HARGA SATUAN

NO URAIAN JENIS TENAGA DAN BAHANSATUAN


( Rp. )
1 2 3 4

A UPAH TENAGA KERJA


1 Pekerja Hr / org 60,000.00
2 Mandor Hr / org 65,000.00
3 Tukang Kayu Hr / org 70,000.00
4 Tukang Batu Hr / org 70,000.00
5 Tukang Aluminium Hr / org 70,000.00
6 Tukang Besi Hr / org 70,000.00
7 Tukang Cat Hr / org 70,000.00
8 Kepala Tukang Hr / org 80,000.00

B HARGA BAHAN / MATERIAL PEKERJAAN STRUKTUR & ARSITEKTUR


1 Tanah Urug Biasa M3 50,000.00
2 Tanah Urug Pilihan/ Tasirtu M 3
80,000.00
3 Pasir Urug M 3
110,000.00
4 Pasir Pasangan M 3
157,000.00
5 Pasir Beton M 3
157,000.00
6 Batu Gunung M3 160,000.00
7 Batu Split 2 x 3 cm M3 230,000.00
8 Batu Split 1 x 2 cm M3 260,000.00
9 Kerikil Kali M 3
210,000.00
10 Batu bata Bh 550.00
11 Batu Candi 15 x 30 m 2
230,000.00
12 Batu Candi 15 x 30 bh 10,000.00
13 Roster/Kerawang 12x30 cm (abu-abu) bh 12,500.00
14 Papan Bekisting Klas III M 3
1,200,000.00
15 Balok Kayu Klas II M 3
2,250,000.00
16 Papan Kayu Klas I M 3
2,800,000.00
17 Kayu Bulat /Dolken D. 5 - 8 cm Btg 7,500.00
18 Pintu Jati m 2
400,000.00
19 Multipleks 6 mm Lbr 131,100.00
20 Multipleks 9 mm Lbr 207,000.00
21 Minyak Bekesting Ltr 7,000.00
22 Semen Portlan Jenis Tonasa kg 1,500.00
23 Semen Warna kg 11,000.00
24 Besi Beton Variabel kg 15,000.00
25 Kawat Beton kg 20,000.00
26 Hollow Galvalum 40 x 40 m 8,915.00
27 Hollow Galvalum 40 x 20 m 6,475.00
28 Besi Hollow 40 x 40 m 20,000.00
29 Besi Hollow 40 x 20 m 17,500.00
30 Stailess Stel Dia 1.5" m 18,750.00
31 Were mesh M5 kg 25,000.00
32 Were mesh 4 x 4 kg 25,000.00
33 Insulation Aircell 85R M2
25,000.00
34 Paku Campur 5/7/10 Kg 17,500.00
35 Paku Sekerup buah 400.00
36 Paku + Karet Khusus Untuk Atap Zin Buah 500.00
37 Rangka Atap Baja Ringan M2
165,000.00
38 Besi Pipa Baja Hitam Kg 15,500.00
39 Baja Profil Iwf Kg 15,950.00
40 Baja Siku 65.65.6 Kg 13,750.00
41 Baja Siku 45.45.4 Kg 13,750.00
42 Plat Simpul 7 mm Kg 20,000.00
42 Baut Dia 16 mm bh 23,400.00
43 Baut Dia 12 mm bh 5,000.00
43 Baut Dia 10 mm bh 4,500.00
44 Angkur Baut Dia 16 mm Panjang 25 bh 34,500.00
44 Angkur Baut Dia 20 mm Panjang 60 bh 116,350.00
45 Baja Canal 125.50.20.3 kg 15,350.00
45 Trak Stang Besi Beton Dia 12 mm kg 50,000.00
46 Mur Baut Pengeras Track Stang bh 6,000.00
47 Kawat Las kg 50,000.00
48 Solar Industri Ltr 8,000.00
49 Pelumas Ltr 45,000.00
50 Atap Spandek Hi-Ten Colorbond 0.4 T M2
203,580.00
51 Atap Metal Zincalume Lbr 37,000.00
52 Nok Atap Genteng Metal Zincalume Lbr 40,000.00
53 Karet Pelapis Talang Lebar 0,60 M 1
15,000.00
54 Formtie/penjaga jarak bekesting/spac Buah 4,750.00
55 Plastik Sheet M2
6,500.00
56 Sewa Scafolding / Perancah M2
100,000.00
57 Batu Alam Jenis Candi (Hitam) Bh 10,000.00
