You are on page 1of 10

This article appeared in a journal published by Elsevier.

The attached
copy is furnished to the author for internal non-commercial research
and education use, including for instruction at the authors institution
and sharing with colleagues.
Other uses, including reproduction and distribution, or selling or
licensing copies, or posting to personal, institutional or third party
websites are prohibited.
In most cases authors are permitted to post their version of the
article (e.g. in Word or Tex form) to their personal website or
institutional repository. Authors requiring further information
regarding Elsevier’s archiving and manuscript policies are
encouraged to visit:
http://www.elsevier.com/authorsrights
Author's personal copy

Construction Cost Overruns and


Electricity Infrastructure: An
Unavoidable Risk?
Dr. Benjamin K. Sovacool is An analysis of 401 power plant and transmission projects
Director of the Danish Center for in 57 countries suggests that costs are underestimated in
Energy Technologies at AU-Herning
and a Professor of Business and three out of every four projects, with only 39 projects
Social Sciences at Aarhus University across the entire sample experiencing no cost overrun or
in Denmark. He is also Associate
Professor of Law at Vermont Law underrun. Hydroelectric dams, nuclear power plants,
School (VLS), where he manages the wind farms and solar facilities each have their own unique
Energy Security and Justice Program
at its Institute for Energy and the set of construction risks.
Environment.
Benjamin K. Sovacool, Daniel Nugent and Alex Gilbert
Daniel Nugent is a Research
Associate at VLS’ Institute for
Energy and the Environment,
primarily providing legal support to
the U.S. Department of Energy’s
SunShot Plug-&-Play Initiative. He I. Introduction Strategic Sourcing, 2014).
is also nearing completion of his J.D./ These expenses exclude other
Energy Certificate and a Master’s Those outside the construction ‘‘soft costs’’ such as contingency
Degree in Environmental Law and industry may be surprised to fees, risk premiums, land, and
Policy. learn that the cost of building permitting (Severance, 2009).
power plants has escalated in The nuclear energy industry
Alex Gilbert is an Energy Analyst
at Haynes and Boone, LLP. He recent years. The Power Capital has been particularly hard hit,
received his Master’s Degree of Costs Index, which tracks the with material, labor, and
Energy Regulation and Law from expense of power plant materials engineering costs for nuclear
VLS, where he also served as a and components, showed an power plants jumping more than
Research Associate at the Institute for increase in North America by a the average over the same
Energy and Environment. factor of 2.26 between 2000 and period, meaning a plant that cost
2013, and in Europe by a $4 billion to build in 2000 would
factor of 1.93 over the same cost almost $12 billion today
period (IHS Costs and (Findlay, 2010).

112 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 The Electricity Journal
Author's personal copy

But how do the risks of Independent of their type, we completed utility-scale projects
construction cost overruns conclude that construction costs greater than 1 MW in size. This
compare across different forms of for electricity projects are difficult excluded forms of distributed
electricity infrastructure? How do to predict, as only 39 projects generation such as fuel cells and
utility-scale renewable sources of across the entire sample were Stirling engines, smaller-scale
electricity such as wind farms and completed at or under budget. We generation sources such as diesel
solar facilities perform compared also find that hydroelectric dams, generator sets and microhydro
to thermal plants, nuclear nuclear power plants, wind dams, and projects canceled or
reactors, and hydroelectric dams? farms, and solar facilities each still under construction in late
Where do high-voltage have their own unique set of 2013 and early 2014. As locating
transmission networks fall on this construction risks, which we reliable data for both the original
continuum of overrun risk? elaborate on below. cost estimate and the actual cost of

