You are on page 1of 10

Improving sulphur plant performance

Strict attention to utilities is critical to ensure safe and reliable sulphur


recovery unit operation

ELMO NASATO
Nasato Consulting

C
urrent trends in the char- In theory, the SRU is a rela- dioxide (SO2) that is generated.
acteristics of crude oil tively simple process operating Redundant sulphur plants may
supply, petroleum prod- unit, but the details in design be required and the refinery
uct demand, and tightening and operation of the SRU, the may need to curtail or limit
environmental regulations upstream amine acid gas unit throughput in its sulphur pro-
require continuous change in (AGU) and sour water stripper ducing units until the sulphur
the worldwide refining and gas (SWS) acid gas unit are criti- plant can be repaired. This
producing industry. Refiners cal in maintaining very high can lead to lost profits and,
and gas producers are con- on-line factors. In comparison in some cases, fines by envi-
fronted with more stringent with the process side of the ronmental agencies. Proven
environmental, safety and reg- SRU, the utility side of the SRU techniques exist in both the
ulatory requirements that must is frequently neglected in both design and operation of the sul-
be met while maintaining very the details of the conceptual phur recovery block that will
high on-line factors in a safe design and in normal day-to- improve its reliability. These
and highly efficient operation. day operation. However, the techniques have been shown to
More hydrotreating and utility side frequently provides improve the on-stream factor
increased processing severity harsh reminders of its impor- dramatically and provide for
are required for removing sul- tance and the need for keen up to the industry standard of
phur and nitrogen compounds attention in order to ensure five years between scheduled
from fuels to meet current and reliable, safe and high on-line turnarounds.
future environmental regula- operation of the SRU complex. As environmental regulations
tions. The increase in produc- This article will describe some become more stringent, optimi-
tion of hydrogen sulphide (H2S) of the key design and operating sation of the sulphur complex
and ammonia (NH3) in com- parameters that are to be con- continues to be a design chal-
bination with more stringent sidered in the SRU, AGU and lenge as the industry continues
sulphur recovery levels, on-line SWS in order to improve per- to approach near 100% sul-
factors, and safety requirements formance and on-line reliability phur recovery levels. However,
has placed new demands on of the SRU. the challenge for operating
the processing capability of companies is to take action to
refinery sulphur recovery units Reliability considerations control excess emissions and
(SRU). These developments Acid gas flaring is prohibited maintenance costs. The goal
have led to an increased under- by law in most regions, except for most operators is to elimi-
standing of root cause failure for very short periods of time nate unplanned shutdowns of
adversely affecting SRU perfor- during an emergency situa- the sulphur recovery opera-
mance and on-line time. tion, due to the toxic sulphur tions. This goal has the bene-