58 Gypsum Board t = 9mm Lbr 180,000.00
59 Gypsum Pilaste Kg 50,000.00
60 Textile Taste Lbr 500.00
61 Calsiboard 6 mm Lbr 80,500.00
62 Sekerup Fixer Buah 750.00
63 Paku Hak Panjang 15 cm Buah 768.00
64 Rangka kayu daun pintu m' 135,000.00
65 Honeycom m2 85,000.00
66 HPL m2 300,000.00
67 Pasangan lapisan Pb m2 750,000.00
68 Cat dasar ( Cat Tembok ) Kg 9,600.00
69 Cat Penutup ( Cat Tembok warna ) Kg 24,000.00
70 Cat Penutup Anti Lumut ( Cat Tembok Kg 27,000.00
71 Cat Kilap Kayu Kg 32,000.00
72 Cat Wheathershiled ( Dulux Primer Alk Kg 90,000.00
73 Cat Penutup Wheathershiled ( Dulux Kg 100,000.00
74 Meny Kayu Kg 3,600.00
75 Meny Besi Kg 13,500.00
76 Minyak Cat Kg 3,150.00
77 Plamir Tembok Kg 8,000.00
78 Dempul Kayu Kg 15,000.00
79 Dempul Impra Kaleng 25,000.00
80 Cat dasar Impra Kaleng 55,000.00
81 Clear Sanding Sealer Impra Kaleng 39,000.00
82 Melamik Clear Impra Kaleng 42,000.00
83 Kompon gypsum plaster Kg 6,500.00
84 Thinner Ltr 7,000.00
85 Solar Ltr 17,500.00
86 List Kaca MN 17,500.00
87 Tripleks 4 mm Lbr 75,000.00
88 Tripleks 3 mm Lbr 65,000.00
89 Amplas Lbr 10,000.00
90 Lem Fox Kg 15,000.00
91 Tegel Granit 80x80 M2 138,333.33
92 Tegel Kramik 60x60 M2 150,000.00
93 Tegel Keramik 40x40 M2 150,000.00
94 Tegel Kramik 30x30 M2 80,500.00
95 Tegel Keramik Anti Slip 20x20 M2 120,000.00
96 Tegel Dinding Keramik 20x25 M2 120,000.00
97 Waterproofing Sika Zak 800,000.00
98 Waterproofing Membrane m2 207,900.00
99 Kuas Bh 27,500.00
100 Pintu Double Teakwood bh 800,000.00
101 Pas. Kusen Pintu Aluminium m' 50,000.00
102 Pas Bingkai Jendela Aluminium & Acce m' 70,000.00
103 Kusen Alumunium + Kaca Clear 5 mm m2 850,000.00
104 Kaca Panasab 6 mm m2 300,000.00
105 Kaca Panasb 8 mm m2 800,000.00
106 Kaca Tempered 12 mm m2 1,640,000.00
107 Sandblasting m2 300,000.00
108 Hendel Pintu Kaca Bh 300,000.00
109 Hendel Pintu Glass Tempered Bh 700,000.00
110 Engsel Pintu Bh 45,000.00
111 Engsel Tanam Bh 400,000.00
112 Kunci Tanam Pintu 2x putar Bh 200,000.00
113 Kunci Tanam Pintu Glass Tempered Bh 250,000.00
114 Grendel Pintu Bh 35,000.00
115 Pintu Metal Plate + Rangka set 1,500,000.00
116 Pintu Metal+ Rangka set 15,000,000.00
117 Pintu Fiber + Rangka set 400,000.00
118 Grendel Jendela bh 27,500.00
119 Engsel Jendela Bh 35,000.00
120 Hak Angin + Engsel Bh 32,500.00
121 Sekerup Fixer m 12,500.00
122 Sealant m 25,000.00
123 Profil Kaca Aluminium buah 10,000.00
124 Lis Profil Tube 50,000.00
125 Pas. Aluminium Composite Panel m2 750,000.00
126 Pas. Double Aluminium Composite Pa m2 850,000.00
127 Sewa Mesin Las Jam 40,000.00
128 Pengelasan cm 5,000.00
129 Closet duduk Ex. Toto unit 2,000,000.00
130 Closet Jongkok Ex. Toto unit 1,500,000.00
131 Lavatory unit 3,634,800.00