T his article answers such


questions by exploring
initial construction budgets and II. Research Methods
a project was surprisingly
difficult, we choose not to confine
our data collection to any
final costs associated with 401 geographical area or period of
separate power plant and In defining the scope of this time in order to make our
transmission projects, spread study, we first decided to limit database as large, and robust, as
across 57 countries, representing our assessment to electricity possible.
nearly $820 billion worth of
investment and 325,515 MW of
installed capacity. We find that
infrastructure, given that
transportation projects have
already been assessed extensively
T o begin collecting data, we
first searched the energy,
electricity, transport, and
although costs are by Flyvbjerg and his colleagues, infrastructure literature for
underestimated in three out of who compiled a database of 258 reliable peer-reviewed data,
every four projects, the frequency transportation infrastructure which we did find in a few
and magnitude of those overruns projects worth $90 billion instances (Flyvbjerg et al., 2002,
differ substantially by size, (Flyvbjerg et al., 2002, 2004). 2004; De Bondt and Makhija, 1988;
location, and fuel source, as Secondly, we decided to Marshall and Navarro, 1991;
Figure 1 summarizes. investigate only actually Grubler, 2010; Ansar et al., 2014;
[(Figure_1)TD$IG] Bacon and Besant-Jones, 1998).
120 However the rest we compiled
106
ourselves by searching hundreds
100 of project documents, press
Energy infrastructure
projects (n=401) releases, and reports (Appendix
80
I). We only included a project
Frequency (n)

60 in our database when we could


47 50
43 find complete information
39
40 regarding:
21 24  The year the project entered
20 16
10 8 9 10 10 service;
4 4
 Its geographic location;
0
 Its name;
 Its size in installed capacity
(in MW or kV);
Cost escalaon (%)
 Its estimated or quoted
Figure 1: Frequency and Cost Escalation of Electricity Infrastructure Projects construction cost;

May 2014, Vol. 27, Issue 4 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 113
Author's personal copy

 Its actual construction cost; precise phrase, we also inferred A. Hydroelectric dams
and them if there was a difference
 If available, its estimated between the quoted cost at the Sixty-one hydroelectric dams
construction time and actual start of project and quoted cost at made it into our sample
construction time (which we were the completion of project. representing 113,774 MW of
able to find for a smaller installed capacity worth $271.5
subsample of 327 projects). billion of investment. These
We updated all costs and III. Results projects experienced a total of
currencies to US$2012 using $148.6 billion in cost overruns
historical currency conversions Across our entire sample of (38.3 percent of the total overrun
available at Oanda.com and more than 400 projects, the cost across the entire sample) and
adjustments for inflation from the average installed capacity was exhibited a mean cost escalation
Statistical Abstracts of the United 927 MW for a power plant, and of 70.6 percent. Cost overruns also
States. Our final dataset the average length was 193 km afflicted more than three out of
encompassed 401 projects for a transmission line. The mean every four (75.4 percent) of the
(Appendix II). installed cost per kilowatt (kW) hydroelectric projects in the

I n building our database this


way, some caveats deserve
mentioning. We searched only in
was $3,185. The average,
randomly chosen project took
73.4 months to construct and had
sample. Hydroelectric dams had
the longest mean construction
time of all projects, as well as the
English, so our sample has a a cost overrun of $1 billion (or a largest total cost overrun amount
likely bias for North American mean budget escalation of 66 per project, as Figure 2 reveals.
and European projects (66
percent of those in the database).
We also built our database from
percent). Overall, 75.1 percent of
projects in the sample
experienced a cost overrun. As
O ne possible explanation for
why hydroelectric projects
suffer the largest mean cost
September 2013 to January 2014, this section of the article overrun of any project is that they
meaning any newly released explains, the particular are, on average, more materials-
data post-Jan. 31, 2014, would construction cost overrun risks intensive than other energy
not be included. By differ meaningfully between sources. On a per GW basis, for
‘‘construction cost’’ we refer to hydroelectric dams, nuclear instance, they need three times as
‘‘the process of assembling the power plants, wind farms, and much concrete as a nuclear
components of the facility, the solar energy facilities. reactor (Sovacool, 2010). The
carrying out of civil works, [and]
[(Figure_2)TD$IG]
the installation of component
and equipment prior to the start 3000 120
Mean construcon me
of commercial operation’’ 2500 (right axis) 100
(Zerger and Noël, 2011). This Mean cost overrun (le
Millions of US$2012

axis)
means we investigated so-called 2000 80
Months

‘‘installed costs’’ rather than


1500 60
‘‘overnight construction costs’’
(Koomey and Hultman, 2007). 1000 40
Because we are cognizant that
500 20
the term ‘‘cost overrun’’ is a
pejorative term that project 0 0
sponsors may not want to Hydro Nuclear Thermal Wind Solar T&D

publicize, we not only detected Figure 2: Mean Construction Times and Cost Overruns for Electricity Infrastructure by
them when documents used that Reference Class. Note: Construction time data are from a smaller sample of projects

