You are on page 1of 6

Australasian Universities Power Engineering Conference- AUPEC2016

A Comprehensive Community Energy Storage


Planning Strategy based on a Cost-Benefit Analysis
Junainah Sardi1,2, N. Mithulananthan1, Duong Quoc Hung3
1
School of Information Technology and Electrical Engineering, University of Queensland, Brisbane, Australia
2
Faculty of Electrical Engineering, Universiti Teknikal Malaysia Melaka, Melaka, Malaysia
3
School of Engineering, Deakin University, Geelong, Australia
j.sardi@uq.edu.au, mithulan@itee.uq.edu.au, hung.duong@deakin.edu.au

Abstract— Energy Storage (ES) has been seen as a crucial Numerous studies on ES planning in distribution networks
element in active distribution networks. It facilitates a high have been reported considering different techniques and
penetration level of intermittent renewable energy in power objectives. For example, the authors in [3] applied an
systems thus provide several technical and economic benefits to analytical approach to find the optimal size of ES that can
the utility and consumer. However, given a high capital cost
associated with ES, it is crucial to develop an effective planning
solve voltage fluctuation problems and minimize annual
strategy to avail the maximum benefit. This paper proposes a costs. Heuristic approaches such as Genetic Algorithm (GA)
methodology to determine the optimal location and capacity of with Simulated Annealing [4], a hybrid of GA and AC
Community Energy Storage (CES) units by considering all their Optimal Power Flow [5], and Fuzzy Particle Swarm
possible benefits and costs. The benefits are obtained from Optimization [6] were also used to determine the optimal
energy arbitrage, peaking power generation, energy losses location and capacity of ES considering different objectives.
reduction, Transmission and Distribution (T&D) system In addition, the authors in [7] proposed a numerical approach
upgrade deferral, CO2 emission reduction and VAr support, to allocate and size ES for minimizing the cost through
while the costs include CES’s capital, replacement and accommodating all spilled wind energy and reducing network
Operational and Maintenance (O&M) costs. A comprehensive
cost-benefit analysis is conducted to identify the optimal Net
losses. This survey reveals that most of the existing works on
Present Value (NPV), Discounted Payback Period (DPP) and ES planning and cost-benefit analyses consider only one or
Benefit Cost ratio (BCR) of CES investment starting at current few benefits of ES. In addition, a research in [8] concluded
year, year 2025 and 2035. Numerical results show that the that deployment of ES is presently still uneconomic as the
proposed strategy is able to specify the optimal location and size overall ES installation cost is higher than the total profit
of CES unit for maximizing the NPV. Some interesting findings obtained from its deployment. It is expected that if all its
are also discussed in the paper. benefits and cost reduction in the future are considered, ES
Index Terms—Community Energy Storage (CES), distributed will be a profitable solution [9]. This paper proposes a
generation, CES planning, cost-benefit analysis, photovoltaic. methodology to determine the optimal site and capacity of
CES by considering all possible benefits obtained from CES.
I. INTRODUCTION The benefit includes energy arbitrage, peaking power
Energy Storage (ES) system has become a crucial element generation, energy losses reduction, T&D system upgrade
in smart distribution networks due to massive deployment of deferral, CO2 emission reduction and VAr support. In
intermittent Renewable Energy Sources (RES). Among them, addition, a comprehensive cost-benefit analysis is conducted
community level Distributed Photovoltaic (DPV) is the to identify the optimal Net Present Value (NPV), Discounted
fastest-growing power generation system owing to its Payback Period (DPP) and Benefit Cost ratio (BCR) of CES
technology advancement, investment cost reduction and investment for three scenarios that are CES deployment
environmental benefits [1]. Thus, the impact of intermittent starting at current year, year 2025 and 2035.
PV output power is being more severe at the community The rest of the paper is organized as follows: Section II
level. Community Energy Storage (CES) is capable of presents CES benefits. Section III discusses a methodology
solving a number of operational problems due to the for CES planning. Section IV presents numerical results.
intermittent characteristic of PV output while providing Finally, Section V concludes the paper by highlighting the
numerous other benefits such as ancillary services, peak load major conclusions and contribution of the work.
reduction and reliability improvement to the grid [2]. In order II. CES BENEFITS
to optimize these benefits, it is crucial to develop a planning This study considers the CES capability to shave the peak
strategy that includes the determination of the optimal load by storing energy during the off-peak period and
location, size and operational characteristic of CES. releasing the stored energy back to the grid during the peak
period. This application can make the demand profile flatten