132 Papper holder unit 320,000.00
133 Shoap Holder unit 73,000.00
134 Shower Head unit 1,524,000.00
135 Jet washer unit 400,000.00
136 Floor drain unit 50,000.00
137 Roof drain dia. 2" cash iron unit 62,000.00
138 Urinoir unit 1,700,000.00
139 Divider unit 850,000.00
140 Grab Bar unit 1,189,200.00
141 Kran Air unit 385,000.00
142 Cermin 6 mm unit 300,000.00
143 Meja wastafel fin….. unit 2,400,000.00
144 Profil Aluminium lebar 8 cm m' 50,000.00
145 Pipa Galvanized Iron Medium dia 3/4" m' 40,000.00
146 Pipa Galvanized Iron Medium dia 1/2" m' 27,500.00
147 Pipa Galvanized dia 2,5" m' 75,000.00
148 Reng Canal m' 45,000.00
149 Pipa PVC AW dia 3" m' 34,000.00
150 Pipa PVC AW dia 2" m' 25,000.00
151 Knee GIV dia 3/4" bh 20,000.00
152 Tee GIV dia 3/4" bh 20,000.00
153 Knee GIV dia 1/2" bh 15,000.00
154 Tee GIV dia 1/2" bh 15,000.00
155 Knee PVC dia 3" bh 25,000.00
156 Tee PVC dia 3" bh 25,000.00
157 Knee PVC dia 2" bh 22,000.00
158 Tee PVC dia 2" unit 22,000.00
159 Tangki Air Stainless Stell Kap. 1000 Lt bh 3,500,000.00
160 Septik Tank dan Peresapan Ls 6,325,000.00
161 Instalasi Penerangan/Wall Fan/Air Cu titik 175,000.00
162 Instalasi Stop Kontak/ceiling fan/Ax titik 180,000.00
163 Panel MCB unit 700,000.00
164 Panel KWH PLN unit 9,500,000.00
165 Panel unit 8,000,000.00
166 Lampu TL 1 x 18 watt unit 85,000.00
167 Recessed Mounted Emergency 2xTD buah 32,000.00
168 Lampu Down Light 18 W buah 35,000.00
169 Barret Lamp 18 W Unit 156,900.00
170 Single Swict buah 40,000.00
171 Double Swict buah 45,000.00
172 Triple Swict buah 50,000.00
173 Four Swict buah 55,000.00
174 Stop Kontak buah 35,000.00
175 Grounding System Kelistrikan buah 9,300,000.00
176 Grounding & Pertanahan buah 9,450,000.00
177 Klem Tembok buah 5,750.00
178 Kepala Penangkal Petir unit 23,000,000.00
179 Coaxial 35 mm2 penghantar turun m m 258,750.00
180 BC 35 mm2 penghantar turun menuju m 212,750.00
181 Terminal Pemeriksaan unit 1,725,000.00
182 Grounding System max. 2 ohm ( Pent unit 2,300,000.00
183 Bak Kontrol ; uk. 40 x 40 40 cm unit 977,500.00
184 Klem Tembok bh 5,750.00
185 Fire Extinguisher 6 Kg Ls 1,740,000.00
186 Testing & Commissioning Ls 8,625,000.00
187 Wallt Fan 1.04 1100 Cfm unit 3,000,000.00
188 Exhaust Fan 1.04 1100 Cfm unit 5,867,000.00
189 Pengadaan/Pemasangan dudukan indoounit 318,000.00
190 Pengadaan/Pemasangan dudukan outdounit 629,990.00
191 BJLS 100 (Ducting BJLS lengkap Isolasi m 1,611,000.00
192 BJLS 80 (Ducting BJLS lengkap Isolasi m 880,000.00
193 BJLS 60 (Ducting BJLS lengkap Isolasi m 766,800.00
194 Return Air Grille 900 x 600 mm bh 760,000.00
195 Volume Damper 900 x 600 mm bh 1,085,000.00
196 Flexible duct dia. 10 inch LS 16,000,000.00