114 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 The Electricity Journal
Author's personal copy

World Commission on Dams has cost escalation was 56 percent and the monotonic relationship
also posited that large dams are that about three-quarters of between time overruns and cost
unusually prone to unforeseen projects were afflicted by cost overruns. One explanation for
excavation and construction overruns (World Commission on this mismatch between project
problems given that geotechnical Dams, 2000). In parallel, the delays and cost overrun trends
conditions at the site, such as the World Bank has noted could be that costly attempts were
quality of foundational rocks and meaningful cost overrun trends in made to accelerate schedules so as
composition of construction some of their assessments of large to minimize delays. This could
materials, cannot be precisely hydropower projects (Merrow have resulted in higher wages and
evaluated until after construction and Shangraw, 1990; Bacon et al., overtime costs, used to attract
begins (World Commission on 1996). workers, leading to a decrease in
Dams, 2000). Building dams thus lead times but an increase in
involves a great deal of B. Nuclear power plants expenses (U.S. Energy
(expensive) trial and error. Information Administration,

O ther studies seem to


confirm our findings about
hydroelectric infrastructure being
One hundred and eighty
nuclear reactors in our sample,
representing 177,591 MW of
1986).
Another possible reason
nuclear plants were prone to such
prone, excessively, to cost installed capacity and $459 billion a large total amount of cost
overruns. One recent study from worth of investment, generated overruns (almost two-thirds of all
Flyvbjerg and his colleagues almost $231 billion in cost costs in our sample of 401
utilized reference class overruns (59.5 percent of all projects) could be that atomic
forecasting to assess the outcomes overruns across the sample), the energy was not technically or
and costs of 245 dams—186 of largest of any class of technology. economically feasible when it was
which were hydroelectric—built As Figure 3 indicates, such originally embraced in the 1940s
between 1934 and 2007, across reactors had a mean cost and 1950s. For example, the
five continents and 65 countries escalation of 117.3 percent, and Dwight D. Eisenhower
(Ansar et al., 2014). These dams cost overruns afflicted more than Administration decided to
collectively involved more than nine out of every 10 of the projects develop nuclear power plants in
$353 billion worth of investment. in our sample. the 1950s for entirely political
The study found ‘‘overwhelming Interestingly, 64 percent of reasons, seeking to demonstrate
evidence that budgets are nuclear projects had a time positive aspects of nuclear energy
systematically biased below overrun yet close to all of them after World War II, and to
actual costs of large hydropower (97.2 percent) had a cost overrun, instigate a technology race with
dams’’ and that ‘‘actual costs were which does cast some doubt on the Soviet Union (Byrne and
[(Figure_3)TD$IG]
on average 96 percent higher than
estimated costs.’’ The authors 100
90 Mean me overrun (%)
highlighted that these cost 80
Projects with overrun (%)
overrun figures are exceptionally 70
60
conservative as they exclude 50
inflation, substantial debt 40
30
servicing, and other 20
environmental and social costs. 10
0
Similar conclusions were reached Hydro Nuclear Thermal Wind Solar T&D

by the World Commission on


Figure 3: Mean Time Overruns and Percentage of Projects with a Cost Overrun for
Dams, who surveyed 81 large Electricity Infrastructure by Reference Class. Note: Construction time data are from a
projects and found that the mean smaller sample of projects

May 2014, Vol. 27, Issue 4 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 115
Author's personal copy

Hoffman, 1996). Similarly in used throughout industry and not University of California at
France, Charles de Gaulle necessarily only the energy Berkeley, and the Lawrence
promoted nuclear power plants industry): those at ‘‘big plants,’’ Berkeley National Laboratory
as a mechanism to reconstruct those with medium-sized assessed a three decade historical
French national identity. Nuclear ‘‘modules,’’ and those with database of delivered costs from
technology was seen by French smaller-scale systems that were each of 99 conventional nuclear
policymakers as a way to ‘‘continuously’’ operated. They reactors operating in the United
simultaneously rebuild French found that the ‘‘highest learning States (at that time) (Hultman
infrastructure and reestablish its effects’’ were observed for the et al., 2007). Their assessment
role as a world leader (Hecht, smallest facilities and that ‘‘big found a significant group of
1998). In both the French and plants and modules display less plants with extremely high
American cases, government dynamic learning effects’’ historical costs: 16 percent in the
created a market for nuclear (Christiansson, 1995). Indeed, in more than 8¢/kWh category. The
power, rather than the other way authors pointed out two unique
around—meaning cost attributes of reactors that made
considerations came second to Nuclear technology was them prone to unexpected
political ones. seen by French increases in cost: (1) their

