ID Task Task Name Duration Start Finish Predecessors Resource Names

11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
0 Project 84 days? 30/3/18 25/7/18
Management for 8:00 AM 5:00 PM
1 MSInitiating
Website 7.5 days? 30/3/18 8:00 10/4/18
AM 12:00 PM

2 Develop Project 3.5 days? 30/3/18 4/4/18


Charter 8:00 AM 12:00 PM
3 Identify 1 day? 30/3/18 30/3/18 Project Director Project Director
Goals and 8:00 AM 5:00 PM
4 Objectives
Develop 1 day? 2/4/18 8:00 2/4/18 5:00 3 Project Director Project Director
Strategies AM PM
and Plans
5 Research 1 day? 3/4/18 8:00 3/4/18 5:00 4 Project Manager Project Manager
Previous AM PM
Experience
6 Develop 0.5 days? 4/4/18 8:00 4/4/18 5 Project Project Manager,Acceptor
Project AM 12:00 PM Manager,Acceptor
7 Charter
Develop 4 days? 4/4/18 1:00 10/4/18 2
Preliminary PM 12:00 PM
Project Scope
8 Statement
Conduct 1 day? 4/4/18 1:00 5/4/18 Project Director Project Director
Planning PM 12:00 PM
Workshop
9 Document 0.5 days? 5/4/18 1:00 5/4/18 5:00 8 Application Application Architect,Technical Architect,Project Manager
Project Costs PM PM Architect,Technical
and Benefits Architect,Project
10 Develop High 1 day? 6/4/18 8:00 6/4/18 5:00 9 Manager
Project Manager Project Manager
Level Work AM PM
Breakdown
Structure
11 Conduct Peer 1 day? 9/4/18 8:00 9/4/18 5:00 10 Project Manager Project Manager
Review AM PM
12 Prepare 0.5 days? 10/4/18 10/4/18 11 Project Project Manager,Acceptor
Preliminary 8:00 AM 12:00 PM Manager,Acceptor
Project Scope
Statement
13 Planning 27 days? 10/4/18 1:00 17/5/18
PM 12:001 PM

14 Set Up Project 4 days? 10/4/18 16/4/18


Environment 1:00 PM 12:00 PM
15 Prepare 1 day? 10/4/18 11/4/18 Project Manager Project Manager
Facilities 1:00 PM 12:00 PM
16 Set Up 1 day? 11/4/18 12/4/18 15 Quality Quality Assurance Manager
Project 1:00 PM 12:00 PM Assurance
Standards Manager
and

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
17 Set Up 1 day? 12/4/18 13/4/18 16 Project Manager Project Manager
Project 1:00 PM 12:00 PM
Management
18 Tools
Set Up 1 day? 13/4/18 16/4/18 17 Project Manager Project Manager
Project Book 1:00 PM 12:00 PM
19 Define Scope 4 days? 16/4/18 1:00 20/4/18
PM 12:0014PM

20 Document 1 day? 16/4/18 17/4/18 Project Manager Project Manager


Scope 1:00 PM 12:00 PM
Management
21 Plan
Specify 1 day? 17/4/18 18/4/18 20 Project Manager Project Manager
Deliverables 1:00 PM 12:00 PM
and
Acceptance
22 CriteriaScope 1 day?
Define 18/4/18 1:00 19/4/18
PM 12:0021PM Project Manager Project Manager

23 Document 1 day? 19/4/18 20/4/18 22 Project Manager Project Manager


Assumptions 1:00 PM 12:00 PM
24 Develop Project 5 days? 20/4/18 27/4/18 19
Schedule 1:00 PM 12:00 PM
25 Build Work 1 day? 20/4/18 23/4/18 Project Manager Project Manager
Breakdown 1:00 PM 12:00 PM
Structure
26 Develop 1 day? 23/4/18 24/4/18 25 Project Manager Project Manager
Resource 1:00 PM 12:00 PM
27 Plans
Prepare 1 day? 24/4/18 25/4/18 26 Project Manager Project Manager
Project 1:00 PM 12:00 PM
28 Estimates
Define 1 day? 25/4/18 26/4/18 27 Project Manager Project Manager
Dependencies 1:00 PM 12:00 PM
and Develop
Project
29 Schedule
Document 1 day? 26/4/18 27/4/18 28 Project Manager Project Manager
Assumptions 1:00 PM 12:00 PM
30 Develop Risk Plans
3 days? 27/4/18 1:00 2/5/18
PM 12:00 24
PM

31 Document 0.5 days? 27/4/18 27/4/18 Project Project Manager,Acceptor


Risk 1:00 PM 5:00 PM Manager,Acceptor
Management
32 Plan
Identify Risks 1 day? 30/4/18 8:00 30/4/18
AM 5:00 31
PM Project Manager Project Manager

