Professional Documents
Culture Documents
Appendix A: 23
Part 2: Blemishes in Concrete
Production of Concrete Surface Finishes
Appendix B: 27
General 8 Checklist of Specification, Design and
Construction Matters.
Variations in colour and texture 8 Structural detailing 27
Formwork 27
Determination of Finish 9 Release agents 27
Cements 27
Treatment before casting – Type A 9 Aggregates 27
Off-the-form finish 9 Mix design 27
Characteristics of form materials 10 Preliminary contract work 28
Surfacings applied in the mould 12 Supervision 28
Surfacings applied after casting 13 Weather conditions 28
Wet off-the-form finish 13 Batching 28
Mixing 28
Treatment during setting – Type B 13 Placing and compaction 28
Face-down treatment 13 Striking 28
Face-up treatment 14 Remedial work 28
Coloured concrete surfaces 15
NZS 3114, which was revised in 1987, provides the Limited by standard measurement.
format which enables the statement of the concrete
finishing requirements of the specifier to be • Colour Variation
translated, through contract documentation, to the
contractor. The standard is divided into three parts: Inherent shade variations are limited by
Sample Reference Panels (SRP) defining the
1. Off-the-form surfaces. standard and a photographic grey scale used
to define variation limit.
2. Exposed aggregate surfaces.
3. Floors, exterior pavements and inverts. Tolerance for other colour variation factors are
not defined. SRPs are recommended where
The appendix describes the various blemishes and colour is important.
their probable causes.
Particular characteristics that cause common
The application of the standard permits appropriate distinct problems are highlighted and it is
qualities of finish to be assigned to all surfaces recommended that “precautions be taken to
being constructed, and attention to be drawn to minimise the effect”.
specific needs and requirements to be emphasised
to the contractor. • Physical Irregularities
1. Finishes that are formed, and thus mirror the Particular physical characteristics are
characteristics of the form are "F" finishes and highlighted and “precaution taken to
are described in Part 1 – Off-the-form Finishes. minimise” or “to prevent the effect” are
recommended.
2. Exposed aggregate finishes, whether formed
or otherwise are described in Part 2 - Exposed • The “X” Factor – (for Exceptions)
Aggregate Finishes. This section refers to its
counterpart in Parts 1 and 3, using a suffix 'E' The specification permits the specifier to
and also dictates additional parameters that define variations from the standard by using
are imposed because of the exposed the “X” factor. Thus the finish will be as
aggregate nature of the finish. defined by the standard except as further
• Sample Reference Panels (SRP) This category covers the concrete surfaces
that are primarily dependent on the formwork
To quantify tolerance limits of physical for texture and finish. As such the most
irregularities and colour variation, the effective results are gained by attention to
specification stipulates that the specifier detail before the concrete is cast. The
nominate an existing finish that is locally formwork dimensions, rigidity, joint tightness
available for inspection (Cl. 104.4.1). and texture all become of increasing
Minimum size SRPs (650 x 650 mm) could be importance. It is commonly accepted that time
produced during the tender period if required spent before casting to ensure the exactness
by the specifier. The standard recommends of all of the above is never wasted. Often
that full size sample panels be produced short-cuts prove very troublesome and more
following tender acceptance, and that costly in the long-term with significantly more
acceptance of such panels should serve to hours, and money, being spent attempting to
establish a quality reference for the remainder remedy defects resulting from such short cuts.
of the job. The specifier and constructor are
recommended to consider the checklists in The six classifications (F1 to F6) cover all
Figures 1 and 2. qualities of formed finish. They range from
hidden surfaces - (F1) (e.g. foundations, rear
Since the production of the SRP will be, unless of retaining walls, lined surfaces, underwater
otherwise specified, after the contract is dam faces), plaster surfaces (F2), exposed
awarded, it is important that the specifier surfaces viewed from afar (F3), to architectural
clearly define the texture and any special and high quality panels (F6). Table 1 outlines
effects he requires at the timer of tender. the range and requirements incorporated in
Such definition may be by reference to the standard specification.
existing panels, the use of good quality
photographs, including scale, or a Although there is a grey scale included in the
combination of both. Standard there are no specific limits set as to
the variations accepted under each finish. It is
The constructor must be confident that the up to the specifier to determine an acceptable
required finish can be produced and should range and to monitor this with a SRP. Any
incorporate in his tender price an allowance finish that has nominated colour range
for all special measures that he considers restriction must be designated with the X
necessary to achieve the required finish. suffix and the range specified.