197 Plenum Box Return ( isolasi luar dan set 4,047,840.00
198 Pipa BSP - SCH 40 Pipa diameter : m 2,050,650
199 Pipa BSP - SCH 40 Pipa diameter : m 1,493,962
200 Pipa BSP - SCH 40 Pipa diameter : m 1,101,465
201 Pipa diameter : 40 mm (1.5") m 515,700
202 Kotak Hydrant termasuk : Landing Va Set' 5,000,000
203 Tee 4' x 4' bsc 40 (dia=100x100) bh 313,950
204 Tee 4' x 3' bsc 40 (di 80 x 80) bh 231,335
205 Tee 3' x 1.5' bsc 40 (dia 80 x 40) bh 143,100
206 Knee BSC 40 dia 100 bh 148,230
207 Knee BSC 40 dia 80 bh 98,820
208 Knee BSC 40 dia 65 bh 66,960
209 Reduser 100 x 80 bh 60,345
210 Reduser 80 x 65 bh 36,045
211 Pemadam api Ringan Jenis Serbuk Hall bh 693,000
212 Pemadam api Ringan Jenis Serbuk Hall bh 1,350,000
213 Radio Tuner/AM-FM Tuner unit 1,150,000.00
214 Compact Disk Player/MP3 Player unit 2,875,000.00
215 Paging + Chime unit 2,472,500.00
216 Power Amplifier, 300 W unit 7,475,000.00
217 Speaker Selector unit 2,875,000.00
218 Rack Equipment, c/w Power Supply 22 lot 4,025,000.00
219 MDF, Kabel Distribusi, dll unit 3,220,000.00
220 TBS - 10 pairs unit 517,500.00
221 Ceilling Speaker, 3 Watt unit 168,750.00
222 Instalasi Ceilling Speaker ttk 258,750.00
223 Volume Control unit 300,000.00
224 Instalasi Volume Control ttk 258,750.00
225 P/T/Z Controler unit 8,837,031.25
226 Triplex DVR+CDRW+HDD 320 GB unit 21,275,000.00
227 TV Monitor unit 3,162,500.00
228 MDF, Kabel Distribusi, dll lot 9,315,000.00
229 Terminal Box unit 1,187,500.00
230 Dome Camera Colour 1/3" built-in fi unit 3,162,500.00
231 Instalasi kabel distribusi dari kamera ke :
- Central CCTV : Coaxial Cable RG-6 ttk 1,062,500.00
232 Instalasi kabel power dari kamera ke :
- PP-CCTV : NYM 3 x 2,5 mm2 + uPVC ttk 343,750.00
233 Terminal Box Telepon TBTP.S unit 7,475,000.00
234 Outlet telepon unit 155,250.00
235 Outlet data unit 178,250.00
236 Hand Set/Pesawat Telepon unit 155,250.00
237 Instalasi outlet telepon ttk 320,735.00
238 Instalasi outlet Data ttk 486,565.00
239 Anuniciator 24 Zone set 4,025,000.00
240 TB Fire Alarm unit 14,375,000.00
241 TBFA Twisted Shieled 2 x AWG 18 mtr 23,125.00
242 NYMHY 2 x 2,5 mm2 mtr 23,125.00
243 Heat Detector ROR (Rate of Rise Dete unit 74,750.00
244 Fixed Heat Detector unit 175,000.00
245 End Of Line Resistor unit 96,720.00
246 Smoke Detector unit 345,000.00
247 Manual Push Button unit 66,125.00
248 Remote Indicator Lamp unit 66,125.00
249 Alarm Bell unit 224,250.00
250 Break Glass unit 402,500.00
251 Instalasi Detector ttk 258,750.00
252 Instalasi bell + indicator lamp ttk 258,750.00
253 Instalasi Flow Switch ttk 258,750.00
1 Pekerja OH Rp 64,700.00 0.250 Rp 16,175.00
2 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Harga Satuan Rp 17,330.00