A third reason nuclear plants


experienced major cost
overruns relates to the process of
policymakers as a way
to simultaneously
dependence on operational
learning, a feature not well suited
to rapidly changing technology
‘‘regulatory ratcheting.’’ Dozens rebuild French and market environments subject
of reactors in our sample were infrastructure and to local variability in supplies,
under construction during the reestablish its role as a labor, technology, public opinion,
major nuclear accidents at Three and the risks of capital cost
Mile Island (in 1979) and
world leader. escalation; and (2) difficulty in
Chernobyl (in 1986). After these standardizing units, or the
events, regulatory requirements idiosyncratic problems of relying
were significantly tightened, with some cases, such as France, on large generators whose specific
significant impacts on equipment nuclear power reactors have site requirements do not allow for
needs, construction designs, shown a negative learning curve mass production.
labor, and materials. As Cohen with rising costs between each
writes, ‘‘ratcheting applied to generation of technology C. Wind and solar farms
plants under construction caused (Grubler, 2009).
much more serious problems. As A fifth and final reason, at least Thirty-five onshore and
new regulations were issued, for reactors in the United States, offshore wind farms, constituting
designs had to be modified to which composed a large part of 6,201 MW of installed capacity
incorporate them’’ (Cohen, 1990). our sample, is that that there was and worth $20.1 billion in
This resulted in significant price no universally accepted or investment, generated $1.1 billion
increases and delays. standardized plant design when of cost overruns, the second
A fourth reason involves most facilities were being built smallest in our sample. These
‘‘negative learning.’’ Researchers throughout the country. wind farms had a mean cost
from the International Institute Consequently, engineering costs escalation of only 7.7 percent, and
for Applied Systems Analysis for almost every single plant were while cost overruns afflicted
looked at the learning curves for much higher than they would be slightly more than half (57
three types of general otherwise. Researchers at percent) of projects, the mean cost
manufacturing processes (i.e., Georgetown University, the overrun amount was only $32.8

116 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 The Electricity Journal
Author's personal copy

[(Figure_4)TD$IG]
Mean size, Right Axis
9000
Mean cost, Le Axis
2000 cost of scaling is justified by
8000 Mean cost overrun, Le Axis 1800 greater energy capture, resulting
7000 1600 in a lower levelized cost of wind
1400 generated electricity. Solar
6000
1200
5000 facilities, by contrast, have
1000
4000 benefited from lower priced
800
3000 inputs such as silicon and faster
600
2000 rates of technological learning
400
1000
(Nemet, 2006, 2009).
200
0 0
Hydro Nuclear Thermal Wind Solar

Figure 4: Mean Size (MW), Cost Overrun (Millions of USD), and Cost (per installed kW) for IV. Discussion
Electricity Infrastructure by Reference Class
What, then, accounts for the
prevalence of cost overruns across
million. Thirty-nine large solar PV escalation. However, the price per these distinct classes of electricity
or CSP power plants, installed kW jumps—suggesting projects? While not an exhaustive
representing 2,374 MW of that one must ‘‘pay’’ for the explanation, this section proposes
installed capacity worth $16.5 mitigation of construction risk at least three fundamental
billion worth of investment, that these smaller projects offer. reasons.
actually came in as a class $4.2
million under budget, or $200,000
less than expected per project,
As to the subtle differences
between wind and solar—both
are considered forms of
F irst, construction cost
overruns are multi-causal;
they cannot be reduced to a single
with a mean cost escalation distributed generation and are factor, which means even having
(overall, when it did occur) of 1.3 built in much smaller increments one thing ‘‘go wrong’’—such as a
percent. These solar systems had than thermal, nuclear, and hydro delay, missing component, or
the highest rate (28.2 percent) of facilities—perhaps wind shortage of labor—can impact
cost underruns, when excluding experienced a greater degree and construction schedules. The U.S.
transmission projects, as well. extent of cost overruns due to Energy Information