978-1-5090-1405-7/16/$31.00 ©2016 IEEE


and improve the load factor. However, the economic distribution function (PDF) [16], [17]. In this model, there are
feasibility of the application should be justified by 96 time segments (i.e. 24 time segments for each season) in a
considering all associated investment cost and benefits. year where each has their own PDF of solar irradiance. The
Possible benefits that can be achieved from shifting the load continuous PDF of each hour is then divided into 20 states to
demand using CES are listed as follows: incorporate the PV output power as multistate variables in the
• Peaking power generation - gas combustion turbine plant planning problem formulation. Finally, the same approaches
cost reduction due to the unleashed power from CES, of modelling the combination of PV generation and load, and
during the peak load period for generating the same calculating the energy losses and demand in [16] are adopted
amount of peaking power [10], [11]. in this work.
• Energy arbitrage - the benefit from buying energy at a low
price during the off-peak period and selling the energy
stored back at a high price at the peak period [12].
• Energy loss reduction - CES discharging some energy to
the grid that may result in reductions in peak demand and
subsequent energy losses [12].
• T&D system upgrade deferral – CES is used to serve a
peak demand so that the T&D system upgrades can be
delayed [12].
• Reduction in CO2 emission- electricity demand shifting
by CES can reduce the CO2 emissions from coal-fired
power plants [13].
• Reactive power (VAR) support- that is used to maintain
the voltage levels on the distribution system. [14].
In order to capture all of these benefits in CES planning Figure 1 Flowchart of the proposed methodology.
strategy, an optimization technique as presented in the next
section is utilized. B. CES Operational Characteristic
III. METHODOLOGY A CES unit is assumed to be connected to an AC system
via bidirectional DC/AC converters that can be operated in all
The aim of the planning problem is to optimally site and four quadrants [18]. PCES at a specific bus and time is
size CES units in a system with distributed PV units based on dispatched with the aim of flattening the substation power
maximizing the total NPV obtained from CES deployment profile as much as possible based on a given population of
over a specified planning horizon. In this optimization CES capacity (MCES) by the GA. Therefore, a “Load
problem, the inputs are test system data, the probabilistic Following” control method is developed in MATLAB
model of PV and costs associated with CES units while the environment. The control strategy is able to charge CES
decision variables are the optimal location and capacity of during the off-peak period and to discharge it during the peak
CES units in kWh. Genetic Algorithm (GA) in the MATLAB period. Moreover, itis considered that the energy remaining in
optimization toolbox is used for solving the planning problem the CES at the beginning of the day is equal to that at the end
due to its simplicity and capability in handling integer of the day [19]. Specifically, the control mechanism will
variables and robustness. Figure 1 briefly illustrates the charge the battery if the overall downstream power is below
proposed methodology adopted in this paper. GA first the charge threshold, Pcha and discharge if the total
downstream power is above the discharge threshold, Pdis.
generates an initial population for the optimization problem.
These thresholds are determined using an iterative method as
Based on this initial population, real and reactive powers
shown in Figure 2. Thus, the power and energy variations of
dispatched by CES (i.e., PCES and QCES, respectively) are CES located at bus i and time t (i.e., PCESi,t and ECESi,t
determined using iterative and analytical methods. Using respectively) can be expressed as (1) and (2). It is noted that
these computed PCES and QCES, the rated power and energy of several indices ware used throughout this paper. They are
CES (i.e., PCESR and ECESR, respectively) and CES’s inverter system bus indices, i and j; time in hour, t; combined
size (SCESR) are next calculated. Finally, the objective function generation-load state, s; and year in the planning horizon, n.
is evaluated until the desired stopping criteria are met. These
 (PDt − Pdis ) ∈ PDt ≥ Pdis
steps are further detailed in the next subsections. 
PCESi ,t = (PDt − Pcha ) ∈ PDt ≤ Pcha (1)
A. Load and PV Modelling
0 ∈ P < P < P
The load model is assumed to follow the historical hourly  cha Dt dis