8 Anl. SNI 1M3 Urugan tanah Alas Lantai


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Tanah urug M3 Rp 56,400.00 1.200 Rp 67,680.00
Jumlah A Rp 67,680.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.500 Rp 32,350.00
2 Mandor OH Rp 77,000.00 0.050 Rp 3,850.00
Jumlah B Rp 36,200.00
Harga Satuan A+B Rp 103,880.00

9 Anl. SNI 1M3 Urugan Pasir Alas Pondasi Batu Kali


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
Harga Satuan A+B Rp 253,784.00

10 Anl. SNI 1M3 Urugan Pasir Alas Lantai


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
Harga Satuan A+B Rp 253,784.00

11 Anl. SNI 1M3 Urugan Pasir Alas Pondasi


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
DAFTAR HARGA SATUAN DAN UPAH KERJA

Nama : ANDI NUR ALAN


Stambuk : E3B1 13 042
Judul Tugas Akhir : Perancangan Kantor Badan Pertanahan Nasional di Kabupaten Konawe
Tahun : 2016

NO. URAIAN JENIS TENAGA/BAHAN SATUAN HARGA


(Rp)
1 2 3 4
A. UPAH KERJA
1 Mandor OH Rp 77,000.00
2 Kepala Tukang OH Rp 97,400.00
3 Tukang listrik OH Rp 83,490.00
4 Tukang kayu OH Rp 83,490.00
5 Tukang batu OH Rp 83,490.00
6 Tukang besi OH Rp 83,490.00
7 Tukang cat OH Rp 83,490.00
8 Tukang cat OH Rp 83,490.00
9 Tukang gypsum OH Rp 83,490.00
10 Tukang Pipa OH Rp 83,490.00
11 Pekerja OH Rp 64,700.00

B. BAHAN DASAR
1 Tanah urug M3 Rp 56,400.00
2 Pasir urug M3 Rp 194,670.00
3 Pasir pasangan (PP) M3 Rp 236,740.00
4 Pasir beton M3 Rp 236,740.00
5 Batu gunung M3 Rp 112,200.00
6 Batu bata Bh Rp 750.00
7 Batu Split 2x3 M3 Rp 230,000.00
8 Batu Split 1x2 M3 Rp 260,000.00
8 Buis beton dia 20 cm panjang 1 m M1 Rp 50,000.00
9 Semen portland (PC) tonasa Kg Rp 1,692.00
10 Semen warna Kg Rp 22,900.00
11 Semen putih Kg Rp 1,675.00
12 Minyak Bekisting Ltr Rp 11,400.00
13 Air Ltr Rp 175.00
14 Bahan bakar solar Ltr Rp 11,400.00
15 Kapur Tonasa Kg Rp 12,200.00
16 Paving Block Internusa 10,5 x 21 x 8 M2 Rp 120,000.00

C. BAHAN LANTAI
1 Homogenous Tile 60 x 60 cm Bh Rp 73,000.00
4 Homogeneous Tile 20 x 20 cm Bh Rp 22,700.00
D. BAHAN KAYU
1 Balok kelas I ( Kayu Jati) M3 Rp 4,500,000.00
2 Papan kelas I (Kayu Jati) M3 Rp 4,702,500.00
3 Balok kayu kelas II (Kayu Kalapi) M3 Rp 4,000,000.00
4 Papan kayu kelas II (Kayu Kalapi) M3 Rp 4,000,000.00
5 Balok kayu kelas III ( Kayu Maranti ) M3 Rp 2,100,000.00
6 Papan kayu kelas III (Kayu Maranti ) M3 Rp 2,100,000.00
7 Papan bekisting Kelas IV ( Kayu Silai ) M3 Rp 2,090,000.00
8 Dolken 8 - 12 cm Btg Rp 8,000.00
10 Tripleks tebal 3 mm Lbr Rp 67,900.00
11.3 Teakwood 4 mm uk. 120 x 240 Lbr Rp 70,000.00
12.8 Formika 120 x 240 t 15 mm Lbr Rp 65,000.00
14.3 Plywood 9 mm Lbr Rp 143,000.00