33 Analyze Risks 1 day? 1/5/18 8:00 AM


1/5/18 5:00 PM
32 Project Manager Project Manager

34 Document 0.5 days? 2/5/18 8:00 2/5/18 33 Project Project Manager,Acceptor


Risk AM 12:00 PM Manager,Acceptor
Management
Plans

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
35 Plan for Quality 0.5 days? 2/5/18 1:00 PM
2/5/18 5:00 PM
30

36 Document 0.5 days? 2/5/18 1:00 2/5/18 5:00 Quality Quality Assurance Manager,Acceptor
Quality PM PM Assurance
Management Manager,Acceptor
Plan
37 Organize 2 days? 3/5/18 8:00 4/5/18 5:00 35
Project AM PM
38 Resources
Develop 1 day? 3/5/18 8:00 3/5/18 5:00 Project Director Project Director
Organization AM PM
Structure
39 Develop 1 day? 4/5/18 8:00 4/5/18 5:00 38 Project Director Project Director
Staffing Plan AM PM
40 Develop 4.5 days? 7/5/18 8:00 11/5/18 37
Procurement AM 12:00 PM
41 Plans
Determine 1 day? 7/5/18 8:00 7/5/18 5:00 Contracts Contracts Manager
Procurement AM PM Manager
Requirements
42 Define 1 day? 8/5/18 8:00 8/5/18 5:00 41 Contracts Contracts Manager
Subcontractor AM PM Manager
Scope
43 Identify 1 day? 9/5/18 8:00 9/5/18 5:00 42 Contracts Contracts Manager
Potential AM PM Manager
Subcontractors
44 Identify 1 day? 10/5/18 10/5/18 43 Contracts Contracts Manager
Subcontract 8:00 AM 5:00 PM Manager
Type
45 Document 0.5 days? 11/5/18 11/5/18 44 Contracts Contracts Manager,Acceptor
Subcontractor 8:00 AM 12:00 PM Manager,Acceptor
Management
Plan
46 Develop 2 days? 11/5/18 15/5/18 40
Financial Plan 1:00 PM 12:00 PM
47 Prepare 1 day? 11/5/18 14/5/18 Project Manager Project Manager
Financial Plan 1:00 PM 12:00 PM
48 Document 1 day? 14/5/18 15/5/18 47 Project Manager Project Manager
Assumptions 1:00 PM 12:00 PM
49 Develop Project 1.5 days? 15/5/18 16/5/18 46
Support Plans 1:00 PM 5:00 PM
50 Document 0.5 days? 15/5/18 15/5/18 Project Project Manager,Acceptor
Communications 1:00 PM 5:00 PM Manager,Acceptor
Management
Plan

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
51 Document 0.5 days? 16/5/18 16/5/18 50 Project Project Manager,Acceptor
Configuration 8:00 AM 12:00 PM Manager,Acceptor
Management
Plan
52 Document 0.5 days? 16/5/18 16/5/18 51 Project Project Manager,Acceptor
Data 1:00 PM 5:00 PM Manager,Acceptor
Management
53 Plan Project 0.5 days?
Develop 17/5/18 17/5/18 49
Management 8:00 AM 12:00 PM
54 Plan
Document 0.5 days? 17/5/18 17/5/18 Project Project Manager,Acceptor
Project 8:00 AM 12:00 PM Manager,Acceptor
Management
Plan
55 Executing 18 days? 17/5/18 1:00 12/6/18
PM 12:0013PM

56 Acquire Project 3 days? 17/5/18 22/5/18


Team 1:00 PM 12:00 PM
57 Obtain 1 day? 17/5/18 18/5/18 Project Director Project Director
Resources 1:00 PM 12:00 PM
58 Conduct 1 day? 18/5/18 21/5/18 57 Project Director Project Director
Team 1:00 PM 12:00 PM
59 Orientation
Assign 1 day? 21/5/18 22/5/18 58 Project Manager Project Manager
Responsibilities 1:00 PM 12:00 PM
60 Direct and 5 days? 22/5/18 29/5/18 56
Manage Project 1:00 PM 12:00 PM
61 Execution
Manage Data 1 day? 22/5/18 23/5/18 Project Manager Project Manager
Items 1:00 PM 12:00 PM
62 Manage 1 day? 23/5/18 24/5/18 61 Project Manager Project Manager
Configuration 1:00 PM 12:00 PM
Items
63 Manage 1 day? 24/5/18 25/5/18 62 Project Manager Project Manager
Process Data 1:00 PM 12:00 PM
64 Provide 1 day? 25/5/18 28/5/18 63 Project Manager Project Manager
General 1:00 PM 12:00 PM
65 Office
Administer 1 day? 28/5/18 29/5/18 64 Project Manager Project Manager
Project 1:00 PM 12:00 PM
Security
66 Processes
Manage Team 2 days? 29/5/18 31/5/18 60
Performance 1:00 PM 12:00 PM
67 Provide 1 day? 29/5/18 30/5/18 Project Manager Project Manager
Team 1:00 PM 12:00 PM
68 Training
Recognize 1 day? 30/5/18 31/5/18 67 Project Director Project Director
Success 1:00 PM 12:00 PM
69 Assure Quality 4 days? 31/5/18 1:00 6/6/18
PM 12:00 66
PM

