You are on page 1of 567

bending restraint. With this purpose bending restraint.

With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsore bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Labor bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laborat bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
ory of Lehigh U bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
niversity. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
atory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
d and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsore bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Labor bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laborat bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted bea bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsore bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Labor bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laborat bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
ory of Lehigh U bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
niversity. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
atory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
d and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
m-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
ory of Lehigh U bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam bending restraint. With this purpose in view,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
tests of forty-seven riveted beam-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
-to-column connections were made

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
at the Fritz Engineering Laboratory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
niversity. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
atory of Lehigh University. The test

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
results are interpreted and a simple design procedure is developed.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The investigation was sponsored and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
d and financed by the American Institute

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
of Steel Construction, which, through its Committee on Steel

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Structures Research authorized the initial work to begin in September

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1939. Actual testing was completed in June 1941, and the study of

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
the test data was virtually completed by January 1942, but the war

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
interrupted plans for publication.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
The design requirements for a beam-to-column connection in a

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
steel building frame will include the following:

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
1. The connection must have vertical shear strength sufficient to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
carry safely the vertical beam end reaction.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
2. If lateral forces on the building, such as wind loads, are to

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
be considered, the connection must have moment strength

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
as well as shear strength.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
3. If the connection is designed only for vertical loads it must

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
either be (a) flexible, or non-moment resisting, or (b) moment

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
resisting with moment strength inversely proportional to its

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
flexibility.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
---

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
* Formerly American Institute of Steel Construction Research Fellow, Lehigh

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
University ; now Research Engineer, University of Illinois, Urbana, Illinois.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
t Professor of Civil Engineering and Director, Fritz Engineerin~ Laboratory,

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
Lehigh University, Bethlehem, Pennsylvania.

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to
[ 11

bending restraint. With this purpose in view,


tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsore bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Labor bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laborat bending restraint. With this purpose in view,
tests of forty-seven riveted beam-to-column connections were made
at the Fritz Engineering Laboratory of Lehigh University. The test
results are interpreted and a simple design procedure is developed.
The investigation was sponsored and financed by the American Institute
of Steel Construction, which, through its Committee on Steel
Structures Research authorized the initial work to begin in September
1939. Actual testing was completed in June 1941, and the study of
the test data was virtually completed by January 1942, but the war
interrupted plans for publication.
The design requirements for a beam-to-column connection in a
steel building frame will include the following:
1. The connection must have vertical shear strength sufficient to
carry safely the vertical beam end reaction.
2. If lateral forces on the building, such as wind loads, are to

You might also like