E. BAHAN LANGIT-LANGIT
1 Gypsum Board 120 x 240 cm, t=9mm Lbr Rp 81,500.00
2 Gypsum Board 120 x 240 cm, t=12mm Lbr Rp 97,000.00
2 List profil gypsum M1 Rp 35,000.00
3 Wall anggel Btg Rp 12,500.00
4 Draywall screw Doz Rp 55,000.00
5 Anggel bracket Biji Rp 600.00
6 Paku ramset Doz Rp 120,000.00
7 Kawat gantung Roll Rp 500,000.00
8 Paku gypsum Kg Rp 16,700.00

F. BAHAN ATAP
1 Atap Spandek Hi-Ten Colorbond 0.4 TCT M2 Rp 203,580.00
2 Seng G. BWG 34" Bjls 2.0 mm Kk Rp 8,700.00

G. BAHAN BESI
1 Kawat beton Kg Rp 26,100.00
2 Besi beton polos dia 6-20 Kg Rp 21,000.00
3 Paku campur 5 - 12 cm Kg Rp 20,000.00
4 Paku seng Kg Rp 28,200.00
5 Paku tripleks Kg Rp 26,100.00
6 Sekrup fixser Doz Rp 1,300.00
7 Besi Hollow 20x20 mm M1 Rp 16,000.00
8 Pipa Stainless stell dia 1" M1 Rp 15,000.00
9 Pipa Stainless stell dia 2" M1 Rp 28,000.00
11 Sealent Tube Rp 35,000.00
12 Alluminium profil daun jendela M2 Rp 89,000.00
13 Pipa Giv dia 3" M1 Rp 46,400.00
14 Pipa Giv dia 4" M1 Rp 32,400.00
15 Baja Siku 70.70.7 Kg Rp 24,800.00
16 Baja C 150.50.6 Kg Rp 18,500.00
17 Beugel Bh Rp 15,000.00
18 Besi strip tebal 5 mm Kg Rp 4,000.00
21 Sekrup/Baut Kg Rp 20,600.00
22 Hollow 40x40 mm M1 Rp 17,700.00
23 Baja I 8-25 Kg Rp 8,750.00
24 1 set Pintu Besi Unit Rp 6,200,000.00
25 Rolling Door M2 Rp 430,000.00
H. BAHAN CAT
1 Cat dasar (tembok) Kg Rp 9,600.00
2 Cat Penutup (cat trembok warna) Kg Rp 24,000.00
3 Cat Penutup Anti Lumut (warna) Kg Rp 27,000.00
4 Cat Whethershiled (warna) Kg Rp 100,000.00
5 Minyak cat Ltr Rp 25,410.00
6 Lem fox/Lem kayu Kg Rp 25,410.00
7 Kuas biasa 3" Bh Rp 10,175.00
8 Kuas biasa 4" Bh Rp 15,015.00
9 Kuas roll Bh Rp 16,170.00
10 Ampelas halus Lbr Rp 3,850.00
11 Ampelas kasar Lbr Rp 3,850.00
12 Meni besi Kg Rp 15,700.00
13 Residu Kg Rp 9,515.00
14 Vernis Ltr Rp 40,000.00
15 Meni Kayu Kg Rp 16,170.00
16 Plamir Kg Rp 8,600.00

