Professional Documents
Culture Documents
PROCUREMENT DIVISION
320 Hospital Drive, Suite 23
Warrenton, Virginia 20186
Phone: (540) 422-8348 Fax: (540) 422-8355
February 5, 2018
The following revisions are made to the original Request For Proposals noted:
Section 5.2, Specific Proposal Requirements, 5.2.2, revised additional language noted next to original
text.
Location of the Offeror’s headquarters; nearest offices, applicable phone, facsimile numbers, e-mail address;
and any other pertinent information relative to the size and organizational structure of the company. Regardless
of corporate location, provide a statement confirming the Offeror’s willingness to locate personnel directly
associated with the oversight of construction of their design, within a two-hour distance of the construction site,
to avoid any unnecessary delays during construction of the new middle school.
Section 5.2, Specific Proposal Requirements, 5.2.3, revised additional language noted next to original
text (will now appear as the last sentence, added to that section).
Provide a narrative of middle school design and construction projects similar in size and scope to this project;
Offerors shall provide photos of the design and final constructed school, along with a concise summary of the
project including length of contract time from design through final construction; initial design construction
estimate; final construction cost, inclusive of change orders; and any challenges encountered during the middle
school project. Provide breakdown of project change orders, indicating total quantity and indicate if they were
Owner directed, Architect directed, or other, for our review and consideration of the effect on the total project.
6.1.1 Qualification of the Offeror to provide new middle school design, either new or prototypical re-design,
and other required services, based on resumes provided, experience of subcontractors, and references
provided. (25 points)
6.1.2 Experience of Offeror as demonstrated by middle school design and construction projects of similar size
and scope, including project summary, length of project through construction, original estimated
construction cost and final construction cost, and all change orders including quantity and source of
change order. (25 points)
6.1.3 Offeror’s written narrative/approach to fulfilling services, both as outlined in Section 3 and, in meeting
the Owner’s Middle School Philosophy and Desired Outcomes, Section 2.1. (35 points)
6.1.4 Overall completeness of proposal (15 points)
RFP 49-18sm, Professional A/E Services, New Middle School, Add #2, 2-5-18 1
Note: A signed acknowledgement of this addendum must be received by this office either prior to the
proposal due date and hour or attached to your proposal. Signature on this addendum does not
substitute for your signature on the original RFP document. The original RFP document must be
signed.
RFP 49-18sm, Professional A/E Services, New Middle School, Add #2, 2-5-18 2