residential load data obtained in [15]. One day of the load


curve is picked from every season (i.e., winter, spring, E CESi ,t = E CESi ,t −1 − PCESi ,t Δt (2)
summer and autumn) in a year to represent every day in that
The positive PCES in (1) and (2) represents the discharged
particular season. PV generation is modelled by first
power while its negative value is the power charged to the
computing the probabilistic distribution of solar irradiance
CES unit, and PDt is the substation real demand power.
based on the historical data using the Beta probability
ΔVk ,s ,t + dV cor ,k , s ,t
QCESj,s ,t = (7)
K Qkj,s ,t
QCESj,t = max QCESj,s,t ( ) (8)

C. Problem Formulation
This planning problem is formulated as a nonlinear mixed
integer problem that has an objective function of maximizing
the NPV obtained from CES deployment as follows:

Fobj = PG + AB + LR + TDB + REC − CCES − OM (8)


Figure 2 Iterative method for determining the charge and discharge thresholds
of CES. Nyr
APG ∗ LCT
On the other hand, QCES is determined with an objective of
PG =  (1 + IR' )
n =1
n
(9)
bringing the voltage magnitude at every node within its
acceptable limit. The rationale behind the proposed method is 96
that there is a linearity and load independency of the
relationship between the reactive power injection (Qj) and Nyr
90 ×  (P CES ,t × Δt × E price,t )
voltage change ( Δ Vi ) as estimated in (3), where KQij is the
AB =  n =1
t =1
(1 + IR' ) n
(10)

scalar value relating Δ Vi and Qj [20].


ΔVi = K Qij × Q j (3) 96  20  
KQij is obtained by injecting Qtest to bus j while no additional
90 ×    (P loss 0,s ,t − Ploss,s ,t ) × ρ s ,t  × Δt × E price,t 


Nyr
 s =1 

t =1
active and reactive powers are injected to other buses. Power LR = (11)
n =1 (1 + IR')n
flow is then run at every state to calculate the change in
voltage at bus i (∆Vtesti,). Finally, KQij is computed using Tyr
CT & D * fr *UP
K Qij, s ,t =
ΔVtesti , s ,t
(4)
TDB =  (1 + IR ' ) n
(12)
Qtest n =1

The proposed approach begins by observing the system Nyr


2.6 × CS × CCO 2
operating voltage (V) at every state and time after CES
dispatched its active power. The worst bus (i.e. bus that has
REC = 
n =1 (1 + IR')n
(13)
the highest voltage violation from the upper or lower voltage
limit) at every state, is identified. Assuming that the worst bus
C CES = C P × S CESR + (C E + C R ) × E CESR (14)
at state s and time t is bus k. Given the lower and upper limits
of voltages are Vlow and Vup respectively, the desired voltage
Nyr
magnitude changes at bus k can be computed as: C M × PCESR
 (Vk , s ,t − Vlow ) ∈ Vk ,s ,t < Vlow
OM = 
n =1 (1 + IR')n
(15)

ΔVk , s ,t =  (V k , s ,t − Vup ) ∈ Vk , s ,t > Vup (5)
0 ∈ Vlow > Vk ,s ,t > Vup IR − F
 where IR' = (16)
1+ F
From (3), the reactive power dispatched by CES before
considering the correction in ∆V (∆Vcor) (QCES0j,s,t) needed to
achieve ΔVk ,s ,t is expressed as:
(
CS = 90 × E dis × C ps − E cha × C ch / 907.185 ) (17)