www.digitalrefining.com/article/1001391 PTQ Q2 2017 1


FG1 RGG
Air2
RH1 RH2
ABSA
HBED
AD
CV1 CV2 QTW
WHE
RF
IL STK
FG2
Air1 Air3
CD1 CD2 CD3 CL
INCT

Figure 1 Two-stage Claus unit plus reduction/absorption TGTU

fit of achieving environmental phur complex can be linked mise process upsets and equip-
compliance but also improves directly to the SRU, TGTU but ment problems.
overall safety and economic more importantly the AGU and • To achieve high sulphur
viability through increased upstream SWS unit. The four recovery efficiency and reli-
equipment reliability. The best typical, high priority causes of ability in the SRU, the flow
practice for a SRU operation unit failure (causes that fall in measurement and control loops
is to keep the unit hot; this both the high probability and must be accurately tuned and
implies starting the unit and high consequence categories) utilise v-notch control valves,
desirably only shutting down can be categorised in general size permitting. The air con-
for scheduled maintenance terms as follows: trol loop as a minimum should
turnarounds. It is thermal • Fouling problems use a combination of feed for-
cycling of the SRU complex • Instrumentation problems ward and feedback whereas
that causes the most damage • Utility problems feed forward control is based
and places personnel and the • Human or procedural errors. on measured feed flow rates
environment at the greatest It is worth noting that every and independent feedback con-
risk. refinery and gas plant is unique trol from a tail gas air demand
A typical refinery sulphur and consequently operating analyser measuring H2S and
recovery operation, compris- reliability issues are site spe- SO2.
ing of a two stage Claus unit cific. However, in general terms • The acid gas burner must be
and reduction-absorption type the above list of four problem a high efficiency burner capable
tail gas treating unit (TGTU) is items is common to most loca- of operating at high turndown
shown in Figure 1. tions, regardless of location, and ensuring complete contam-
Although the process is sim- operating philosophy and/or inant destruction.
ple, problems do develop. corporate culture. • The reaction furnace must
Unexpected upsets and shut- include a refractory system
downs of sulphur recovery Design impact of SRU and TGTU that is properly designed and
operations cause excess SO2 In theory, the SRU is a rela- installed for start-up, shut-
emissions and increase plant tively simple process operating down and normal operation.
maintenance costs. Examples of unit, but the details in design The refractory material must
resulting cost increases include: of the SRU are critical in main- be compatible with a H2S, SO2
direct replacement costs for taining very high on-line fac- reducing environment in order
damaged equipment, labour tors. Some of the key design to avoid thermal and mechani-
costs for repairs, and increased features of SRUs with higher cal degradation. The refractory
costs for maintaining greater reliability include: design should include a prop-
inventories of spare catalyst • Generously sized knock-out erly designed external weather
and critical parts. drums are provided in the acid shield to control the furnace
Based on operating experi- gas feed piping to remove free metal skin temperature.
ence, shutdowns in the sul- liquids, which helps to mini- • The waste heat boiler should

2 PTQ Q2 2017 www.digitalrefining.com/article/1001391


be designed with thin tube ing with a minimum 1% slope the feed to the amine absorber.
sheet, proper strength weld to be completely free draining One of the main sources of
tube/tube sheet connections • Minimise molten sulphur pip- hydrocarbon carry-over in an
for maximum tube sheet relia- ing lengths, and slope all sul- AGU in a refinery is the hydro-
bility including an engineered phur piping 2% if possible. treater and LPG contactor. To
ceramic ferrule tube sheet pro- prevent hydrocarbon from con-
tection system. Preferred gener- Design impact of amine gas densing inside the contactor,
ated steam pressure is 450 psig unit/sour water stripper the amine temperature must be
or 600 psig. The design of the ARU and 10°C (20°F) greater than that of
• Two or three catalytic reac- SWS should incorporate the the inlet hydrocarbon stream.
tion stages follow the thermal necessary equipment and fea- The lean amine temperature
stage. Indirect steam reheat- tures to ensure the stable, reli- should always be higher than
ers using steam as the heating able and efficient operation the hydrocarbon feed to the
medium to control the reactor of the downstream SRU. To absorber; this prevents conden-
inlet temperatures. minimise the effects of these sation of hydrocarbons into the
• Properly designed, installed upstream units on the opera- rich amine stream.
and maintained thermal steam tion of the SRU it is important
tracing/jacketing system. to minimise the hydrocarbon Amine regeneration unit
The design of the reactor sec- content of the acid gas and to Minimising the hydrocarbon
tion of the TGTU should be provide a consistent acid gas content of the acid gas stream
based on low operating temper- composition. from the amine regenerator
ature hydrogenation catalyst. requires a rich amine flash
This relatively recent devel- Amine absorbers drum sized for a recommended
opment in catalyst technology Fouling problems in the SRU minimum 20-minute residence
increases TGTU reliability and are frequently caused by time and for an operating pres-
reduces capital and operat- hydrocarbon carry-over from sure of less than 350 kPag (50
ing costs. TGTU amine system the AGU that results in the psig). This allows the free liq-
performance and reliability formation of solids in the SRU. uid hydrocarbons to float to
hinge on having a good amine The solids plug instrumenta- the surface and be skimmed off
management programme to tion ports and SRU catalytic and the dissolved hydrocarbons
maintain solvent strength and beds, and foul heat exchang- to flash off from the rich amine.
purity. ers, leading to loss of control, SRU reliability is directly
SRU plant layout can have a operational difficulties, excess correlated to amine system
significant impact on reliability SO2 emissions and, ultimately, performance, with amine reli-
due to the safety, fouling and shutdowns. ability dependent on having a
corrosion problems inherent in To maintain reliable oper- good amine management pro-
the Claus process. The layout ation of the amine plant and gramme to maintain solvent
should incorporate the follow- ultimately the SRU, any oper- strength and purity, consisting
ing design features: ational effects of feed gas con- of the following engineering
• Minimise the length of pro- taminants should be avoided. and operational features:
cess pipe. This is achieved by the high • Lean amine partial but pref-
• With the exception of the separation feed gas knockout erential full stream filtration to
reaction furnace, ensure that all vessel. The feed gas knockout remove particulates.
equipment and piping is prop- vessel should be designed as a • Lean amine slipstream car-
erly insulated. high separation efficiency col- bon bed treating to remove
• Ensure the SRU equipment umn, installed inlet deflection chemical contaminants.
and piping is self-draining to device(s), with adequate dis- • Regular sampling and anal-
the sulphur collection point. engaging space and demister ysis of lean and rich solvent
• Use indirect u-tube steam pads. In some situations, the concentration, heat stable
reheat exchangers with steam knockout drum should incor- salt content, and chemical
on the tube side. porate a water wash to remove composition.
• Lay out equipment and pip- undesirable contaminants from • Correct selection and proper