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
70 Participate in 1 day? 31/5/18 1/6/18 Quality Quality Assurance Manager
Walk-throughs 1:00 PM 12:00 PM Assurance
and Reviews Manager
71 Conduct 1 day? 1/6/18 1:00 4/6/18 70 Quality Quality Assurance Manager
Inspections PM 12:00 PM Assurance
and Audits Manager
72 Conduct 1 day? 4/6/18 1:00 5/6/18 71 Quality Quality Assurance Manager
Project PM 12:00 PM Assurance
73 Reviews
Facilitate 1 day? 5/6/18 1:00 6/6/18 72 Manager
Quality Quality Assurance Manager
Continuous PM 12:00 PM Assurance
Improvement Manager
74 Manage Project 1 day? 6/6/18 1:00 7/6/18 69
Communication PM 12:00 PM
75 Review Progress1 day? 6/6/18 1:00 PM
7/6/18 12:00 PM Project Director Project Director

76 Contracting 3 days? 7/6/18 1:00 12/6/18 74


with PM 12:00 PM
77 Subcontractors
Issue 1 day? 7/6/18 1:00 8/6/18 Contracts Contracts Manager
Requisition PM 12:00 PM Manager
Documents
78 Evaluate 1 day? 8/6/18 1:00 11/6/18 77 Contracts Contracts Manager
Responses PM 12:00 PM Manager
79 Negotiate 1 day? 11/6/18 12/6/18 78 Contracts Contracts Manager
Subcontractor 1:00 PM 12:00 PM Manager
Contract
80 Monitoring and 25.5 days? 12/6/18 17/7/18 55
Controlling 1:00 PM 5:00 PM
81 Monitor and 3 days? 12/6/18 15/6/18
Control Project 1:00 PM 12:00 PM
Work
82 Authorize Work1 day? 12/6/18 1:00 13/6/18
PM 12:00 PM Project Manager Project Manager

83 Manage 1 day? 13/6/18 14/6/18 82 Project Manager Project Manager


Action Items 1:00 PM 12:00 PM
84 Manage 1 day? 14/6/18 15/6/18 83 Project Manager Project Manager
Project 1:00 PM 12:00 PM
85 Records
Integrated 4 days? 15/6/18 21/6/18 81
Change Control 1:00 PM 12:00 PM
86 Manage Scope1 day? 15/6/18 1:00 18/6/18
PM 12:00 PM Project Manager Project Manager

87 Manage 1 day? 18/6/18 19/6/18 86 Project Manager Project Manager


Requirements 1:00 PM 12:00 PM
88 Control 1 day? 19/6/18 20/6/18 87 Project Manager Project Manager
Decisions 1:00 PM 12:00 PM
89 Control Changes
1 day? 20/6/18 1:00 21/6/18
PM 12:0088PM Project Manager Project Manager

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
90 Scope Verification
0.5 days? 21/6/18 1:00 21/6/18
PM 5:00 85
PM

91 Manage 0.5 days? 21/6/18 21/6/18 Project Project Manager,Acceptor


Project 1:00 PM 5:00 PM Manager,Acceptor
92 Acceptance
Schedule Control3 days? 22/6/18 8:00 26/6/18
AM 5:00 90
PM

93 Track Status 1 day? 22/6/18 8:00 22/6/18


AM 5:00 PM Project Manager Project Manager

94 Maintain 1 day? 25/6/18 25/6/18 93 Project Manager Project Manager


Project 8:00 AM 5:00 PM
95 Schedule
Maintain 1 day? 26/6/18 26/6/18 94 Project Manager Project Manager
Work Plans 8:00 AM 5:00 PM
96 Manage Finances3 days? 27/6/18 8:00 29/6/18
AM 5:00 92
PM

97 Monitor 1 day? 27/6/18 27/6/18 Project Manager Project Manager


Cost/Schedule 8:00 AM 5:00 PM
Variance
98 Control Costs 1 day? 28/6/18 8:00 28/6/18
AM 5:00 97
PM Project Director Project Director