When assessing SRPs for acceptance with The typical control is the restriction to a range
respect to colour variation, the time from of 2 or 3 shades. For example: Using the
casting will be significant, and should be shade chart NZS 3114. The SRP sets the mean
agreed. The constructor should use the SRP to position of colour shade. In this example let it
demonstrate difficulties (e.g. formwork be shade 3. A specification calling for a range
junctions and displacements, mix variation, of three shades would permit panels ranging
colour variations due to pressure variation in colour from shade 2 to shade 4.
with height, and vibration. It is advisable to
include construction joints, rebates, arrisses The greatest contrast for two adjoining panels
etc., that will be encountered in the job so or areas is shade 2 compared to shade 4.
Filling Composition
Acceptable Shade
Sample reference
Grout Loss/Scour
Blowhole Limits
panels required
Sheet Location
Contamination
Gradual (mm)
Efflorescence
Discoloration
Abrupt (mm)
Retardation
Deflection
Scabbling
Formwork
Chipping
Form Tie
Spalling
Method
Dusting
Range*
Action
F6 Surface of high Architectural or
importance. feature panels. 1 2 mm
R 4 P P P P P * 2 E A A P P P S A A
Alignment, appear- High velocity water 3 1/360
ance very important. channels.
R = Required S = Specifier to Stipulate P = Precautions to Minimise Effects E = Prevent Occurrence A = Approval Required
* If specified shade range required, the finish must be designated with X suffix.
Tighter control can only be exercised with a The primary extension relates to the selection
range of two shades which is difficult to and uniform end result of the aggregates to be
administer since the concept is that the SRP exposed. In all cases SRPs are required to
sets a mean about which there can be lighter provide a means of compliance.
and darker shades. Consequently unless the
SRP mean shade is literally "between" two When using exposed aggregate surfaces, the
shades, interpretation in a light/dark variation specifier must consider and define the
can be difficult for a range of two. following:
As defined, surfaces enter this category if they 1. Weathering and staining characteristics.
have exposed aggregate on their surface. The 2. The colour and mineral type.
specification extends the classification from 3. The source of the material.
Parts 1 and 3 with an "E" suffix. Thus finish F5E
is a formed finish to F5 tolerance limits with 4. Exposure depth.
exposed aggregate surface texture. 5. Angular characteristics required.
The durability required of the slab often The constructor is required to provide adequate
dictates the finish specified, with U3, U4 and protection for all surfaces from the time of casting,
U11 (trowelled, machine screeded and ground until the completion of the job. This should include
finishes) increasing the toughness of the handling during transportation, erection and all
surface. subsequent operations. Where units move beyond
the control of the constructor, as would often be
The specification tolerances with respect to the case with precast panels, protective measures
colour and physical irregularities are required should be detailed and undertaken by the
tabulated and vary somewhat depending on recipient of the units.
Table 3
Item Feature Defect
Formwork Preparation Alignment, grout loss, joint stepping.
Absorbency Crazing, colour.
Roughness Scaling, chipping, spalling.
Cleanliness Discolouration.
Release Agents Effectiveness Scaling, chipping.
Purity Local discolouration, shade variability.
Compatibility Retardation.
Mix Design Low strength Scour, scaling, chipping.
Excess cement Crazing.
Proportions Blowholes.
Placement Inadequate ventilation Air pockets, honeycomb.
Excessive drops Segregation, steps.
Excessive vibration Crazing, laitance.
Non-uniform Plastic cracking.
Curing Impurities Contamination.
Inadequate Crazing, warping.
Uneven Colour variation, efflorescence.
Excessive Abrasion, scour.