www.digitalrefining.com/article/1001391 PTQ Q2 2017 3


dosage of antifoam agent. instrumentation, especially valve positioning and valve
Also, the cooling capac- with respect to the SRU main characteristic curves. In the
ity should be provided in the burner. The main burner has ideal case, maintaining the
regenerator overhead con- instrumentation that is critical optimal air flow to the reaction
densing system to ensure a to the safe and reliable oper- furnace during start-up and
maximum target acid gas ation of the SRU with certain shutdown procedures would
temperature of 50°C (120°F). components such as flame be accomplished using sepa-
Maintaining a low acid gas detection, front end pressure rate air to feed gas ratios for
temperature improves the acid measurement and ignitor sys- all of the possible feed gases
gas quality by reducing its tems that are included in the (acid gas, SWS gas, hydrogen
water content, to the benefit of SRU shutdown system and gas [if applicable], natural gas
the downstream SRU. burner management system. and/or fuel gas), with the DCS
While the electronics of these then summing and controlling
Sour water strippers devices has improved, the weak the total required air flow at
To minimise the hydrocarbon link in the system is the burner all times. This ‘feed forward’
content of the acid gas pro- nozzle purge system. These method of controlling the air
duced in the SWS, provisions nozzle purge systems are criti- is typically used to control
for separating free hydrocarbon cal in order to allow the instru- the main air, and the tail gas
liquids from the raw sour water mentation to work effectively air demand analyser, which
should be included in the sour but are frequently designed is used to accurately monitor
water gathering system. This and/or operated incorrectly. the tail gas H2S to SO2 ratio
should include a flash drum More detail on this subject and (whenever acid gas is one of
with 20 minutes of residence recent experience with the SRU the streams being processed) is
time, and oil skimming noz- utility systems is discussed in used to automatically adjust the
zles on the sour water storage more detail later in this article. trim air flow. Proper feed for-
tank draining to a skimmed oil In order to maintain relia- ward control, however, is only
drum. Segregating phenolic and ble SRU operation, it is imper- useful if the flow meters for all
non-phenolic sour water should ative to have a proper air streams are reasonably accu-
be considered, based on the end control system that maintains rate and if the stream composi-
use of the treated water and the the SRU operation at the tail tions do not vary significantly.
availability of make-up water. gas analyser setpoint and pro- Similarly, the critical feedback
SRU performance and reliabil- vides adequate robustness loop is very dependent on
ity are greatly enhanced by acid for feed disturbance rejection. having a well maintained and
gas feeds of consistent composi- The control scheme should calibrated air demand tail gas
tion and constant flow rate. To be programmed to allow for analyser.
accomplish this, the SWS feed independent feed flow meas- A sudden change in feed
should be of a consistent com- urement on all feed streams to gas composition represents a
position and constant feed rate. the SRU; this includes amine significant disruption to SRU
This is accomplished by provid- acid gas, SWS acid gas, and all operation. Incorporating feed
ing a well designed raw sour fuel gas streams. Each stream gas analysis in the feed for-
water storage tank with three to will have an air demand mul- ward control loop has been
five days’ capacity for blending tiplier than can be adjusted widely applied using a vari-
the individual raw sour water based on composition in order ety of analytical techniques to
streams. The tank inlet and out- to provide a feed forward air make a comprehensive quanti-
let nozzles must be separated to demand signal. Air demand fication of the components. In
avoid direct feed of sour water requirement for each stream is order to provide proper con-
through the inlet connection then fed to a summation block trol response and disturbance
directly to the outlet connection. to allow for a feed forward rejection, the analytical method
component of an air control must provide a real time (<5
Instrumentation scheme. If there is doubt about seconds) analysis of the com-
In recent years there have sig- the flow measurement, it can bustion components. The
nificant improvements in SRU be checked/inferred based on complication is the multiple

