Owner’s
PT.PLN(PERSERRO) DWG No.
0702-00-E-01-CH-001
PT REKADAYA PT.PLN(PERSERRO)
ELEKTRIKA JAVA MANAJEMEN KONSTRUKSI
CONSORTIUM OF
DONGFANG ELECTRIC CORPORATION AND DALLE ENERGY
DETAIL
SiChuan Electric Power Commissioning & PLTU 1 Jatim-Pacitan (2×315MW) DESIGN STAGE
Test Institute Project
Table of Contents
1. PURPOSE.......................................................................................................................................... 3
2. SCOPE............................................................................................................................................... 3
3. PREPARATION BASIS................................................................................................................... 3
4. BRIEF INTRODUCTION OF SYSTEM AND EQUIPMENT....................................................... 3
5. TOOLS AND INSTRUMENTS FOR COMMISSIONING............................................................ 3
6. PREREQUISITE FOR COMMISSIONING................................................................................... 3
7. MEASURES FOR COMMISSIONING ORGANIZATION............................................................ 3
8. COMMISSIONING PROCEDURE................................................................................................. 5
8.1 ction System........................................................................................................................ 5
8.2 Circuit Check of the Protection System of Generator-transformer Unit........................... 5
9. SAFETY MEASURES................................................................................................................... 5
10. APPENDIX...................................................................................................................................... 6
10.1 Appendix 1 Commissioning Condition Checklist............................................................ 6
10.2 Appendix 2 Logic Test Record Form................................................................................... 6
PLTU 1 Jatim-Pacitan(2×315MW) Project
Procedure of Generator and Transformer Protection System REV A
Commissioning
Procedure
SCCTI-TS-DQ-CS-003-2009A Page 3 of 8
1. Purpose
The protective relay device of electric system is the most basic, important and efficient
technical measure for guaranteeing the safety of electric equipment. This procedure is
prepared in order to ensure the safe, reliable and successful operation of unit so as to monitor
the quality of the whole commissioning process of generator-transformer unit protection
system. The protection system after commissioned will provide reliable protection for the unit
operation to ensure the safe operation of unit.
2. Scope
This procedure is applied to the commissioning of generator-transformer unit protection.
3. Preparation Basis
3.1 The instruction manual of protection system
3.2 The drawing of design institute
8. Commissioning Procedure
8.1 ction System
8.1.1 Appearance inspection of each protection system.
8.1.2 Routine insulation inspection of each protection system: check the insulation of power supply
circuit and all the secondary circuits by 500V megger and make voltage withstand test on the
secondary circuit by 1000V megger.
8.1.3 After the protection system self-checks that the device is powered, (the self-check should be
normal without self-check warning signal) check the device software, it should operate
normally and reliably, and all the indications and device indicator lamp should be normal.
Check the device functions like, protection configuration, definite value setting, output drive,
clock modification and print and so on.
8.1.4 Analog input channel check of the protection system: apply analog, check all the current and
voltage channels of the device; the sampled amplitude, phase and frequency precision should
meet the requirement.
8.1.5 Switching value check of each protection system: check and compare the switching value
input channels of the protection system with the design and they should be correct. Simulate
shorting switching value input in local mode; the switching value input indication of the
protection system is correct.
8.1.6 Warning and trip output check of the protection system
Check the switching value output channel of the protection system according to the design
drawing and test each warning and trip output. The result should be correct.
8.1.7 Protection logic and movement characteristic check of the protection system.
9. Safety Measures
9.1 Obvious mark for electric shock and warning sign should be provided around the protection
system under test.
9.2 The test power supply should be from the test power supply cabinet to meet the requirement.
The test power supply must be connected as required.
9.3 The operation during the test must be done by at least two people, and the work must be
stopped if any abnormal situation is found and will be resumed after found that the abnormal
situation is not related to the work.
9.4 The secondary circuit insulation is tested as qualified. Take out the protection card during
insulation check to avoid damaging the protection chip.
PLTU 1 Jatim-Pacitan(2×315MW) Project
Procedure of Generator and Transformer Protection System REV A
Commissioning
Procedure
SCCTI-TS-DQ-CS-003-2009A Page 6 of 8
9.5 Cut off power when taking out or plugging in card. It’s not allowed to take out or plug in card
with power on.
9.6 Obvious isolation measure should be taken for the operating equipment. It’s not allowed to
have accidental touch on the operating equipment.
9.7 Before the protection system is powered for commissioning, check the correctness of the
device connection and check and ensure that the secondary circuit is connected well and
reliably and each element of card board is welded firmly.
9.8 Check and ensure that the factory acceptance certificate, factory test report, factory
commissioning outline, contract number and the factory test data are correct.
9.9 The grounding of the test equipment and the protection system should meet the requirement.
10. Appendix
10.1 Appendix 1 Commissioning Condition Checklist
No. Inspection Item Requirement Result Remark
Device and device The installation of device is
1 connection finished and all the cables are □Yes □No
finished for pulling and connection
2 Device power Ready for operation □Yes □No
supply
3 Drawing document The drawing document is complete □Yes □No
and correct
Commissioning Familiar with the device, principle
4 personnel and commissioning method and □Yes □No
step.
5 Test equipment The relative test instrument and □Yes □No
equipment are prepared.