylinder strength
A tr ⋅ f yt c + K tr
Ktr K tr = ; ≤ 2.5 for cast - in bars
10 .34 ⋅ s t ⋅ n φ
Atr total cross-sectional area of all transverse reinforcement that is within the spacing s and that
crosses the potential plane of splitting through the reinforcement being developed [mm2]
fyt yield strength of transverse reinforcement [N/mm2]
st maximum spacing of transverse reinforcement within lb, center to center [mm]
n number of bars being developed along the plane of splitting [-]
Note: the following factors used in ACI 318 are set to be 1.0
β = 1.0 for uncoated reinforcement
λ = 1.0 for normal weight concrete
For more detailed Information see: Kunz, J.; Münger, F.: “Splitting- and bond failure of post-installed rebar
splices and anchoring.”; Bond in Concrete – from research to standards, Proceedings of the 3rd International
Symposium held at the Budapest University of Technology and Economics, Budapest, Hungary, 20 to 22
November 2002, p.447 -454.
(Copy available from Hilti Technical Service)
Issue 09/2003
3/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A08 Serviceability Limit State (SLS)
1. General
In general the Hilti HIT-Rebar system is designed to provide similar stiffness as cast in situ connections.
Therefore the provisions of the Standard apply in terms of detailing regarding serviceability limit state.
The limit state of cracking for high bond adhesive like Hilti HIT-RE 500 should be checked for
elevated service temperatures.
Table 1
Hilti HIT-RE 500: bond stress limitation fbt,s for quasi -permanent loads and elevated temperatures
Bar size 10 13 16 20 25 28 32 40 wm
∅ [mm]
[mm]
Temperature T
50°C / 122°F 5.3 4.8 4.2 3.7 3.2 2.9 2.7 2.3
0.3
60°C / 140°F 4.3 3.9 3.3 2.9 2.5 2.2 2.1 1.7
T [°C / °F] servi ce temperature in substrate at the position of the bonded bar
fb,s [N/mm2] bond stress under permanent loads
(load factor γf = 1.0 for dead load and permanent part of variable actions)
wm [mm] Mean value of expected crack width for permanent loads
Notes:
• Ultimate limit state (ULS) design is mandatory in all cases.
• Be aware that the loads in SLS are 50% to 60% of ULS loads for normal cases.
• The table is valid for concrete compressive strength fc ≥ 25 N/mm2
• Scatter of crack width is considerable and larger cracks may occur.
Issue 09/2003
1/1
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A09 Corrosion behavior of bonded-in reinforcement
The Swiss Association for protection against corrosion (SGK) was given the assignment of evaluating the
corrosion behavior of fastenings post-installed in concrete using the Hilti HIT-HY 150 and Hilti HIT-RE 500
injection systems.
Corrosion tests were carried out. The behavior of the two systems had to be evaluated in regard to their use in
field practice and compared with the behavior of cast-in reinforcement. The SGK can look back on extensive
experience in this field, especially on expertise in the field of repair and maintenance work.
The result can be summarized as follows:
For a summery of the test report ask the Hilti Technical Servi ce for the test report
Report No 02015a, dated September 25, 2002: „Corrosion behaviour of fastenings made with Hilti HIT-HY 150
and Hilti HIT-RE 500 injection systems“.
Issue 09/2003
1/1
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
1)
A10 Fire resistance design
If passive fire prevention requirements have to be met,
the suitability of rebar connections should be verified
additionally to ULS cold design.
linst
Note: for the Tables 1 and 2: Fs,T = force in bar when exposed to fire
Intermediate values may be interpolated linearly. Extrapolating is not permitted.
1)
for test reports contact your Hilti Technical Service: (Warrington Report WFRC No. C1211086)
- Test report for rebar connections suitable for fire rating using Hilti HIT-HY 150, IBMB, July 16, 1999
- Test report for rebar connections suitable for fire rating using Hilti HIT-RE 500, IBMB, Aug. 25, 2000
Issue 09/2003
1/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
linst
Issue 09/2003
2/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Max. bond stress, τT , depending on actual clear concrete cover for classifying the fire resistance.
It must be verified that the actual force in the bar during a fire, Fs,T , can be taken up by the bar connection of
the selected length, linst. Note: Cold design for ULS is mandatory. linst cf
Fs, T ≤ (linst – c f)⋅ ∅ ⋅ π ⋅ τT where: (linst - c 1) ≥ ls;
ls = length of overlap joint
φe = nominal diameter of bar
linst – c f) = selected overlap joint length; this must be at least ls, c
but may not be assumed to be more than 80 ∅
τT = bond stress when exposed to fire
Issue 09/2003
3/3
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A11 Fatigue of bonded-in reinforcement
for joints where imposed loading is predominantly cyclical
1. General Notes
For loadbearing elements which are subjected to considerable cyclic stress the bonded-in connections should
be designed for fatigue. In that case evidence for fatigue of reinforcing steel bars, concrete and bond should be
provided separately.