4 PTQ Q2 2017 www.digitalrefining.com/article/1001391


components of hydrocarbons errors investigated. Humans This is especially true for SRU
(HC) that can be present and are much more difficult to specific instrumentation such
will vary and be unique to each predict than equipment per- as the steam trap system, tail
disturbance episode. Recent formance. Sulphur complexes gas analysers and main burner
developments have resulted appear to be simple relative flame scanners.
in significant improvements to most units in a refinery,
that have reduced the response however sulphur units are Utility considerations
time to define each of the HC very unforgiving if there is In comparison to the process
components. Rather, it is suf- improper attention to detail. side of the SRU, the utility side
ficient for control purposes to Successful operations place is frequently neglected in both
make a single measurement emphasis on cross training the fine details of conceptual
of total hydrocarbon content between process engineers, design and in normal day-to-
(THC) that provides a signal and reliability improvement for day operation. However, the
for the total ‘air demand’. This team members, maintenance utility side frequently provides
has proven to be a reliable personnel and unit operators. harsh reminders of the impor-
method that results in a useful The goal of training should be tance of keen attention in order
and quick feed forward signal to improve operational aware- to ensure reliable, safe and high
to assist in rejecting the change ness and the important details on-line operation of the SRU.
in compositional disturbance. of the SRU complex. The purpose of this section is
A significant challenge that Precise and well understood to identify the key design and
can adversely affect reliability procedures should include the operating considerations for the
in a refinery SRU operation is following: utility side of an SRU, with the
maintaining the instrumenta- • Troubleshooting guides indi- primary intention of raising the
tion associated with handling cating possible causes of equip- awareness of its importance.
the SWS acid gas. The SWS ment malfunction and failure. A more extensive review is
acid gas is a difficult stream • Steam system monitoring, available.1
to measure accurately for flow especially steam traps. The SRU utilities and prob-
and level because of inher- • Analyser calibration and lems associated with operation
ent problems with ammonia monitoring. and design include:
salt formation at temperatures • Lists of equipment requir- • Steam (imported and
below 80°C (180°F). Formation ing vibration analysis and exported)
of salt will plug large items monitoring. • Boiler feed water, utility
such as piping, mesh pads and • Recommended lubricants and water and make-up water
condenser tubes, but is most lubrication intervals for specific • Fuel and natural gas
likely to plug smaller diame- equipment. • Nitrogen
ter items like instrument con- • Preventive maintenance task • Instrument air
nections such as flow meter lists for critical equipment. • Electricity.
pulse lines and transmitter A good predictive/preven- In all likelihood, the prob-
connections. Thermal heat tive maintenance programme lems associated with utility sys-
maintenance is critical on the includes equipment prioritisa- tems have always existed but
SWS acid gas knockout drum tion so that maximum effort is it appears that in more recent
high level switches; purging focused on the critical pieces years the frequency and sever-
of instrument lines is required. of equipment, or those with a ity of SRU problems associated
Also, it is recommended to significant impact on refinery with the utility systems have
install a continuous SWS acid operations and environmental increased. It is suggested that
gas purge meter arrange- compliance. Inspection check- the increase and severity of
ment to provide reliable flow lists with procedures includ- these problems are most likely
measurement. ing lists of proper settings, log related, but not limited, to the
sheets, and tests specific to following items:
Human and procedural error individual equipment should • Use of utilities may be
It is difficult to identify com- be made available to mainte- intermittent.
mon causes for the human nance and operations personnel. • Utilities are not instrumented

