ID % Notes Task Name Duration Start 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec

Duration Start 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec 29, '13 Jan 5, '14 Jan 12, '14 Jan 19, '14 Jan 26, '14 Feb 2, '14
Complete M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1
2
3 2% ROMPORTMET 61 days? Tue 12/3/13 2%
4 0% Proiectare 20 days? Tue 12/3/13 0%
5 0% Mecanic 5 days Tue 12/3/13 0%
6 0% Constructii 5 days Mon 12/9/13 0%
7 0% Electric 1 day? Mon 12/16/13 0%
8 0% Predare beneficiar 1 day? Sun 12/22/13 0%
9
10 3% Separator hidrocarburi 27 days? Mon 1/6/14 3%
11 100% Realizare proiect electric 1 day? Mon 1/6/14 100%
12 0% Aprovizionare echipamente electrice conform proiect 10 days Mon 1/20/14 0%
13 0% Realizare dulap electric 3 days Thu 1/30/14 0%
14 0% Realizare softuer de aplicatii 10 days Mon 1/20/14 0%
15 0% Reamenajare decantor subteran existent 1 day? Mon 1/6/14 0%
16 0% Lucrari de constructie 1 day? Mon 1/6/14 0%
17 0% Lucrari de instalatii 1 day? Mon 1/6/14 0%
18 0% Reabilitarea tehnologica a decantorului existent 1 day? Mon 1/6/14 0%
19 0% Lucrari de montaj instalatii de conducte 1 day? Mon 1/6/14 0%
20 0% Lucrari de montaj echipamente 1 day? Mon 1/6/14 0%
21 0% Lucrari de alimentare cu energie electrica 1 day? Mon 1/6/14 0%
22 0% Lucrari de verificare, de probe tehnologice si PIF 1 day? Mon 1/6/14 0%
23
24
25 0% 1 day? Mon 1/6/14 0%
26 0% Constructii- Camin nou preluare ape meteorice si ape tratate din IFS 1 day? Mon 1/6/14 0%
27 0% Realizare camin nou subteran de colectare ape meteorice si de la 1 day? Mon 1/6/14 0%
Instalatia finala de separare filtrare ape uzate contaminate cu
hidrocarburi provenite de la spalatoria auto.
28 0% Lucrari de sapatura si terasamente 1 day? Mon 1/6/14 0%
29 0% Lucrari de montaj camin prefabricat tipizat 1 day? Mon 1/6/14 0%
30 0% Lucrari de montaj instalatii de conducte pt transvazare ape pluviale si 1 day? Mon 1/6/14 0%
de la IFS la canalizarea uzinala de dupa statia de epurare biologica
31 0% Lucrari de montaj echipamente noi 1 day? Mon 1/6/14 0%
32 0% Lucrari de montaj 1 day? Mon 1/6/14 0%
33
34
35
36 0% Statie de epurare biologica 1 day? Mon 1/6/14 0%
37 0% Constructie bazin subteran suplimentar bicompartimentat cu dimensiuni
1 day? interioare
Mon 1/6/14
4.00x3.00m 0%
38 0% Lucrari de sapatura si terasamente 1 day? Mon 1/6/14 0%
39 0% Lucrari de montaj camin prefabricat tipizat 1 day? Mon 1/6/14 0%
40 0% Lucrari de instalatii bazin subteran bicompartimentat nou 1 day? Mon 1/6/14 0%
41 0% Lucrari pentru reconfigurarea compartimentelor statiei actuale de 1 day? Mon 1/6/14 0%
epurare biologica
42 0% Lucrari de constructii 1 day? Mon 1/6/14 0%
43 0% Lucrari de instalatii 1 day? Mon 1/6/14 0%
44 0% Lucrari instalatii hidromecanice 1 day? Mon 1/6/14 0%
45 0% Lucrari de montaj instalatii de conducte pt transvazarea apelor si a 1 day? Mon 1/6/14 0%
namolului intre compartimente
46 0% Lucrari de montaj echipamente 1 day? Mon 1/6/14 0%
47 0% Lucrari de alimentare cu energie electrica 1 day? Mon 1/6/14 0%
48 0% Lucrari de verificare, de probe tehnologice si PIF 1 day? Mon 1/6/14 0%
49
50 0% Modul de epurare biologica 1 day? Mon 1/6/14 0%
51 0% Constructie bazin subteran suplimentar bicompartimentat cu 1 day? Mon 1/6/14 0%
dimensiuni interioare 4.00x3.00m
52 0% Lucrari de sapatura si terasamente 1 day? Mon 1/6/14 0%
53 0% Lucrari de montaj camin prefabricat tipizat 1 day? Mon 1/6/14 0%
54 0% Lucrari de instalatii bazin subteran bicompartimentat nou 1 day? Mon 1/6/14 0%
55 0% Lucrari pentru reconfigurarea compartimentelor modul actual de epurare biologica 1 day? Mon 1/6/14 0%
56 0% Lucrari instalatii hidromecanice 1 day? Mon 1/6/14 0%
57 0% Lucrari de montaj echipamente 1 day? Mon 1/6/14 0%
58 0% Lucrari de alimentare cu energie electrica 1 day? Mon 1/6/14 0%
59 0% Lucrari de verificare, de probe tehnologice si PIF 1 day? Mon 1/6/14 0%

Critical Task Baseline Milestone Project Summary Task Baseline Milestone


Project: SKAKO Planning Schedule_e Critical Split Split Baseline Split Summary Progress Critical Split Split Baseline Split Summary Progress
Date: Wed 1/22/14
Critical Progress Task Progress Baseline Milestone Summary Critical Progress Task Progress Baseline Milestone Summary