I. BAHAN PENGGANTUNG
1 Kunci tanam merek anchor 2x slag Bh Rp 82,000.00
2 Kunci tanam Kamar Mandi 1x slag Bh Rp 69,400.00
3 Kunci tanam Pintu Glass Tempered Bh Rp 250,000.00
4 Grendel tanam Bh Rp 7,500.00
5 Engsel Bh Rp 25,000.00
8 Handel Steanless Bh Rp 317,625.00
9 Door closer Bh Rp 302,500.00
10 Door stop Bh Rp 34,000.00
11 Hak Angin Allumunium Bh Rp 32,000.00
12 Flooer Hinge Bh Rp 900,000.00

J. BAHAN KACA
1 Kaca bening 5 mm M2 Rp 115,500.00
2 Cermin 5mm M2 Rp 121,000.00
3 Lem sealent Kg Rp 101,640.00
4 Karet pelapis kaca M1 Rp 10,000.00
5 Kaca Panasap 8mm M2 Rp 900,000.00
6 Kaca Tempered 12mm M2 Rp 1,640,000.00
7 Kaca Tempered 8mm M2 Rp 825,000.00
8 Kaca Tempered 6mm M2 Rp 743,000.00
9 Sealant M1 Rp 27,000.00

K. BAHAN ALLUMINIUM
1 Profil alluminium M1 Rp 90,200.00
2 Skrup fixser Bh Rp 1,300.00
3 Dreeling Kg Rp 1,000.00
4 Pintu PVC Bh Rp 290,000.00
5 Mur baut Kg Rp 35,000.00

L. BAHAN INSTALASI LISTRIK


1 Lampu TL 1 x 18 watt Bh Rp 85,000.00
2 RME 2xTDL 36W/84/220 volt Bh Rp 32,000.00
3 Lampu Down Light 18 watt Bh Rp 35,000.00
4 Instalasi Penerangan/titik lampu Titik Rp 136,200.00
5 Saklar panel kontrol Bh Rp 125,000.00
6 Single Swict Bh Rp 40,000.00
7 Double Swict Bh Rp 45,000.00
8 Triple Swict Bh Rp 50,000.00
9 Stop kontak open Ex. Clipsal Bh Rp 27,940.00
10 Sekring box Bh Rp 76,000.00
11 Panel MCB Unit Rp 800,000.00
12 Panel KWH Bh Rp 970,000.00
13 Pipa instalasi listrik M Rp 2,500.00
14 Outlet data dan telepon Bh Rp 265,000.00
14 Kabel 3 x 2.5 mm M Rp 12,535.00

M. BAHAN SANITAIR
1 Klosed Duduk Ex TOTO Bh Rp 2,200,000.00
2 Westafel ex TOTO Bh Rp 1,227,000.00
4 Urinoir Bh Rp 1,700,000.00
5 Floor drain stailess stell merk. San Ei Ex. Japan Bh Rp 30,132.00
6 Kran dia 1/2" merk. San Ei Ex. Japan Bh Rp 18,414.00
7 Kran dia 3/4" merk. San Ei Ex. Japan Bh Rp 26,565.00
8 Shoap Holder Bh Rp 73,000.00
9 Jet Washer Bh Rp 400,000.00
10 Stop kran merk. San Ei Ex. Japan Btg Rp 53,130.00
11 Pipa PVC dia 3/4" AW M1 Rp 4,950.00
12 Pipa PVC dia 1/2" AW M1 Rp 4,042.00
13 Pipa PVC dia 1" AW M1 Rp 14,647.00
14 Pipa PVC dia 2" AW M1 Rp 18,755.00
15 Pipa PVC dia 3" AW M1 Rp 25,110.00
16 Pipa PVC dia 4" AW M1 Rp 41,937.00
18 Septictank dan resapan Unit Rp 6,240,000.00
19 Tangki Air Stainless Stell Kap. 1000 Ltr Bh Rp 3,500,000.00

N. BAHAN INSTALASI KEBAKARAN


1 Heat Detector ROR Bh Rp 74,750.00
2 Smoke Detector ROR Bh Rp 345,000.00
O. BAHAN INSTALASI TATA SUARA
1 Ceiling Speaker 6 watt Bh Rp 168,750.00

