You are on page 1of 4

Project:

ETAP Page: 7
12.6.0H
Location: Date: 28-11-2017
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: DanielTER_Rev2 Config.: Normal

SHORT- CIRCUIT REPORT

Fault at bus: F1_Dohaibah Bus

Prefault voltage = 33.000 kV = 100.00 % of nominal bus kV ( 33.000 kV)


= 100.00 % of base kV ( 33.000 kV)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

F1_Dohaibah Bus Total 0.00 4.650 0.00 129.18 124.20 2.682 2.682 1.07E+001 3.61E+001 2.24E+001 1.19E+002

F3_Al Matrouk-Dohaiba F1_Dohaibah Bus 73.73 1.189 72.02 108.76 105.04 0.706 0.747 4.44E+001 1.40E+002 8.95E+001 4.24E+002
OHL
F2_Samirah - Dohaiba F1_Dohaibah Bus 59.56 2.121 56.83 113.47 108.84 1.243 1.282 2.19E+001 7.95E+001 4.59E+001 2.48E+002
OHL
Bus4 F1_Dohaibah Bus 68.13 1.340 66.49 109.46 106.96 0.733 0.654 3.91E+001 1.25E+002 8.29E+001 4.88E+002

Al Matrouk F3_Al 100.00 1.189 100.00 100.00 100.00 0.706 0.747 3.23E+000 3.99E+001 9.19E+000 1.27E+002
Matrouk-Dohaiba OHL
Samirah F2_Samirah - Dohaiba 100.00 2.121 100.00 100.00 100.00 1.243 1.282 3.27E+000 3.41E+001 9.53E+000 1.14E+002
OHL
Wassiyah Bus4 100.00 1.340 100.00 100.00 100.00 0.733 0.654 4.52E+000 4.26E+001 1.60E+001 1.70E+002

# Indicates fault current contribution is from three-winding transformers

* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 8
12.6.0H
Location: Date: 28-11-2017
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: DanielTER_Rev2 Config.: Normal

Fault at bus: F2_Samirah - Dohaiba OHL

Prefault voltage = 33.000 kV = 100.00 % of nominal bus kV ( 33.000 kV)


= 100.00 % of base kV ( 33.000 kV)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

F2_Samirah - Dohaiba Total 0.00 6.558 0.00 128.02 126.32 3.731 3.731 4.00E+000 2.64E+001 1.00E+001 8.68E+001
OHL

F1_Dohaibah Bus F2_Samirah - Dohaiba 41.56 1.480 39.14 117.38 115.20 0.854 0.880 3.94E+001 1.11E+002 7.99E+001 3.62E+002
OHL
Samirah F2_Samirah - Dohaiba 100.00 5.112 100.00 100.00 100.00 2.891 2.857 3.27E+000 3.41E+001 9.53E+000 1.14E+002
OHL

F3_Al Matrouk-Dohaiba F1_Dohaibah Bus 84.71 0.696 83.01 105.44 103.31 0.420 0.469 4.44E+001 1.40E+002 8.95E+001 4.24E+002
OHL
Bus4 F1_Dohaibah Bus 81.43 0.784 79.67 105.83 104.55 0.434 0.411 3.91E+001 1.25E+002 8.29E+001 4.88E+002

# Indicates fault current contribution is from three-winding transformers

* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 9
12.6.0H
Location: Date: 28-11-2017
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: DanielTER_Rev2 Config.: Normal

Fault at bus: F3_Al Matrouk-Dohaiba OHL

Prefault voltage = 33.000 kV = 100.00 % of nominal bus kV ( 33.000 kV)


= 100.00 % of base kV ( 33.000 kV)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

F3_Al Matrouk-Dohaiba Total 0.00 5.438 0.00 126.68 125.23 3.184 3.184 4.36E+000 3.19E+001 1.07E+001 9.99E+001
OHL

F1_Dohaibah Bus F3_Al 68.30 1.101 66.20 109.30 107.55 0.654 0.674 5.53E+001 1.49E+002 1.10E+002 4.62E+002
Matrouk-Dohaiba OHL
Al Matrouk F3_Al 100.00 4.370 100.00 100.00 100.00 2.545 2.517 3.23E+000 3.99E+001 9.19E+000 1.27E+002
Matrouk-Dohaiba OHL

F2_Samirah - Dohaiba F1_Dohaibah Bus 87.25 0.675 85.46 104.57 102.86 0.412 0.446 2.19E+001 7.95E+001 4.59E+001 2.48E+002
OHL
Bus4 F1_Dohaibah Bus 89.98 0.427 88.74 103.23 102.34 0.242 0.228 3.91E+001 1.25E+002 8.29E+001 4.88E+002

# Indicates fault current contribution is from three-winding transformers

* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 10
12.6.0H
Location: Date: 28-11-2017
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: DanielTER_Rev2 Config.: Normal

Short-Circuit Summary Report

1/2 Cycle - 3-Phase, LG, LL, & LLG Fault Currents

Prefault Voltage = 100 % of the Bus Nominal Voltage

Bus 3-Phase Fault Line-to-Ground Fault Line-to-Line Fault *Line-to-Line-to-Ground


ID kV Real Imag. Mag. Real Imag. Mag. Real Imag. Mag. Real Imag. Mag.

F1_Dohaibah Bus 33.00 1.324 -4.457 4.650 0.600 -2.614 2.682 3.860 1.147 4.027 3.673 2.069 4.216

F2_Samirah - Dohaiba OHL 33.00 0.982 -6.484 6.558 0.478 -3.700 3.731 5.615 0.851 5.679 5.459 2.145 5.866

F3_Al Matrouk-Dohaiba OHL 33.00 0.736 -5.388 5.438 0.374 -3.162 3.184 4.666 0.638 4.710 4.542 1.756 4.870

All fault currents are symmetrical momentary (1/2 Cycle network) values in rms kA

* LLG fault current is the larger of the two faulted line currents