For simple cases it is reasonable to use simplified methods on the safe side.
The partial safety factors for loads are specified in the code for reinforced concrete.
The partial safety factors for material are specified in Table 1.
where:
FSd,fat Design value of the anchorage force for the ruling loading model for fatigue.
NRd Design resistance for static load of the anchorage (bond and concrete).
ffat Reduction factor for fatigue for bond and concrete: ffat = 0.5 eq. 2
If max/min of cycles is known, reduction factors are shown in fig. 1.
Figure 1
Diagram for a simplified approach
1 with 106 cycles
0.9 (Weyrauch diagram)
0.8
FSd,fat max
0.7 FSd,fat
/ N Rd FSd,fat max
0.6
0.5
0.4
0.3
0.2
0.1
FSd,fat min
0
0 0.2 0.4 0.6 0.8 1
F Sd,fat min / NRd 0 time
Issue 09/2003
1/1
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
A12 Guide Specifications for bonded-in reinforcement
Specifier Note - General:
This specification is intended to address the use of bonded-in reinforcing bars for safety-related applications,
such as structural connections in reinforced concrete. It has been prepared to assist design professionals in
the preparation of project or office master specifications. Only minor editing should be necessary with most
master specification systems.
Edit carefully to suit project requirements. Modify as necessary and delete/add items as applicable.
This is an open proprietary specification allowing users the option of approving other manufacturers that comply
with the criteria specified herein.
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes: Bonded-in reinforcement for concrete.
1.02 SUBMITTALS
Specifier Note: Insert appropriate section for the project as referred to below for shop drawings or submittals.
A. For bonded-in reinforcement as specified in Section 2.01.B submit in accordance with
Conditions of the Contract and Submittal Procedures Section.
1. Design values and physical characteristics for bonded-in reinforcement, including:
(Proposed to include the standards that is internationally recognised to that subject)
a. considerations for long-time and creep behaviour in elevated temperatures (Include
testing standard.),
b. considerations for installation sensitivity in terms of site conditions (hole cleaning
water saturated concrete,
c. evidence for adequate bond distribution over splice length for splices with cast-in place
bars (splice/splitting test),
d. approved design values for fire resistance where the ISO 834 Standard temperature/
time curve shall be applied (BS 476 : Parts 20 to 23),
e. design values for dynamic loading.
2. Product specifications including:
a. Injection material shelf life and storage conditions,
b. Material Safety Data Sheet,
c. Waste disposal considerations,
d. Overview of chemical resistance for hardened material.
Specifier Note: For normal application of bonded-in reinforcement it is assumed that concrete is not carbonised
and never salt infested at the position of the bars. Minimum concrete cover to bonded-in reinforcement should
be at least according to standard for the relevant environmental conditions.
3. Corrosion behaviour
Provide evidence for adequate corrosion protection of the injection bonding material for the
bonded-in reinforcement for internal [and external] use in normal not-carbonised and not salt
infested concrete
4. Quality Assurance Submittals:
Test Reports: Certified test reports showing compliance with specified performance
characteristics and physical properties.
5. Manufacturer’s installation instructions.
Sample demonstration for suitable installation procedure for holes deeper than 30 cm.
6. Installer Qualifications & Procedures: Submit a letter of procedure stating method of drilling,
the product proposed for use, the complete installation procedure, manufacturer training
date, and a list of the personnel to be trained on bonded-in reinforcing bar installation
B. Closeout Submittals:
Submit the following Record Documents:
1. Project record documents for installed materials in accordance with Closeout Submittals
Section.
2. Test records for field test according to Section 3.03.
1.03 QUALITY ASSURANCE
A. Installer Training: Conduct a thorough training with the manufacturer or the manufacturer’s
representative for the [contractor] [installer] on the project.
Issue 09/2003
1/4
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
1. Training to consist of a review of the complete installation process for bonded-in
reinforcement bars, to include but not limited to:
a. hole drilling procedure,
b. hole preparation & cleaning technique,
c. adhesive injection technique & dispenser training / maintenance,
d. reinforcing bar preparation and installation,
e. proof loading.
Specifier Note: Complete paragraph below to suit project and local jurisdiction requirements. Co-ordinate with
section 1.02.A above.
B. Certifications: Unless otherwise authorised by the Engineer, injection system shall have one of
the following certifications:
1.
2.
1.04 DELIVERY, STORAGE AND HANDLING
Specifier Note: Revise paragraph below to suit project requirements. Co-ordinate terminology with designations
used on the Drawings for other types of reinforcement, coated reinforcement, stainless steel, etc. Special
precautions shall be taken where pitting corrosion is a concern.