www.digitalrefining.com/article/1001391 PTQ Q2 2017 5


to the same degree as the pri- DCS systems have provided sively on data provided by the
mary process and, even when terrific advancements in con- DCS system.
they are instrumented, their trol strategies, process variable
maintenance is not prioritised data tracking, overall system Steam
as highly as process systems. component (control valves, SRUs generate two products,
• The DCS system has reduced rotating equipment, motors) sulphur and steam. In many
field checkout. tracking, and allowing for sta- cases the steam is more val-
• High turnover of staff or tistical data analysis on both uable than the sulphur. The
inexperienced operating staff. the process and utility side. steam is generated as a useful
• Overworked/understaffed However, there are certain crit- way of transferring the signif-
operating and technical support ical items, particularly on the icant amount of energy gen-
staff. utility side, that are not instru- erated by the Claus process in
• Limited SRU design mented. Especially important both the thermal and catalytic
experience. in an SRU, steam traps require stages. The steam generated in
• Lack of understanding of the diligent manual inspection to an SRU can be utilised within
intent and significance of all verify correct operation. Too the SRU, and the excess can
utility requirements. frequently, the failure of a be exported for heating the
By their nature, some of the steam trap is revealed by a low amine reboiler, SWS reboiler,
utility streams are used inter- temperature alarm on the pro- steam tracing, and so on, or to
mittently during start-ups and cess side, or a high pressure spin a turbine. In many cases,
shutdowns and the industry as alarm on the process side, as a SRUs import high pressure
a whole has moved to length- result of inadequate heat input steam, where it is not gener-
ening the run-time between due to a steam trap failure. ated within the SRU, for indi-
scheduled shutdowns. In the The safety and control fea- rect heating for feed preheaters
past, annual turnarounds were tures of the single remote con- and/or catalytic reheaters. It is
common, today scheduled trol room based on a DCS/PLC the desirable and special prop-
turnarounds are typically three system are very beneficial. For erties of steam and water that
to four years apart. Several many locations, an unfortunate make them so widely selected
refineries are targeting five casualty of this ‘advancement’ for the energy transfer role.
years between scheduled turn- is that field checkout is not as In many cases, high pres-
arounds. This change in turna- common. It is not unusual to sure steam is imported to the
round philosophy has resulted spend an entire day in a refin- SRU as the heating medium
in the start-up, shutdown and ery SRU and not see an opera- for heat exchangers for amine
utility systems being less famil- tor. There was an era in which acid gas preheating, SWS acid
iar to operating staff. It is also a routine walk through would gas preheating, combustion
more likely that the operating provide a feel for the operat- air preheating and/or catalytic
staff have changed, and thus ing condition of the unit on the reheaters and in some cases
operating experience has been basis of sound, sight (sulphur for driving steam turbines on a
lost since the last turnaround. rundowns, steam leaks, and combustion air blower.
Furthermore, the extended run- so on), smell and touch. This Another consideration in the
time increases the possibility notion may seem nostalgic, but design and repair of SRU heat
that the utility systems may modern DCS/PLC systems do exchangers is the tube to tube
have been compromised since not completely replace and are sheet weld procedure. For low
their last use. not as reliable as the human pressure heat exchangers, such
Another major change in senses. At one time the limited as the condensers, a seal weld
the industry is the trend of amount of data provided by procedure is acceptable. For
replacing satellite control the control system was supple- high pressure heat exchangers,
rooms, necessitated by pneu- mented and complemented by such as the waste heat boiler, a
matic control systems, with the database accumulated by strength weld procedure must
central remote located con- the human element. It is sug- be utilised. The proper strength
trol rooms utilising electrically gested that there may be too weld procedure is mandatory
based DCS control systems. much reliance placed exclu- but is too often neglected espe-

6 PTQ Q2 2017 www.digitalrefining.com/article/1001391


cially in field repairs.
Sulphur pumps are com- 100 000
1000
monly damaged because too
high a steam pressure is sup-