ΔVk ,s,t
QCES 0 j,s,t = (6) max  PCESi
2 2 
,t + Q CESi ,t 
K Qkj,s,t S CESR =   (18)
In order to cater for the worst condition, the highest QCES0 η
computed over all states at time t is chosen as QCES0 during
time t. It is noted that a CES location and the worst bus may M 
E CESR = (1 + κ ) ×  CESi + (1 − γ ) × M CESi  (19)
not be at the same point. Moreover, the reactive power is not  η 
efficiently travel to far places due to its I2X losses. Therefore,
the calculated QCES0 in (6) may not be sufficient to bring the [
C R = FR × (1 + IR' )− r + (1 + IR ')−2 r + (1 + IR ')−3r +  ] (20)
operating voltage within the acceptable limit. Due to this
reason, ∆Vcor is introduced. This value is determined as in (5) max(PCESi,t )
except that Vk,s,t is the operating voltage after the system is PCESR = (21)
η
being subjected to the computed QCES0 in (6). Then, QCES can
be calculated as follows:
in which PG, AB, LR, TDB and REC are the NPV benefits In addition to NPV, the values of DPP and BCR from the
from the CES’s peaking power generation, energy arbitrage, CES investment were also presented. DPP represents the
energy losses reduction, T&D system upgrade deferral and a number of years it takes to break even from undertaking the
reduction in CO2 emission, respectively. In contrast, the initial expenditure. DPP also takes into account the time
investment cost of CES includes the capital CES cost (CCES) value of money which yields more realistic view of the
and the operation and maintenance costs (OM). IR’, IR and F project profitability. Meanwhile, BCR is a ratio that is
are the effective interest, interest and inflation rate identified as the relationship between the cost and benefit of
respectively; APG is the annual average peaking power the proposed project [22]. It is used in this work due to the
generation from CES; LCT is the unit levelized annual cost of different optimal investment costs and benefits computed for
gas combustion turbine; Eprice,t is the market energy price; different CES configurations. By evaluating the DPP and
Ploss,s,t and Ploss0,s,t are the power losses for the system with BCR, the project profitability can be compared thoroughly.
and without CES deployment, respectively; ρ is the DPP and BCR are expressed as follows:
probability of the combined load-generation state. DCCFT
It is assumed that the T&D upgrade needs to be DPP = T + (24)
DCFT +1
implemented at year 1 of the planning horizon due to the load
CFn
growth in the network. Therefore, CES is deployed at year 1 DCFn = ∈ 0 ≤ n ≤ Nyr (25)
to delay the upgrade, where Tyr in (13) is the last year in the (1 + IR ' )n
planning horizon that the T&D upgrade project can be
deferred. CT&D is the average investment cost for each PG + AB + LR + TDB + REC + RSB
BCR = (26)
additional MW of distribution assets; fr is the fixed charge C CES + OM
rate for converting the investment cost to annuitized cost and where T is the last period with a negative discounted
UP is the T&D upgrade capacity; CS is the coal savings from cumulative cash flow, DCCF; DCCFT is the DCCF at the end
using CES in ton; CCO2 is the cost of reducing CO2 emission; of the period T; DCFT+1 is the discounted cash flow during
Edis and Echa are the total amount of energy discharged and the period after T and CFt is the actual cash flow [23].
charged by CES in kWh, respectively; Cps and Cch are
respectively the standard coal consumption rate of power
supply of the generation plants for peak shaving and routine IV. NUMERICAL RESULTS
period; CP, CE and CR are respectively the capital power The proposed methodology was tested on a 33-bus radial
conversion system (PCS), energy and replacement cost of distribution system [24] with a total load of 3.715 MW and
CES. N is the total number of buses; FR is a future value of 2.3 MVAR, and an annual energy demand value of 15.45
replacement costs; r is the replacement period in year that is GWh. DPV units are placed at all buses that are connected to
determined by dividing the maximum number of battery the loads in the system to represent the rooftop solar PV. The
charge/discharge cycles by the number of operating cycles total annual PV penetration, NPV in the system is 28.62%,
per year and CM is the annual operation and maintenance cost which can be estimated as follows:
of the CES [17], [21]. N PV = E PV / E L × 100 (27)
Another benefit from the CES deployment is VAr support where EPV and EL are respectively the annual energy
(RSB). RSB is not included in the objective function as it produced by PV and required by the load. The mean and
may cause the optimization to select the variable decision that standard deviation of solar irradiance data for three years are
result in the highest reactive power dispatched in order to obtained from [16]. Lithium-ion battery is considered the
obtain the maximum objective value function. This scenario choice of technology for CES due to its maturity for small-
may not be desirable from the power utility point of view. scale grid-connected applications and high efficiency. The
Therefore, this benefit will be added to the objective function maximum cycle in life for this battery is 4000 [25].
after the optimization process is completed. RSB can be Electricity prices are obtained from [26] in which a day of
calculated as: electricity price from every season is selected to represent the
96  20   electricity price for all the days in that particular season.
Nyr
90 ×    Q × ρ s ,t  × Δt × C kVAR 
CESi ,s ,t   Table I lists all the costs associated with CES and economic
 s =1 