99 Maintain 1 day? 29/6/18 29/6/18 98 Project Director Project Director


Financial Plan 8:00 AM 5:00 PM
100 Perform 3 days? 2/7/18 8:00 4/7/18 5:00 96
Quality Control AM PM
101 Control Quality1 day? 2/7/18 8:00 AM
2/7/18 5:00 PM Quality Assurance Manager Quality Assurance Manager

102 Participate in 1 day? 3/7/18 8:00 3/7/18 5:00 101 Quality Quality Assurance Manager
Testing AM PM Assurance
103 Measure 1 day? 4/7/18 8:00 4/7/18 5:00 102 Manager
Quality Quality Assurance Manager
Quality AM PM Assurance
104 Levels Project 4 days?
Manage 5/7/18 8:00 10/7/18 100 Manager
Team AM 5:00 PM
105 Manage 1 day? 5/7/18 8:00 5/7/18 5:00 Project Manager Project Manager
Communications AM PM
106 Meet With Team 1 day? 6/7/18 8:00 AM
6/7/18 5:00 PM
105 Project Manager Project Manager

107 Monitor 1 day? 9/7/18 8:00 9/7/18 5:00 106 Project Manager Project Manager
Team Morale AM PM
108 Conduct 1 day? 10/7/18 10/7/18 107 Project Manager Project Manager
Team 8:00 AM 5:00 PM
Performance
109 Reviews
Produce 1 day? 11/7/18 11/7/18 104
Performance 8:00 AM 5:00 PM
Reports
110 Report 0.5 days? 11/7/18 11/7/18 Project Project Manager,Acceptor
Weekly 8:00 AM 12:00 PM Manager,Acceptor
Status

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 6
ID Task Task Name Duration Start Finish Predecessors Resource Names
11 Mar '18 25 Mar '18 8 Apr '18 22 Apr '18 6 May '18 20 May '18 3 Jun '18 17 Jun '18 1 Jul '18 15 Jul '18 29 Jul '18 12 Aug '18
Mode S F W M S T T S F W M S T T S F W M S T T S F W M S T T S F W
111 Report 0.5 days? 11/7/18 11/7/18 110 Project Project Manager,Acceptor
Monthly 1:00 PM 5:00 PM Manager,Acceptor
112 Status
Manage 2 days? 12/7/18 13/7/18 109
Stakeholders 8:00 AM 5:00 PM
113 Monitor 1 day? 12/7/18 12/7/18 Project Director Project Director
Satisfaction 8:00 AM 5:00 PM
114 Resolve Issues1 day? 13/7/18 8:00 13/7/18
AM 5:00 113
PM Project Director Project Director

115 Risk Monitoring 1 day? 16/7/18 16/7/18 112


and Control 8:00 AM 5:00 PM
116 Manage Risks 1 day? 16/7/18 8:00 16/7/18
AM 5:00 PM Project Manager Project Manager

117 Contract 1 day? 17/7/18 17/7/18 115


Administration 8:00 AM 5:00 PM
118 Manage 1 day? 17/7/18 17/7/18 Contracts Contracts Manager
Subcontractor 8:00 AM 5:00 PM Manager
Contract
119 Closing 6 days? 18/7/18 8:00 25/7/18
AM 5:00 80
PM

120 Close Project 5 days? 18/7/18 8:00 24/7/18


AM 5:00 PM

121 Assess 1 day? 18/7/18 18/7/18 Project Manager Project Manager


Satisfaction 8:00 AM 5:00 PM
122 Summarize 1 day? 19/7/18 19/7/18 121 Project Manager Project Manager
Project 8:00 AM 5:00 PM
Results and
Lessons
123 Learnedand 1 day?
Review 20/7/18 20/7/18 122 Project Manager Project Manager
Recognize 8:00 AM 5:00 PM
Team
124 Performance
Close Out the 1 day? 23/7/18 23/7/18 123 Project Manager Project Manager
Project 8:00 AM 5:00 PM
125 Recordsand 1 day?
Review 24/7/18 24/7/18 124 Project Manager Project Manager
Reconcile 8:00 AM 5:00 PM
Financial
Performance
126 Contract Closure1 day? 25/7/18 8:00 25/7/18
AM 5:00 120
PM

127 Close Contract1 day? 25/7/18 8:00 25/7/18


AM 5:00 PM Contracts Manager Contracts Manager

Task Project Summary Manual Task Start-only Deadline

Project: Project Management fo Split Inactive Task Duration-only Finish-only Progress


Date: 30/3/18 4:34 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 7