You are on page 1of 2

20 Changes in the FIDIC 2017 Editions From a Claims

Perspective
I have just returned from the FIDIC International User’s Conference in
London, attended by roughly 400 delegates and speakers, all there to hear
about the new editions of the Red, Yellow and Silver FIDIC Forms of Contract.
In this blog, I have highlighted 20 changes that are of particular relevance to
claims practitioners:
1. The Red Book now has 106 pages of General Conditions as opposed to the 1999 Edition which had
62 pages. The Yellow and Silver books have been similarly increased. The increased volume is said to
bring greater clarity and include more procedures to be followed as a matter of contract.

2. The word “Claim” is defined as ‘a request or assertion by either Party to the other Party for an
entitlement of relief under any Clause of these Conditions or otherwise in connection with, or arising out
of, the Contract or the execution of the Works.’
3. There is a provision to include a percentage in the Contract Data (formerly the Appendix to Tender)
and if no percentage is stated, the percentage shall be 5%.
4. The term “No-objection” has been introduced and defined.

5. “Notice” is defined as ‘a written communication identified as a Notice and issued in accordance with
Sub-Clause 1.3 (Notices and Other Communications)’.
6. There are many more requirements for the parties to submit Notices.

7. A “Notice of Dissatisfaction” may be issued by either Party if they are dissatisfied with an Engineer’s
determination.

8. There are more detailed requirements for the Contractor’s Programmes, including programmes to
show actual progress.

9. A provision is included for including rules and procedures to deal with concurrent delay.

10. Advance warning provisions have been included.

11. The procedures for evaluating and agreeing Variations and much more prescriptive.

12. The type of events previously included under Employer’s Risks and Force Majeure clauses have
been consolidated into a single clause – Exceptional Events.

13. Both Employer’s and Contractor’s Claims are now dealt with under Clause 20 (Employer’s and
Contractor’s Claims).
14. The provisions of dealing with disputes have been separated into a new Clause 21 (Disputes and
Arbitration) to reflect the fact that claims only become disputes if a Party gives a Notice of a dispute.
15. Specific provisions of the requirements of a claim submission are included under Sub-Clause
20.2.4 (Fully Detailed Claim).
16. Under Sub-Clause 20.2.4 (Fully Detailed Claim), the claim submission period has been extended
from 42 days to 84 days, but submission has now become a condition precedent to entitlement.
17. Under Sub-Clause 3.7 (Agreement or Determination), if the Engineer does not give Notice of
agreement of rejection of a claim within 42 days, the Engineer shall be deemed to have given a Notice
rejecting the claim.
18. The Dispute Adjudication Board (DAB) is now referred to as the Dispute Avoidance/Adjudication
Board (DAAB) which reflects enhanced requirements for the DAAB to be proactive in dispute
avoidance.

19. All DAABs are standing boards.

20. There are many more ‘deeming’ provisions whereby if a Party does not act in accordance with an
obligation, then the provisions will state that a specific action is deemed to have taken place.

On the face of it, the 2017 forms of contract will require more contract administration if the claim
procedures are to be complied with, but if we think about things for a moment, this is not necessarily
the case. Many of the changes have been introduced because the parties simply did not do things in
the way that the 1999 versions required. For example, Contractor’s did not submit claims within 42
days of the event and Engineers did not respond to claims within 42 days, but there were no
consequences for failure to do so. Claims were therefore often left until the end of the project and in
many cases they then became hard to resolve and often resulted in disputes which required additional
and often costly resources to manage matters.

Isn’t it better to put the necessary resources in place from the beginning of a project to avoid things
reaching this situation and settle claims as the project proceeds? You may think that this is an
expensive option, but if we consider that the costs of arbitration may reach US$ 500,0000, I think not.

You might also like