Professional Documents
Culture Documents
P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 1 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
1
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 2 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
CONTENTS
1. SCOPE
2. DEFINITIONS
3. APPARATUS IDENTIFICATION
4. DANGERS
2
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 3 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
1. SCOPE
2. DEFINITIONS
3. APPARATUS IDENTIFICATION
4. DANGERS
The requirements detailed below must be met with regard to the earthing
of High Voltage Apparatus.
Primary Earths must be applied within the Isolated zone and, where
reasonably practicable, be positioned between the point of work and all
point(s) of isolation excluding Low Voltage (LV) connections but
including,
3
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 4 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
When compliance with the above requirements does not give adequate
protection from induced voltages, Drain Earths must be applied in
accordance with an Earthing Schedule.
The application and removal of fixed Primary Earths including the closing
and opening of earth switches and fixed Earthing Devices when used as
Primary Earths must be carried out by the Designated Person or
Safety Controller who has received instruction from the Safety
Controller or in the case of a Person under training, carried out in
accordance with the requirements of procedure no. TgBin-TTB-SH-78012 -
High Voltage Switching. Under the terms of a Permit Test, however, the
recipient of the Permit (Test) may remove or replace those Primary
Earths defined on the Permit (Test) without reference to the Safety
Controller.
4
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 5 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
5
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 6 of 6
Earthing High Voltage Apparatus
Issue Date February 10, 2016
apply. The purpose of this clause is to avoid the necessity of requiring that
a Drain Earth be applied to Apparatus on one side of a wall, e.g. when
the Apparatus has a Primary Earth connected to it on the other side of
the wall and there cannot be any possibility of error or identification or of
Danger from induction.
Drain Earths issued with a Permit (Test) must be applied and removed
in accordance with the requirements of the Earthing Schedule by a
Designated Person or a Person under the Personal Supervision of a
Designated Person.
When either the Primary Earths or Drain Earths would prevent access
to the points of work, the HV Apparatus on which work is to be done must
be efficiently connected to earth at the nearest points to the points of work
and these Drain Earths may be removed in turn when work is to be done
but each earth so removed shall be replaced before another earth is
removed.
When HV Apparatus has been disconnected from all supplies and bodily
removed from its service position, the use of Primary Earths on that HV
Apparatus is not necessary, provided that the HV Apparatus is
electrically discharged.
When Drain Earths are required for work on overhead lines they must be
issued and applied in accordance with the Local Grid Control, if they do not
exist, the Site Manager should produce a Local Safety Instruction to cover
this Safety Instruction for High Voltage Overhead Lines.