Viscosity, centipoise
plied to the pump jacketing. 10 000
100
Most vendors will recommend
adjusting and controlling steam
supply to sulphur pump jack-
1000
eting at 240 kPag (35 psig) in 10
order to avoid viscosity prob-
lems with the sulphur pump. It
is common to burn out sulphur 100
1
pump motors because the sul- 200 300 400 500 600 700 800 900
phur would not flow, so higher Temperature, ºF
pressure steam was used to
help make it flow. The sulphur Figure 2 Pure sulphur viscosity curve
viscosity curve (see Figure 2)
supports the need for utilising Carbon dioxide has a higher of condensate, continuously
240 kPag (35 psig) steam and solubility, roughly 30 times purge non-condensibles and
not higher than 240 kPag (35 greater than oxygen. Free oxy- accommodate the condensate
psig) pressure steam. gen is a normal component of return pressure. Regardless
Boilers and steam systems are a water system but it is the agi- of the steam trap selected, a
full of air prior to start-up. A tation of boiling that causes the robust structured monitoring
very important requirement of carbonates in water to produce and maintenance plan is rec-
getting any steam system oper- carbon dioxide. Both gases will ommended. All traps even-
ating efficiently is the removal cause corrosion in the entire tually fail, and trap surveys
of air. Air is a poor conduc- steam/condensate system. A commonly report that a third
tor of heat and thus mixtures very important feature of a of a plant’s trap population
of steam and air, for a given properly designed steam sys- does not function properly.2 It
steam pressure, have less heat tem is the ability to purge these is mandatory that the design
content than steam alone. non-condensibles from the and installation facilitates iso-
This fact also means that the steam system. lation and easy removal of
mixture will have an adverse One of the critical elements steam traps while the SRU is in
effect on heat transfer rates. in the entire steam system is operation,
With higher pressure boilers, steam traps. In the industry Corrosion is a given factor
the feed water is often passed there have been significant in a steam system. Corrosion
through a deaerator before it is problems with the design and attacks boiler tubes, steam
pumped to the boiler. The best far too often steam traps are mains, heat exchangers, valve
deaerators can reduce oxygen ignored in day-to-day opera- components and fittings such
levels to 3 ppm in water. Non- tions. The purpose of a steam as steam traps. The primary
condensible gases, specifically trap is to remove condensate defence is to carefully mon-
carbon dioxide and oxygen are from a steam heating sys- itor and maintain the boiler
both present in steam systems. tem while ‘trapping’ steam in feed water treatment system
At 80°C (180°F), water can dis- the system. This is essential and control of the non-con-
solve about 0.6% of its volume to the successful operation of densible gases (oxygen and
of air. The solubility of oxygen the heating system. There are carbon dioxide) that promote
is roughly twice that of nitro- many different types and fea- corrosion. There is a significant
gen, so air which dissolves tures of steam traps available amount of trash and accumu-
in water contains nearly one on the market, but not all steam lated debris in both a newly
part of oxygen to two of nitro- traps perform well in all situ- commissioned and existing
gen rather than the one part to ations.2 The steam trap must isolated system. It is manda-
four parts in atmospheric air. keep the jacket system clear tory to disconnect steam traps

www.digitalrefining.com/article/1001391 PTQ Q2 2017 7


connected directly to the steam the boiler regardless of whether
system, admit steam and flush From steam or not continuous blowdown is
tracing/jacketing
the entire system until the sys- Trap employed. Continuous blow-
½ in ½ in
tem is blown clear. In older down is a continuous and auto-
systems, especially those that matic removal of concentrated
½ in
are used intermittently, dirt, boiler water. A problem that
corrosion products and foreign appears to have become more
debris will cause problems with common is related to the design
traps, small valves, instruments Figure 3 Steam trap installation detail and the operational procedures
and steam traps. Dirt prevents related to continuous and inter-
the free movement of internal sure vessel while it is under mittent blow down. By regu-
parts or can get caught between pressure. The removed water larly utilising both intermittent
valves and seat sealing sur- containing suspended and dis- blowdown connections, sludge
faces, leading to erosion dam- solved solids is replaced with and debris can be removed over
age. A properly designed pipe relatively pure feed water even the entire length of the waste
system will protect the steam though this water is treated heat boiler. From an opera-
traps by upstream pipe strain- prior to use through external tional perspective, the intermit-
ers (see Figure 3). processes designed to remove tent blowdown valve(s) should
the unwanted substances which be exercised on a regular and
Boiler feed water/utility water/ contribute to scale and deposit scheduled basis, with good
make-up water formations. Regardless of the practice being considered to be
Many waste heat boiler failures treating efficiency, none of the daily exercise of the valves. Too
are now linked to the boiler treatment processes in them- frequently, intermittent blow-
feed water/steam side of the selves are capable of remov- down is only used based on
exchanger. These problems ing all substances and a small water conductivity test results
have a significant impact on amount of solids will be pres- of samples collected from con-
SRU reliability but the current ent in the boiler water. The sol- tinuous blowdown. Depending
industry trend indicates a lack ids become less soluble in the on the continuous blowdown
of awareness on the importance high temperature of the boiler location, the sample may be
of boiler water/steam qual- water and, as the water boils collected from the steam phase
ity. The treatment of water for off as relatively pure steam, and this may result in a false
steam generation is one of the the remaining water becomes sense of security. Poor water
most difficult branches of water concentrated with either sus- management will result in
chemistry. The pressure and pended or dissolved solids. external tube fouling and
design of the boiler determine The scale forming as salts reduced heat transfer, leading
the quality of water it requires tends to concentrate and crys- to thermal stress of the boiler
for steam generation. tallise on the heating surfaces. tubes, tube sheets and tube to
Deposits, particularly scale, Scale has a low heat transfer tube sheet welds. The unfortu-
can form on boiler tubes. Each value. It acts as an insulation nate result of inadequate use of
contaminant has an established barrier and lowers heat trans- the intermittent blowdown has
solubility in water and will pre- fer, resulting in lower operat- resulted in more frequent tube
cipitate when it is exceeded. At ing efficiency and presents the failures due to high tempera-
the high temperatures found possibility of overheating the ture failure.
in a boiler, deposits are a seri- boiler metal. The result can be
ous problem, causing poor heat tube failures, tube to tube sheet Fuel and natural gas
transfer and a potential for failures or other pressure vessel Most SRUs use natural gas
boiler tube failure. metal damage. on a continuous basis for the
There are two principal types incinerator, but on an inter-
Boiler water blowdown of blowdown, intermittent and mittent basis for SRU start-up,
Boiler water blowdown is used continuous. Intermittent blow- shutdown and hot standby. In
to remove some of the concen- down is done manually and is the case of start-ups where new
trated water from the pres- necessary for the operation of catalyst has been installed, the