t =1
RSB = (22) parameters used in the optimization. This work considers
n =1 (1 + IR')n
three different planning scenarios: CES deployments starting
In which CkVAR is the reactive power payment [14]. The at current year (Scenario 1), year 2025 (Scenario 2) and 2035
objective function in (8) is maximized subjected to several (Scenario 3). These scenarios are simulated to investigate the
constraints, which are power flow balance that considers the potential of CES investment in present and later years. It is
real and reactive power dispatched by CES and the feeder assumed that the PV penetration in the system is fixed for all
capacity limit. In addition, the constraint related to the the scenarios to reduce complexity. The planning horizon is
capacity of CES as presented in (23) is also included [17]. set to be 20 years. All GA parameters are in default values
(PCESi,t )2 + (QCESi,t )2 ≤ (SCESR ×η )2 (23) except for stall time limit and tolfun which are set to 6000
and 0.001 respectively.
Table II depicts the result from the proposed planning upgrade cannot be deferred by CES at year 17 for this
strategy. It can be seen that the optimal site of CES is bus 8 specified case. As the benefit contribution from the T&D
for Scenario 1 and bus 7 for Scenarios 2 and 3. It is also upgrade deferral is the largest, its absence caused a
found that as the cost of CES reduced in later years, the significant reduction in the total profit obtained. Meanwhile,
optimal CES penetration increased from 9.27% (3979 kWh) for the other two scenarios, this phenomenon occurs later
in Scenario 1 to 13.55% (5817 kWh) and 22.09% (9482 than the first scenario which is at year 19. This is due to the
kWh) in Scenarios 2 and 3, respectively. A similar trend was higher ECESR deployed for the latter scenarios that provides
found for the optimal values of PCESR and SCESR. This reveals more capability for CES to defer the T&D system upgrade.
that the CES cost reduction in later years allows more CES to
be penetrated in the system. A higher CES penetration level TABLE II. DETAILED RESULTS
may result in a higher benefit and total profit obtained from Scenario 1 2 3
CES deployment. This are reflected by higher values of the Optimal Location (Bus) 8 7 7
total profit and BCR, and also a faster DPP value for CES Optimal Capacity (kWh) 3979 5817 9482
Optimal Size (kW) 1002 1306 1818
deployment begins at later years than that at present as shown Optimal Inverter rating (kVA) 1518 2047 2547
in Table II. For instance, the total revenue recorded for CES Capital Cost (Mil) 4.9091 4.2388 4.2945
deployment start at 2025 and 2035 are about 4.7 Mil and 5.9 NPV O&M Cost (Mil) 0.1367 0.1781 0.2479
Mil, which correspond to 56.71% and 95.12% increments NPV Peaking Generation (Mil) 1.1445 1.4251 2.1628
NPV Arbitrage Benefit (Mil) 0.2911 0.4545 0.7738
respectively, than that starts now. A similar trend was also
NPV Energy Losses Reduction (Mil) 0.0708 0.1022 0.1413
found for the BCR value. Particularly, deferring T&D system NPV T&D upgrade deferal benefit (Mil) 6.3456 6.8527 6.8527
upgrade contributed the highest profit from CES deployment. NPV Reduction in CO2 Emission (Mil) 0.1976 0.2889 0.4709
This is due to the high cost of T&D system upgrade and the NPV VAR support (Mil) 0.0052 0.0090 0.0120
lower annual peak demand growth assumed in this work. Objective Function (Mil) 3.0038 4.7064 5.8591
Total Profit (Mil) 3.0090 4.7155 5.8711
Conversely, VAr support recorded the lowest benefit as in Discounted Payback Period (year) 6.12 4.66 4.37
this case study, only a small amount of VAr is needed for Benefit to Cost ratio 1.60 2.07 2.29
voltage profile improvement. Overall, it is revealed from
Table II that there is a promising economic profit from CES 1
No CES CES
0.9
deployment as its cost becomes lower in later years. 0.8
Daily Load Factor