• Blowholes: Form faces which have an tongues and plastic foam strips should
impermeable surface tend to have a be used. The tongues hold adjacent
higher incidence of surface blowholes. In boards in alignment and the plastic foam
this regard plastic faced ply whilst strip prevents leakage at the joints which
producing a smooth surface is likely to otherwise would form fins or
have a higher incidence of blowholes discolouration accentuating the joint
(Figure 5); lines. The boards must be of uniform
thickness so that there will be no offsets
• Crazing: Form faces which have a glazed at the joints.
smooth or polished impermeable surface
can lead to fine cracking. As will be seen Rough board surfaces; Where no joints
from a comparison of these factors, between boards are to be emphasised
specific provisions to avoid blowholes the procedures are as above.
may lead to hydration discolourations
and vice versa (Figure 6). Featured joints; Raised joints between
adjacent boards can be emphasised by a
• Characteristics of Form Materials chamfer of say 10 mm on a 25 mm board.
Mechanical damage however is very likely
The range of patterned and smooth textured with horizontal raised joints. A better
finishes is considerable. Some examples of feature therefore is produced at the joints
materials used to imprint patterns are between boards. The indent is produced
discussed. by fixing a fillet on the board face at the
joint position.
• Timber: Sand blasted to raise the grain,
rough cut; bevelled or champhered for Profiled surfaces; When deep profiled
fluting; clapboard fashion for bold texture surfaces are to be produced, timber
etc. formers should have a draw of 1 in 4 for
softwood and 1 in 6 for hardwood.
Smooth board surfaces; For the
smoothest possible board marked finish General comments; To achieve maximum
only dressed tongued and grooved uniformity of colour, timber should be
boards or grooved boards with loose pre-treated by thorough oiling before the
Surface coatings reduce the colour • Neoprene and rubber linings: Rubber
variations on the concrete face as well as sheet linings may be used to create
extending the ply's use. In particular, textured or profiled surfaces. The surface
colour variations due to concrete is generally of uniform colour although
pressure are less marked. having some blowholes. For fixing in
vertical positions linings can be glued or
As the surface coating becomes more tacked to the backing sheet.
impermeable, such as a plastic faced
sheet – HDO – then there tends to be an Thick sheets may be lightly tacked since
increase in the formation of blowholes the fluid pressure of the concrete is
and a possibility of crazing. Relative sufficient to expel any air between shutter
number of reuses is, however, increased. face and rubber lining. Thin sheets
should be stuck to the backing
• Steel: Steel forms produce concrete of shuttering.
uniform colour provided they are
protected adequately from rusting and Mineral oil based release agents must not
form face vibration can be reduced; be used since these soften the rubber.
however, because they are impermeable, Castor oil or lanolin are suitable release
• Face-down Treatment
Figure 8: Sand bed technique for face-down
This process involves the treatment of the
special finish casting.
mould with a chemical surface retarder which
slows the setting process of the concrete
The aggregate transfer method can be used for which comes into contact with it while
small areas of vertical casting. Aggregate is allowing the body of the concrete to gain
pre-selected and glued to a backing sheet strength. The slowing of the surface setting
which is placed in the mould and allows the form to be struck and the soft
subsequently stripped off after casting has material to be removed by washing and/or
embedded the aggregate. brushing exposing the aggregate. Finishes
vary from a light exposure (cement only
• Surfacings Applied After Casting removed and edges of closest coarse
(Precast Only). aggregate exposed) through a medium
exposure (cement and surface sand removed)
The finish is that of the facing material with to a deep exposure (up to 12 mm surface
the concrete providing strength and bond to removed, coarse aggregate is the predominant
the element (ceramic tile, brick, or stone). surface feature).
Attention must be paid to the compatibility of The shape of the aggregate, its position
the texturing material with the concrete following consolidation and the depth of etch
backing. Aspects requiring investigation will determine the surface appearance. The
include different thermal expansion appearance will therefore vary to some degree
characteristics, (especially for dark coloured depending on orientation of the surface and
materials), the effects of humidity, stability on the aggregate shape. This should be taken
under atmospheric attack, and chemical into account for returns and exposed vertical
compatibility with the concrete backing. sides of forms.