1. Prepared Reinforcing Bars: Grade 500, high bond, deformed type 2 as per EC 2. Size as
indicated on Drawings.
B. Injection Adhesive System:
1.Dual foil/cartridge packing injection system having fast curing hybrid adhesive, styrene free and
odour-less of 3:1 mixing ratio for anchorage to concrete, or approved equivalent.
2.Dual foil/cartridge packing injection system of high performance slows curing, odour-less
Epoxy adhesive having 3:1 mixing ratio for anchorage to concrete, or approved equivalent.
3.The Manufacturing and Expiry date must be clearly indicated on the packing for tracking
purposes and mixing of the chemical should be done using a static mixer during injection.
4.Where bonding injection system manufacturer is not indicated, subject to compliance with
requirements and acceptance by the Architect / Engineer, provide the following:
a. Approved substitute in accordance with Section - Product Substitution Procedures must
be comply with and all relevant test reports to be supported.
PART 3 – EXECUTION
3.01 INSTALLATION
Table 1
Batch Size Nos. of tests
>99 10 %
100 - 500 As per table 2
Issue 09/2003
3/4
Fastening Technology Manual
Bonded-in Reinforcement B 2.11
Europe
Table 2
Sequential % of tests Permissible No of Action upon batch Upon completion of Three
test stage. per batch. Failure per batch failure successful batch test.
1 10% 0 ( Nil) Seek the advise of the Revert to stage 2 testing
responsible engineer
2 5% 0 ( Nil) Revert to stage 1 Revert to stage 2 testing
3 2% 0 ( Nil) Revert to stage 1 Continue stage 3 testing
A. Testing: [2%] [10%] [25%] ______ of each type and size of drilled-in bars shall be proof loaded
by [the manufacturer representative] [the independent testing laboratory]. If [any] [more than
10%] ______ of the tested bars fail to achieve the specified proof load within the limits as defined
on the Drawings, all bars of the same diameter and type as the failed bar shall be tested, unless
otherwise instructed by the Engineer.
1. Proof loads shall be applied with a calibrated hydraulic ram. Displacement of adhesive bars
at proof load shall not exceed ∅ /10, where ∅ is the nominal bar diameter.
B. Minimum bar embedment, proof loads shall be as shown on the Drawings.
3.0.4. Values for Proof loading
Specifier Note: Proof loading of bonded-in bars is intended to catch significant installation problems, such as
partial or complete failure to cure. It is not intended to check the design capacity of the anchorage. Other limits
on displacement may be appropriate, depending on the magnitude of the proof load and the requirements of the
application.
B. Field quality control
1. Proof loads shall be applied with a calibrated hydraulic ram. Displacement of adhesive bars
at proof load shall not exceed ∅ /10, where ∅ is the nominal bar diameter.
2. Unless otherwise shown on the Drawings, minimum anchor embedment and proof load
shall be as follows:
Specifier Note: The proof loads provided in the following tables are based on the lesser of 50% of the minimum
ultimate bond strength in C20/25 concrete or 75% of the bar yield (Grade 500 reinforcing bar). The data shown
are appropriate for fast curing hybrid and slow curing Epoxy adhesive injection systems. Tension development
length values are based on Manufacturer’s Fastening Technology Manual for Post-installed Reinforcing Bars B
2.11, loaded with narrow support and edge distance ≥ 4 ∅ , bar spacing ≥ 8 ∅ (concrete splitting condition),.
Proof loads for shorter embedment but not less then minimum embedment may be calculated proportionally.
REINFORCING BAR GRADE 500, ribbed bars
INJECTION ADHESIVE SYSTEM: Fast Curing Hybrid and Slow Curing Epoxy Adhesive
BAR BAR EMBEDMENT LENGTH IN NORMAL WT. CONCRETE (C20/25)
SIZE
MINIMUM Fast curing Hybrid Adhesive Slow Curing Epoxy Adhesive
EMBEDMENT TENSION TENSION
∅ LENGTH PROOF PROOF
DEVELOPMENT DEVELOPMENT
10 ∅ LOAD LOAD
LENGTH linst LENGTH linst
mm mm mm kN mm kN
10 100 180 27 170 27
12 120 260 46 220 46
16 190 360 69 270 69
20 240 500 108 340 108
22 265 580 131 370 131
25 300 700 169 420 169
28 335 - - 540 212
32 385 - - 670 277
40 480 - - 980 434
Issue 09/2003
4/4
Fastening Technology Manual
Postinstalled Reinforcement Bars B 2.11
Europe
A13 Approvals and Test Reports
1. List of approvals for Hilti HIT-HY 150
3. Test Reports
Hilti Corporation
FL-9494 Schaan
Principality of Liechtenstein Hilti Fastening Technology Manual FTM B 2.11
Europe
www.hilti.com
Issue09/2003
1/1