You are on page 1of 8

SN Description No.

Length(ft) Breadth(ft) Height(ft) Quantity


1 Earthwork
1.1 Excavation
1.1.1 Footing F1 7 5 5 5.5 962.5
1.1.2 Footing F2 3 6 6 5.5 594
1.1.3 Footing F3 2 7 7 5.5 539
2095.5
1.2 For tie beam wall 1 101.923 2 3.5 713.46

1.3 Toe Wall 1 12.33 2 1.67 41.8


Total 2850.76

2 Layer Brick soling


2.1 Below Footing
F1 7 5 5 175
F2 3 6 6 108
F3 2 7 7 98
381
2.2 Below tie beam wall 1 101.923 2 203.85
2.3 Toe wall 1 12.33 2 24.66
609.51
3 75 mm thick PCC(1:3:6)
3.1 Below Footing
F1 7 5 5 0.34 59.5
F2 3 6 6 0.34 36.72
F3 2 7 7 0.34 33.32
129.54
3.2 Tie beam wall 1 101.923 2 0.34 69.31
3.3 Toe wall 1 12.33 2 0.34 8.38
207.23
4 RCC work
4.1 Footing
F1 7 5 5 0.83 145.25
F2 3 6 6 1 108
F3 2 7 7 1.16 113.68
Total 366.93
4.2 Column
4.2.1 Below plinth beam
column isolate 12 1 1 4.5 54
4.2.2 Ground floor
column 12 1 1 8.92 107.04
4.2.3 First Floor 12 1 1 8.92 107.04
4.2.4 Top Floor 11 1 1 8.92 98.12
Total 366.2
4.3 Slabs
4.3.1 First Floor Slab
Total area 1 1080.276 0.42 453.72
Deduction fo staiarcase -1 72.67 0.42 -30.5
423.21
4.3.2 Second Floor slab
Total area 1 1080.276 0.42 453.72
Deduction for staircase -1 72.67 0.42 -30.5
423.21
4.3.3 Top Floor slab
total area 1 952.504 0.42 400.5

Total slab concreting 1246.83

4.4 Beam
4.4.1 Tie beam 2 186.843 0.75 1 280.26
4.4.2 toe wall 1 12.33 0.75 0.75 6.94
4.4.3 First Floor beam 1 203.679 0.75 1 152.759
4.4.4 Second Foor beam 1 203.679 0.75 1 152.759
4.4.5 Top floor beam 1 178.756 0.75 1 134.067
Total beam Concreting 726.785

4.5 Staircase
4.5.1 Ground floor to First floor
Landing 2 12.118 0.42 10.18
Inclined 1 16.249 3.5 0.42 23.89
Steps 16 0.8333 3.5 0.5833 27.22
61.29
4.5.2 First Floor to Second floor
Landing 2 12.118 0.42 10.18
Inclined 1 16.249 3.5 0.42 23.89
Steps 16 0.833 3.5 0.5833 27.22
61.29
Total stair case concreting 122.57
Total Rcc work 2829.315

5 Masonry wall/Brick work


5.1 For tie beam wall 1 186.843 0.75 2.83 396.574
5.2 Toe wall 1 1.98 12.75 25.25
5.3 Ground Floor
9" Wall 1 118.823 0.75 8.16 727.2
4" wall 1 34.923 0.33 8.91 102.68
829.88
5.4 First floor
9" wall 2 122.823 0.75 8.16 1503.35
4" wall 2 109.336 0.33 8.91 642.96
2146.31
5.5 Second floor
9" wall 1 126.14 0.75 8.16 771.98
4" wall 1 93.836 0.33 8.91 275.91
1047.88
5.6 Top Floor
Parapet wall
1 29 2 3 174
1 18 0.33 2.5 14.85
1 23.75 0.33 3 23.51
212.36
5.7 4" thick brick all over exterior slab 1 261.83 0.33 0.33 28.51

Deductions
Door MD -1 3.5 0.75 7 -18.38
Door D1 -7 3 0.75 7 -110.25
Door D2 -5 2.5 0.75 7 -65.63
Door/Window -1 10.25 0.75 8.16 -62.73
Door/Window -2 9 0.75 8.16 -110.16
Window W -1 6 0.75 24 -108
Window W1 -1 10 0.75 8.16 -61.2
Window W2 -1 8 0.75 4.5 -27
Window W3 -5 6 0.75 4.5 -101.25
Window W4 -1 4 0.75 4.5 -13.5
Window W5 -1 3 0.75 4.5 -10.13
Window W6 -3 1 0.75 8.16 -18.36
Window W7 -3 1 0.75 5 -4.95
Ventilation V1 -1 7.5 0.75 2 -11.25
Ventilation V2 -1 6.75 0.75 2 -10.13
Ventilation V3 -1 6 0.75 2 -9
Ventilation V4 -4 2 0.75 2 -12
-753.9
Total Masonry Work 3932.87

6 Plaster Work
6.1 Exterior Plaster
6.1.1 Ground Floor 1 120.98 9.33 1128.743
Deduction
Door MD -1 3.5 7 -24.5
Window W7 -3 1 5 -15
W2 -1 8 4.5 -36
W3 -3 6 4.5 -81
W4 -1 4 4.5 -18
W -1 6 24 -144
V4 -1 2 2 -4
806.24

6.1.2 First floor 1 120.98 9.33 1128.743


Deduction
D/W1 -1 9 8.16
W3 -1 6 4.5
DW -1 10.25 8.16
W1 -1 10 8.16
V3 -1 6
V4 -2 2
Unit Remarks

ft^3
ft^3 L=16.67+14.17+14.17+13.083+16.75+11.75+15.33

ft^3
ft^3

ft^2
ft^2
ft^2

ft^2

ft^3
ft^3

ft^3

ft^3

ft^3

ft^3
ft^3
ft^3
ft^3
ft^3
ft^3
ft^3

ft^3
ft^3
ft^3

ft^3

ft^3

ft^3
ft^3
ft^3
ft^3
ft^3
ft^3

ft^3
ft^3
ft^3
ft^3

ft^3
ft^3
ft^3

ft^3
ft^3

ft^3
ft^3

ft^3

ft^3

ft^3
ft^3

ft^2 L=32.75+27.5+32.75+28.167=120.8/ H=8+1+0.33

ft^2
ft^2

ft^2

You might also like