Where significant differences in movement are The retarder is usually in a liquid form. It must
expected between the facing material and the be applied uniformly to the formwork usually
concrete, a complete bondbreak can be with a roller, although it may be spray applied.
incorporated, and the facing attached by
mechanical fasteners. Recognition of the need If the formwork has varying absorbency (e.g.
for independent movement must be made. timber or ply) this can influence the degree to
Usually, cut stone faces have little resistance which the retarder will be effective when it
to bowing, and chipping or cracking can comes to exposing the aggregate. This effect
readily occur. This necessitates careful can be reduced by sealing the formwork with a
• Face-up Treatment
Care must be taken when casting vertical It is possible to produce different textured
elements that the concrete does not discharge finishes by stopping at the screeding
directly on to a retarder-treated surface, as stage or proceeding to the floating stage
this will both remove the retarder and when, for example, a woodfloat finish is
contaminate the concrete mass. Similarly, formed. Texturing is described in a later
vibrators should not be held in contact with section.
the form surface as this will also remove the
retarder. Rain may also remove the retarder • Exposed aggregate: The process primarily
before casting. involves a brushing and washing method
during the concrete setting process.
The selection of which type of retarder to use Occasionally a retarder application and
will depend upon the time to stripping, the after-set washing may be used. The
• Pigmented concrete: The pigments are 3. Consisting striking times for face
added to the concrete during batching formwork where used, or consistent
and operate on the binder (i.e. the trowelling techniques for horizontal
cement) while the aggregate particles surfaces. Different trowelling times
remain unaffected. The use of coloured or applications can give colour
aggregates is not necessary although variations;
contrasting aggregate/binder colours can
be used to good effect with exposed 4. Consistent curing methods used
aggregate finishes. throughout job. Variation in curing
can give rise to serious colour
Care must be taken when selecting discrepancies.
colouring pigments which must remain
colour stable when exposed to sunlight • Coloured aggregates: Both colour and
and weather. Water soluble salts within texture can be added to concrete surfaces
the pigment may accentuate by using coloured aggregates which are
efflorescence and should be avoided. exposed. The methods and depth of
exposure are the same as those
The pigments are most commonly described elsewhere (i.e. retarder,
derivatives of Iron Oxide (reds, browns, brushed, sand embedded etc.).
yellows and blacks), Chrome Oxides
(greens and blues) and Titanium Dioxide The significant differences between this
(white). type of colouring and pigmented concrete
is that the surface usually has texture as
To achieve maximum uniformity of colour well as colour. The exception is when the
it is vitally important to have: hardened surfaces are mechanically
ground (see later section) thus exposing
1. Consistent batching of all materials sections through the aggregate.
Removal of the skin of hardened cement Whilst tooling should not be commenced
paste from the face of the concrete until the concrete has gained sufficient
reveals rather than masks any strength to resist serious spalling, it is
imperfections, whether they be from poor possible to start after 1-2 days. The earlier
formwork design or lack of attention to the start obviously the greater the rate of
mixing, placing and compaction of the production. By leaving the tooling to the
concrete. This cannot be emphasised too latter stages of the job, the work takes
strongly as the most common considerably longer to execute but has of
misconception is that tooling will improve course the advantage of removing surface
the appearance of poor quality concrete. staining that might have occurred during
construction at higher levels of the
In general, to produce a satisfactory building.
tooled finish, it is first necessary to
produce a good plain finish. It is Scaling is achieved by using a pneumatic
important to obtain complete compaction scaler fitted with three piston-headed
and to avoid any segregation for when the chisels that rotate and fracture the
mortar skin is removed these defects are concrete surface. The result is a fine
noticeable to a greater depth than before. nibbled effect, rather than a deeply
chipped texture. This method is more
Colour variations on the mortar skin helpful towards minimising surface
caused by the use of an absorbent lining defects than say blasting, and is
are not important as this discolouration considerably cleaner than grit blasting.
does not penetrate deeply. Consequently
any type of form face material may be Bush-hammering is a similar process but
used as long as special attention is paid the bush-hammer face has a deeply
to rigidity at all joints and the avoidance indented multi-pyramidal pattern. The
of leakage through the formwork. The hammer head is driven by a pneumatic,
final finished appearance will depend electric or hand hammer and the result is
upon the detailed design, the forgiving in that it can contribute to
composition of the concrete and the masking surface defects.
method used to expose the aggregate.