0.7
TABLE I. ECONOMIC PARAMETERS 0.6
0.5
Value Parameter (unit) Value 0.4
Parameter (unit) 0.3
Current 2025 2035 Cps (kg/kWh) [13] 0.48
0.2
CE($/kWh) [25] 543 280 180 Cch (kg/kWh) [13] 0.27
0.1
CP($/kVA) [25] 813 580 510 CkVAR (cents/kVArh) [27] 0.1063 0
CM($(kW) [25] 10 CT&D (Mil $/MW) [9] 2 Winter Spring Summer Autumn
IR (%) [17] 5 fr [9] 0.13
Figure 3 Daily load factor improvement for Scenario 3.
F (%) [17] 1 UP (kW) 2000
LCT($/kW) [28] 162 CCO2 ($/ton) [29] 22.4
η [25] 0.9 κ [13] 0.1 6
Scenario 1 Scenario 2 Scenario 3
γ [25] 0.9 Annual demand growth (%)[26] 1.3 5
Discounted Cumulative Cash Flow (Mil)

Note: All values of the costs is in AU dollars.


4

Figures 3 and 4 illustrate the daily load factor 3

improvements for Scenario 3 and the DCCF for all scenarios 2


from the proposed planning strategy, respectively. It is 1
revealed from Figure 3 that CES deployment based on 0
proposed planning strategy was able to improve the daily load -1
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

factor for all the seasons as high as 99% from the base case -2
load factor. For example, the daily load factor during winter -3
for the system with CES is 0.9, which is almost twice than -4
that without CES at 0.453. An increase in the daily load Year in the planning horizon