8 PTQ Q2 2017 www.digitalrefining.com/article/1001391


main burner may be fired with standby operation. During fuel SRU shutdown. If it is available
excess air. For all other cases gas operation, the flame colour and there is no negative impact
and for the majority of natu- should be field checked sys- upon the furnace flame temper-
ral gas firing, the burner must tematically. An orange flame ature and flame stability, nitro-
be fired at slightly sub-stoichi- colour is indicative of air defi- gen can be utilised at all times.
ometric (air deficient) condi- cient operation, a blue flame is Each purge connection requires
tions. This is necessary because oxygen rich and a salmon-pink an individual rotameter with
any excess air will cause cat- flame color is indicative of sto- proper tagging to allow for con-
alyst deactivation and may ichiometric burn. Whenever tinuous system monitoring and
result in sulphur fires that can fuel gas firing is used intention- troubleshooting.
be very damaging to catalyst ally for an extended period, the
and equipment. first condenser outlet should Instrument air
When firing at near stoichio- be checked for excess oxygen The SRU is no different from
metric conditions, the compo- and CO. A good indication of other operating units in that
sition of the fuel gas or natural the correct (95%) stoichiometry instrument air must be reliable,
gas must be known and remain will produce 0-0.4% oxygen and properly designed and main-
constant. This is where a clear around 2000-4000 ppm CO in tained in order to ensure safe
distinction between fuel gas the flue gases. and reliable operation of the
and natural gas exists. Natural The thermal stage is designed SRU. There are certain design
gas is normally of fixed and to operate with natural gas and maintenance requirements
known composition while fuel for start-up, shutdown and that are somewhat unique to
gas can be made up of almost hot standby. Natural gas fir- SRUs.
any mix of constituents, hydro- ing requires stoichiometric The air system for an SRU
carbon and non-hydrocarbon operation and the resulting must have adequate capac-
that can be found in a refinery. flame temperature of 1650+°C ity for air consuming instru-
Furthermore, the only certainty (3000+°F) can be damaging and ments and, if applicable, all
with fuel gas composition is thus natural gas firing requires furnace purge connections. As
that it most likely will change. flame moderation. The refrac- described in the nitrogen sec-
Not knowing the exact compo- tory in the reaction furnace and tion, it is common to utilise
sition of the fuel gas runs the fired reheaters must be designed air for the continuous purge of
risk of either firing with excess for the elevated temperature of burner nozzles during normal
oxygen, resulting in potential the natural gas operation. operation. This is acceptable
sulphur fires, or firing with as long as the SRU is in opera-
significantly deficient oxygen, Nitrogen tion but if the SRU trips the air
resulting in soot formation. It is paramount for the contin- must automatically be replaced
The effects of a sulphur fire are uous, successful operation of by an inert medium such as
quite clear. The formation of a the reaction furnace burner that nitrogen (preferred) or steam.
significant amount of soot will during normal operation, con- The quantity of air required for
result in heat exchanger foul- tinuous purge is provided to the purges must be included
ing, catalyst damage and the the following burner nozzles: in the design of the instrument
soot will reduce SRU capac- • Flame scanners air system and supply headers.
ity. If the additional pressure • Sight glasses on the burner Some pilots require large quan-
drop created by the soot can- and reaction furnace tities of instrument air which
not be tolerated, and if the soot • Ignitor port can tax the system severely.
cannot be removed on-line, a • Reaction furnace temperature The instrument air should be
shutdown will be required to measurement free of all contaminants such
mechanically remove the soot • Idle ports, such as natural as dirt, oil, water and corrosive
and to clean heat exchanger gas, on burner (purge rate to be gases. It is recommended to
tubes. The SRU must be set by vendor). utilise instrument air for purg-
designed and operated with The purge medium can be ing rather than a slipstream of
known composition natural gas instrument air during normal air from the SRU combustion
for start-up, shutdown and hot operation and nitrogen after an air blower. The combustion