H owever, our class of solar


facilities also had, by far,
the highest construction costs per
recent trends specific to that
sector. Rapid growth in demand
has led to shortfalls of equipment,
Administration (EIA) made this
argument when looking at the
factors causing cost overruns in
installed kW, in some instances and macroeconomic drivers such the nuclear industry in the 1980s,
exceeding more than three times as labor costs and commodity and concluded that ‘‘increases in
that of thermal and nuclear prices have led to higher capital the quantities of land, labor,
plants. (Wind farms had a far and operating expenses (Levitt material, and equipment’’ as well
lower mean cost per kW, coming et al., 2011; Bolinger and Wiser, as increases in financing charges
third in terms of cheapness after 2009). Bolinger and Wiser (2012) all played contributory roles (U.S.
thermal and nuclear plants). The attribute much of the increase to EIA, 1986). Similarly, technical
implication—evident in ‘‘turbine scaling,’’ making construction problems, poor
Figure 4—seems to be that as individual units larger, which implementation by suppliers and
facilities grow smaller, they found to have been the contractors, changes in economic
construction lead times drop largest single contributor to a and regulatory conditions, and
significantly, and the amount of price doubling of wind energy resettlement costs all play
the average cost overrun declines from 2000 to 2008, although they contributory roles to cost
along with the percentage of cost emphasize that the incremental overruns for hydroelectric dams

May 2014, Vol. 27, Issue 4 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 117
Author's personal copy

(World Commission on Dams, economic development effects. V. Conclusion


2000). This misinformation intentionally
Second, poor management and/ distorts risk assessments and Essentially, our data suggests
or accountability can be just as conceals the true risk of projects that power plants and
influential in causing an overrun from investors, taxpayers, and investments in electricity
as difficulties with technology and regulators until it is ‘‘too late’’ to infrastructure are risky ventures.
equipment. The EIA confirmed abandon a project. Contractors The average length of
this point when they compared eager to have their projects construction for the 401 projects
cost overruns between utilities accepted may produce overly we surveyed exceeded 70 months,
that performed their own optimistic assessments at the which, by the way, is longer than
construction management and genesis of a project expecting that the duration of World War II. In
those that outsourced it. They addition, for some specific
found that ‘‘the management technologies, mean construction
structure under which a power times surpassed 118 months
plant is constructed is an (hydroelectric dams) and 90
important determinant of real months (nuclear reactors). Across
overnight costs’’ and that direct the whole sample, the average
utility participation in the cost overrun was $967 million per
construction process contributed project or an overrun of 66.3
to lower costs and increased percent, rising to $1.2 billion per
learning (U.S. EIA, 1986). A nuclear project (mean cost
separate study of the Japanese escalation of 117 percent) or $2.4
nuclear power industry reached billion per hydro project (mean
much the same conclusion, noting cost escalation of 70.6 percent).
that nuclear power plant operators Also, across the entire sample 75.1
with large ownership stakes it will be too far along to back-out percent of projects suffered cost
exercised more diligent cost by the time its viability can be more overruns.
control than when overruns were
spread over a larger number of co-
owners (Lyon and Mayo, 2005).
accurately assessed (Flyvbjerg
et al., 2003). According to
Flyvbjerg and his colleagues,
R evealingly, while solar and
wind have lower overall
construction risks, they were still

T hird, cost overruns may not


always be accidental, and
can, in a sense, be strategic. That is,
contractual penalties for
producing overly optimistic
assessments are lower than the
susceptible to cost overruns.
Almost one in three solar
projects (28.2 percent) suffered an
project sponsors can misrepresent potential profits to be gained by overrun and more than half (57
costs and benefits of a project in misrepresentation, providing a percent) of wind projects did.
order to motivate stakeholder perverse incentive for contractors However, the mean amounts of
involvement and then to game the system even if they are $1.3 million (solar) and $7.7
commitment (Sovacool and held accountable later (Flyvbjerg, million (wind) pale in
Cooper, 2013). Flyvbjerg has found 2006). The solution, for Flyvbjerg, relationship to the others. As
that large-scale energy and is to improve accountability. As he Table 1 summarizes, when
transport projects are consistently concludes, ‘‘the key principle is compared to other types of
approved on the basis of that the cost of making a wrong infrastructure, nuclear reactors,
underestimated costs, forecast should fall on those and hydroelectric dams stand in a
overestimated revenues, making the forecast, a class of their own concerning the
undervalued environmental principle often violated today’’ risk of a construction cost
impacts, and overvalued (Flyvbjerg, 2005). overrun.