factor indicates that the demand profile of the system with Figure 4 DCCF of CES investment for current, 2025 and 2035 periods.
CES is more flat than that without CES. On the other hand, it
To validate the proposed method in determining the
can be observed from Figure 4 that the DCCF for all
operational characteristic of CES to improve the voltage
scenarios decreased at year 11 due to the CES replacement
profile, the operating voltage distribution for a day in four
cost. Additionally, it is found that at year 17 and above,
different seasons in Scenario 1 is recorded in Figure 5. It is
DCCF for Scenario 1 had a slower increment than that at the
assumed that the upper and lower voltage limits are 1.06 and
earlier years. This is due to the fact that no benefit is obtained
0.94 p.u, respectively. Figure 5 reveals that the operation of
from the T&D system upgrade deferral as CES capacity
CES units with optimal power factor (PF) dispatch can
installed in the system no longer meets the peak demand
significantly improve the voltage profile when compared to
increment in that particular year. This also means that the
that with unity PF operation. Although dispatching active
power only by CES may also improve the voltage profile, it is [6] Y. Zheng, Z. Y. Dong, F. J. Luo,K.Meng, J. Qiu, and K. P.Wong,
“Optimal allocation of energy storage system for risk mitigation of
not sufficient to bring all the operating voltages within the DISCOs with high renewable penetrations,” IEEE Trans. Power Syst.,
desired limit. In order to bring all the voltages within its vol. 29, no. 1, pp. 212–220, 2014.
limits using a unity PF CES, more active power dispatched is [7] J. Taylor, J. W. Smith, and R. Dugan, “Distribution modeling
needed. This may lead to a significant increase in the CES requirements for integration of PV, PEV, and storage in a smart grid
environment,”IEEE Power Energy Soc. Gen. Meet., pp.1–6, Jul. 2011.
investment cost. Therefore, as far as the voltage constraint is [8] Y. Yang, H. Li, A. Aichhorn, J. Zheng, and M.Greenleaf, “Sizing
concerned, CES deployment with optimal PF dispatch could strategy of distributed battery storage system with high penetration of
be more profitable than that with unity PF operation. photovoltaic for voltage regulation and peak load shaving,” IEEE
Trans. Smart Grid, vol. 5, no. 2, pp. 982–991, Mar. 2014.
[9] Abeygunawardana, A., Ledwich, G. “Estimating benefits of energy
storage for aggregate storage applications in electricity distribution
networks in Queensland”, IEEE Power Energy Soc. Gen. Meet., pp. 1–
5, July 2013.
[10] Y. Yang; N.Yang, and H. Li, "Cost-benefit study of dispersed battery
storage to increase penetration of photovoltaic systems on distribution
feeders," IEEE Power Energy Soc. Gen. Meet., pp. 1-5, July 2014.
[11] N. Jayasekara, M. A. S. Masoum, P. J. Wolfs, “Optimal Operation of
Distributed Energy Storage Systems to Improve Distribution Network
Load and Generation Hosting Capability,” IEEE Trans. Sustainable
Energy, vol. 7, no. 1, pp. 250–261, 2015.
[12] J. Eyer, Electric Utility Transmission and Distribution Upgrade
Deferral Benefits From Modular Electricity Storage Sandia National
Laboratories, Tech. Rep. SAND2009-4070, Jun. 2009.
[13] X. Yan, X. Zhang, H. Chen, Y. Xu, and C. Tan, “Techno-economic
Figure 5 Distribution of the system operating voltage for Scenario 1. and social analysis of energy storage for commercial buildings,”
Energy Convers. Manag., vol. 78, pp. 125–136, 2014.
V. CONCLUSION [14] D. Rastler, “Benefit analysis of ES: Case study with Sacramento
This paper has presented a methodology to identify the Municipal Utility District,” EPRI, Tech. Rep. 1023591, 2011.
[15] Xcel Energy Data Archive. [Online]. Available: https://www.
optimal site and size of CES by considering all its possible xcelenergy.com /staticfiles/xe/Corporate/Corporate PDFs/AppendixD-
benefits. The benefits are obtained from energy arbitrage, Hourly_Load_Profiles.pdf.
peaking power generation, energy losses reduction, T&D [16] D. Q. Hung, N. Mithulananthan, and K. Y. Lee, “Determining PV