A chiselled or pointed tool is used for
With all methods of bush hammering, the jack-hammered surfaces. This system
If tie rods are the type that are entirely removed A typical specification for bag rubbed surface
from the wall they should be pulled toward the dressing is as follows:
inside face to avoid spalling the concrete on the
exposed surface. The holes should be filled as 1. The concrete surface should be thoroughly
soon as possible after stripping of formwork. pre-wetted then permitted to approach a
surface dry condition.
Tie holes should be filled solid with mortar using a
grease gun of the plunger type such as those used 2. The grout mix should consist of 1 part cement
on automobile transmissions. The flexible hose on to 1½ to 2 parts fine sand. The sand should be
the gun should be replaced by a short pipe for this clean and free of deleterious materials. White
purpose. Filling should be done from the inside of cement or white sand may be used in place of
the wall. A piece of burlap or canvas should be held a proportion of the ordinary portland cement
over the hole on the outside face and when the and sand. The grout should have the
hole is completely filled the excess mortar should consistency of thick cream.
be wiped off with this cloth. No other finishing is
necessary. 3. To fill all small air holes the grout should be
rubbed thoroughly in a circular motion over
Where tie holes are to be filled and there is no the area with clean burlap or sponge rubber
colour match requirement, then the holes should pads.
be filled with a mortar mix consisting of 1 part of
cement to 1 to 2 parts of sand passing a 4.75 mm 4. After the grout has stiffened sufficiently any
sieve. Appearance can be enhanced in many cases surplus grout may be removed with a burlap or
by stopping the mortar filling of form tie holes sponge rubber pad.
about 2 or 3 mm from the surface. This requires
properly aligned tie bolts, but the resulting effect is 5. When visibly dry (after 2 hours) the surface
worth the slight effort required in setting out and should have a final rubbing down as in (4).
placing the tie bolts. This recessed filling also
relieves problems of colour differences and of Note: Brushed on cement washes are not
smearing the surface as could happen with a flush normally standard practice.
finish.
The sand should all pass a 600 µm sieve and not
Exact colour and texture matching for tie hole filling more than 10%' should pass a 150 µm sieve.
is virtually impossible to achieve. However, partial
replacement of ordinary portland cement with white If it is necessary to remove fins of mortar projecting
cement and the use of a light coloured sand can at formwork joints, care should be taken to avoid
assist in reducing the colour differences between damaging the surface.
the concrete and mortar fill. Because of the
colour/texture match problem it is recommended Excessive surface grinding can cause exposing of
that holes be featured in some way such as aggregate and the resulting change of texture may
described above. be unacceptable. Hand rubbing down to remove
fins and rough patches using silicon carbide stones
Tie-rod holes left by removing only the outer ends is recommended. Grade 36 stone is the most usual
of the rod so as to leave no metal closer than 35 used but finer work can be achieved by finer stone
mm to the surface, should be filled with a small grades.
tool that will permit filling the hole solid with
mortar beginning at the back of the hole. Final hand rubbing with a piece of marble or No. 80
carbide stone can often produce an even, smooth
The mortar should be stiff enough to allow for surface.
Formwork Cements
1. The formwork should be watertight and be 1. All the cement for one job should preferably
capable of resisting the pressures generated be from the same consignment; it should
during placing. certainly be from the same works.
4. Formwork ties should be arranged in a regular 1. To obtain concrete with few blowholes, the
pattern. They should be positioned to facilitate sand content of the mix should be no higher
securing the formwork against leakage at than is necessary to avoid segregation and
construction joints. bleeding.
Weather Conditions
Striking
1. Extremes of temperatures may have an
untoward effect on the concrete. 1. The top of the concrete should remain covered
until striking.
ISSN 0114-8826
© December 1989. Cement & Concrete Association of New Zealand, Level 6, 142 Featherston Street, PO Box 448, Wellington, telephone (04) 499-
8820, fax (04) 499-7760, e-mail admin@cca.org.nz, www.cca.org.nz.
Since the information in the bulletin is for general guidance only and in no way replaces the services of professional consultants on particular projects,
no liability can be accepted by the Association by its use.