118 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 The Electricity Journal
Author's personal copy

Table 1: Mean Cost Escalation for Various Infrastructure Projects. lisation of nuclear power. In: Byrne,
J., Hoffman, S.M. (Eds.), Governing
Technology Mean Cost Escalation (%) (n) for the Sample the Atom: The Politics of Risk.
Nuclear reactors 117 180 Transaction Publishers, London,
pp. 11–46.
Hydroelectric dams 71 61 Christiansson, L., December 1995. Dif-
Railway networks 45 58 fusion and Learning Curves of
Bridges and tunnels 34 33 Renewable Energy Technologies.
IIASA, Luxemburg WP-95-126.
Roads 20 167
Cohen, B.L., 1990. Costs of Nuclear
Mining projects 14 63 Power Plants: What Went Wrong?
Thermal power plants 13 36 Nuclear Energy Option. Plenum
Wind farms 8 35 Press, New York.
De Bondt, W.F.M., Makhija, A.K., 1988.
Transmission projects 8 50 Throwing good money after bad?
Solar farms 1 39 Nuclear power plant investment
Source: Data for electricity infrastructure comes from this study. Data for other items come from (Flyvbjerg et al., 2002, decisions and the relevance of sunk
2004). costs. J. Econ. Behav. Org. 10, 173–
199.
Findlay, T., 2010. The Future of Nuclear
Energy to 2030 and Its Implications
Appendices I and
I n sum, electricity for Safety, Security, and Nonproli-
feration. Center for International
infrastructure seems prone to II. Supplementary data Governance Innovation, Waterloo,
cost overrun issues independent, Ontario.
almost, of technology or location. Supplementary material related Flyvbjerg, B., 2005. Design by decep-
Each of these different types of to this article can be found, in the tion: the politics of megaproject
approval. Harvard Des. Mag.
electricity infrastructure poses online version, at http://dx.doi.
(Spring/Summer) 50–59.
different construction risks. The org/10.1016/j.tej.2014.03.015. Flyvbjerg, B., 2006. From nobel prize to
findings of this study do not bode project management: getting risks
References right. Project Manage. J. (August)
well for climate change mitigation 5–15.
efforts, given that two of the largest Ansar, A., Flyvbjerg, B., Budzier, A., Flyvbjerg, B., Holm, M.S., Buhl, S., 2002.
‘‘wedges’’ (Pacala and Socolow, Lunn, D., 2014. Should we build Underestimating costs in public
more large dams? The actual costs works projects: error or lie? J. Am.
2004) that we have to mitigate of mega-dam development. Energy Plan. Assoc. 68 (Summer (3)) 279–
emissions—hydroelectric dams Policy (forthcoming). 295.
and nuclear reactors—have the Bacon, R.W., Besant-Jones, J.E., 1998. Flyvbjerg, B., Bruzelius, N., Rothengat-
Estimating construction costs and ter, W., 2003. Megaprojects and Risk:
greatest amount and frequency of schedules. Energy Policy 26 (4) An Anatomy of Ambition. Cam-
cost overruns. Yet as systems get 317–333. bridge University Press, New York.
smaller in overall capacity Bacon, R.W., Besant-Jones, J.E., Heidar- Flyvbjerg, B., Holm, M.S., Buhl, S., 2004.
ian, J., August 1996. Estimating Con- What causes cost overrun in trans-
(moving to wind and solar) we see
struction Costs and Schedules port infrastructure projects? Trans-
generally higher per installed kW Experience with Power Generation port Rev. 24 (January (1)) 3–18.
costs but also less risk to overruns Projects in Developing Countries. Grubler, A., 2010. The costs of the
and lower rates of overruns that World Bank, Washington, DC. French nuclear scale-up: a case of
Bolinger, M., Wiser, R., 2009. Wind negative learning by doing. Energy
are less costly when they occur. power price trends in the United Policy 38, 5174–5188.
This may imply that utilities and States: struggling to remain compe- Grubler, A., October 2009. An Assess-
project sponsors face the dilemma titive in the face of strong growth. ment of the Costs of the French
Energy Policy 37 (March (3)) 1061– Nuclear PWR Program, 1970–2000.
of having to ‘‘pay’’ for risk 1071. International Institute for Applied
protection: you pay higher costs Bolinger, M., Wiser, R., 2012. Under- Systems Analysis, Vienna IR-09-376.
per kW to achieve more standing wind turbine price trends Hecht, G., 1998. The Radiance of France:
in the U.S. over the past decade. Nuclear Power and National Identity
predictable risks/investment
Energy Policy 42 (March) 628–641. After World War II. MIT Press.
ratios due to solar and wind’s Byrne, J., Hoffman, S.M., 1996. The Hultman, N.E., Koomey, J.G., Kam-
modularity. ideology of progress and the globa- men, D.M., 2007. What history can