www.digitalrefining.com/article/1001391 PTQ Q2 2017 9


air stream is dirty, wet and at • Check quench water pH. • Instrumentation problems
a lower operating pressure. There is no replacement • Utility problems
This will cause problems with for field checkout. Extended • Human or procedural errors.
rotameters and, where appli- off-ratio operation can lead to In summary, SRU reliability
cable, burner pilots and igni- severe damage to the quench can be directly linked to keep-
tors. The air system should be water system and the amine in ing contaminants out and keep-
designed and operated with the TGTU. Operator training ing the SRU hot. While simple
a drying system that must becomes very important in this in description, the execution in
reduce the water dewpoint to a type of situation. keeping contaminants out and
minimum of 6°C (10°F) below consideration for keeping the
ambient temperature at operat- Conclusion SRU hot in the design phase,
ing pressure. Wet air has been In theory, the SRU is a rela- maintenance programme and
known to short out some igni- tively simple process operating daily operation will result in
tor systems. unit, but the details in design reliable SRU operation.
and operation of the SRU, the
Electricity upstream AGU and SWS acid References
Normally, the UPS is designed gas unit are critical in main- 1 Utility Considerations for Sulphur
to provide enough battery taining very high on-line fac- Recovery Units, Elmo Nasato, Sulphur
back-up power to allow an tors. In comparison to the 2014 conference.
2 Steam Traps, Controls Southeast Inc.
orderly shutdown in the case process side of the SRU, the
that the instrument air system utility side of the SRU is fre- Elmo Nasato is a Senior Process Engineer
is depleted of air. For the SRU quently neglected in both the specialising in sulphur recovery with
it is imperative to back up the details of the conceptual design 30 years’ experience in the sulphur
tail gas analyser, flame scan- and in the normal day-to-day recovery industry. He currently serves
ners and, where applicable, operation. The utility compo- on the Technical Advisory Committee
for the Laurance Reid Gas Conditioning
the TGTU hydrogen and pH nent and in particular the ther-
Conference and was a member of the
analyser. An SRU designed mal heat maintenance system
Board of Directors of Alberta Sulphur
with steam turbine air blowers is critical to ensure safe and Research. He has been awarded seven
will continue to operate with- reliable SRU operation. patents for SRU operation, oxygen
out external power but without Based on operating experi- enrichment and sulphur degassing
analysers the operator will be ence, shutdowns in the sulphur technologies, and holds a BSc in chemical
running the plant blind. While complex can be linked directly engineering from the University of
operating on battery back-up, it to the SRU and TGTU, but Waterloo, Ontario, Canada.
is recommended to field check more importantly the upstream
the unit including the follow- AGU and upstream SWS unit.
ing items: The four typical, high priority LINKS
• Main burner sight glasses causes of unit failure (causes
to verify the flame colour and that fall in both the high prob- More articles from the following
pattern ability and high consequence categories:
• Draeger tube, or equal, the categories) can be categorised Reliability and Asset Management
tail gas sample to determine in general terms as follows: Sulphur Removal and Recovery
H2S/SO2 ratio • Fouling problems

10 PTQ Q2 2017 www.digitalrefining.com/article/1001391

You might also like