system upgrade deferral, a reduction in CO2 emission and penetration for distribution systems with time-varying load models,”
IEEE Trans. Power Syst., vol. 29, no. 6, pp. 3048–3057. Apr. 2014.
VAr support. A comprehensive cost-benefit analysis is [17] A. Awad, “Novel planning and market models for energy storage
conducted to specify the optimal NPV, DPP and BCR of CES systems in smart grids,” Phd Thesis, 2014.
investment for three scenarios that are CES deployment [18] A. F. Crossland, D. Jones, and N. S. Wade, “Planning the location and
starting at current year, year 2025 and 2035. Moreover, the rating of distributed energy storage in LV networks using a genetic
algorithm with simulated annealing,” Int. J. Electr. Power Energy
probabilistic distribution of PV output is considered for Syst., vol. 59, pp. 103–110, Jul. 2014.
representing PV uncertainties. The findings reveal that the [19] S. Shao, F. Jahanbakhsh, J. R. Agüero, and L. Xu, “Integration of
proposed strategy is able to identify the optimal location and PEVs and PV-DG in Power Distribution Systems using Distributed
size of CES for maximizing the profit. It is also found that the Energy Storage – Dynamic Analyses,” IEEE PES Innovative Smart
Grid Tech. (ISGT), pp. 1–6, 2013.
DPP and BCR values for CES allocation starting at current [20] J. Yaghoobi, N. Mithulananthan, and T. K. Saha, “Effect of PV power
year are 6.12 and 1.6, respectively. In addition, the numerical injection in unbalanced distribution systems,” in Australasian
results show that there is a promising economic profit from Universities Power Eng. Conf., AUPEC 2014, pp. 1–6.
CES deployment as the cost of CES becomes lower in later [21] Y. M. Atwa, “Distribution System Planning and Reliability
Assessment under High DG Penetration,” Phd Thesis, 2010.
years. The results also demonstrated that the deferring T&D [22] Investopedia, [Online], Available: http://www.investopedia.com
system upgrade is the highest benefits contributed by CES, /terms/ d.asp.
followed by the peaking generation and energy arbitrage. [23] EasyCalculation.com., [Online], Available: https://www.Easycalcu
Finally, the operation of CES with optimal PF dispatch can lation.com/budget/learn.php.
[24] N. Acharya, P. Mahat, and N. Mithulananthan, "An analytical
significantly improve voltage profiles. approach for DG allocation in primary distribution network," Int. J.
Elect. Power Energy Syst., vol. 28, pp. 669-678, Dec. 2006.
REFERENCES [25] Brinsmead TS, Graham P, Hayward J, Ratnam EL, Reedman L. Future
[1] B. Mountain and P. Szuster, “Solar, solar everywhere: opportunities energy storage trends: an assessment of the economic viability,
and challenges for australia’s rooftop PV systems,” IEEE power potential uptake and impacts of electrical energy storage on the NEM
energy Mag., vol. 13, no. 4, pp. 53–60, Aug. 2015. 2015-2035, CSIRO, Australia. Report No. EP155039; 2015.
[2] B. A. Nourai and C. Schafer, “Changing the Electricity Game,” IEEE [26] Australian energy Market Operator (AEMO), [Online]. Available:
Power & Energy Magazine, pp. 42–47, August 2009. http://www.aemo.com.au/.
[3] Dunn B, Kamath H, Tarascon J-M. Electrical energy storage for the [27] V. Kekatos, G. Wang, A. J. Conejo, and G. B. Giannakis, “Stochastic
grid: a battery of choices. Science 2011;334:928–35. Reactive Power Management in Microgrids with Renewables,” IEEE
[4] Hoffman MG, Sadovsky A, Kintner-Meyer MC et al. Analysis tools Trans. Power Syst., vol. 30, no. 6, pp. 3386–3395, 2015.
for sizing and placement of energy storage in grid applications: a [28] K. Spees, S. a Newell, J. P. Pfeifenberger, and C. H. M. Hill, “Cost of
literature review. Pacific Northwest National Laboratory; 2010. New Entry Estimates For Combustion-Turbine and Combined-Cycle
[5] Yuan. G, “Improving grid reliability through integration of distributed Plants in PJM,” PJM Group, 2011.
PV and ES ”,IEEE innovative smart grid tech. ISGT 2012, p.1–2. [29] EconWeekly, (2016) [Online]. Available: http://www.econweekly.
com/2007/09/on-cost-of-reducing-co2-emissions.html.

You might also like