May 2014, Vol. 27, Issue 4 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 119
Author's personal copy

teach us about the future costs of theory and new evidence. RAND J. Sovacool, B.K., 2010. Exploring the
U.S. nuclear power. Environ. Sci. Econ. 22 (Spring (I)) 148–154. hypothetical limits to a nuclear
Technol. 1 (April) . Merrow, E.W., Shangraw, R.F., July and renewable electricity future.
IHS Costs and Strategic Sourcing, 2014. 1990. Understanding the Costs and Int. J. Energy Res. 34 (November)
Power Capital Costs Index and Eur- Schedules of World Bank Supported 1183–1194.
opean Power Capital Costs Index., Hydroelectric Projects. World Bank Sovacool, B.K., Cooper, C.J., 2013. The
http://www.ihs.com/info/cera/ Energy Series Working Paper No. Governance of Energy Megapro-
ihsindexes/index.aspx (accessed 31, Washington, DC. jects: Politics, Hubris, and Energy
February 2014). Nemet, G.F., 2006. Beyond the learning Security. Edward Elgar, London.
Koomey, J., Hultman, N.E., 2007. A curve: factors influencing cost U.S. Energy Information Administra-
reactor-level analysis of busbar reductions in photovoltaics. Energy tion, 1986. An Analysis of Nuclear
costs for U.S. nuclear plants, Policy 34, 3218–3232. Power Plant Construction Costs.
1970–2005. Energy Policy 35, Nemet, G.F., 2009. Interim monitoring Office of Coal, Nuclear, Electric
5630–5642. of cost dynamics for publicly sup- and Alternate Fuels, U.S. Depart-
Levitt, A.C., Kempton, W., Smith, A.P., ported energy technologies. Energy ment of Energy DOE/EIA-0485,
Musial, W., Firestone, J., 2011. Pri- Policy 37, 825–835. Washington, DC.
cing offshore wind power. Energy Pacala, S., Socolow, R., 2004. Stabiliza- World Commission on Dams, Dams
Policy 39, 6408–6421. tion wedges: solving the climate and Development: A New Frame-
Lyon, T.P., Mayo, J.W., 2005. Regula- problem for the next 50 years with work for Decision-making (London:
tory opportunism and investment current technologies. Science 305 Earthscan, 2000).
behavior: evidence from the ILS. (August) 968–972. Zerger, B., Noël, M., 2011. Nuclear
Electric utility industry. RAND J. Severance, C.A., 2009. Business Risks power plant construction: what
Econ. 36 (Autumn (3)) 628–644. and Costs of New Nuclear Power. can be learned from past and on-
Marshall, J.M., Navarro, P., 1991. Costs Climate Progress, Washington, DC, going projects? Nucl. Eng. Des.
of nuclear power plant construction: pp. 13. 241 (August (8)) 2916–2926.

Conference Date Place Sponsor Contact


Energy Policy Institute Sept. 4–5, 2014 San Boise State epi.boisestate.edu/conference
Research Conference Francisco University

120 1040-6190/$–see front matter # 2014 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2014.03.015 The Electricity Journal

You might also like