N. ALAT BERAT
1 Buldozer H Rp 4,570,000.00
2 Excavator H Rp 6,250,000.00
3 Dump truck H Rp 269,000.00
ANALISA HARGA SATUAN PEKERJAAN

Nama : ANDI NUR ALAN


Stambuk : E3B1 13 042
Judul Tugas Akhir : Perancangan Kantor Badan Pertanahan Nasional di Kabupaten Konawe
Tahun : 2016

1 Anl. SNI 1 M² Membersihkan Lapangan dan Peralatan


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Alat
1 Buldozer H Rp 4,570,000.00 0.007 Rp 31,990.00
2 Excavator H Rp 6,250,000.00 0.007 Rp 43,750.00
3 Dump Truck H Rp 269,000.00 0.014 Rp 3,766.00
Jumlah A Rp 79,506.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.100 Rp 6,470.00
2 Mandor OH Rp 77,000.00 0.050 Rp 3,850.00
Jumlah B Rp 10,320.00
Harga Satuan A+B Rp 89,826.00

2 Anl. SNI 1 M1 Pagar Sementara Dari Seng Gelombang Tinggi 2 M


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Dolken kayu dia 8-10/400 cm Btg Rp 8,000.00 1.250 Rp 10,000.00
2 Seng G. BWG 34" Bjls 2.0 mm kk Rp 8,700.00 12.000 Rp 104,400.00
3 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.072 Rp 151,200.00
4 Paku biasa 2"-5" Kg Rp 20,000.00 0.060 Rp 1,200.00
Jumlah A Rp 266,800.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.400 Rp 25,880.00
2 Tukang kayu OH Rp 83,490.00 0.200 Rp 16,698.00
3 Kepala tukang OH Rp 97,400.00 0.020 Rp 1,948.00
4 Mandor OH Rp 77,000.00 0.020 Rp 1,540.00
Jumlah B Rp 46,066.00
Harga Satuan A+B Rp 312,866.00

3 Anl. SNI 1 M1 Pengukuran dan pemasangan bouwplank


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Kaso 5/7 kayu kelas III M3 Rp 2,100,000.00 0.012 Rp 25,200.00
2 Paku campur 5 - 12 cm Kg Rp 20,000.00 0.020 Rp 400.00
3 Kayu papan kelas III M3 Rp 2,100,000.00 0.007 Rp 14,700.00
Jumlah A Rp 40,300.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.100 Rp 6,470.00
2 Tukang kayu OH Rp 83,490.00 0.100 Rp 8,349.00
3 Kepala tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.005 Rp 385.00
Jumlah B Rp 16,178.00
Harga Satuan A+B Rp 56,478.00
4 Anl. SNI 1M2 Pembuatan barak kerja
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Papan kayu kelas III M3 Rp 2,100,000.00 0.012 Rp 25,200.00
2 Balok kayu kelas III M3 Rp 2,100,000.00 0.012 Rp 25,200.00
3 Paku campur 5 - 12 cm Kg Rp 20,000.00 1.200 Rp 24,000.00
4 Seng gelombang kk Rp 8,700.00 7.000 Rp 60,900.00
5 Tripleks tebal 3 mm Lbr Rp 67,900.00 1.200 Rp 81,480.00
Jumlah A Rp 216,780.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.250 Rp 16,175.00
2 Tukang kayu OH Rp 83,490.00 0.490 Rp 40,910.10
3 Kepala tukang OH Rp 97,400.00 0.050 Rp 4,870.00
4 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 62,725.10
Harga Satuan A+B Rp 279,505.10

5 Anl. SNI 1M3 Galian tanah biasa sedalam 1 m


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.750 Rp 48,525.00
2 Mandor OH Rp 77,000.00 0.045 Rp 3,465.00
Harga Satuan Rp 51,990.00

6 Anl. SNI 1M3 Galian tanah biasa sedalam 2 m


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.900 Rp 58,230.00
2 Mandor OH Rp 77,000.00 0.045 Rp 3,465.00
Harga Satuan Rp 61,695.00

7 Anl. SNI 1M3 Mengurug kembali galian


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.250 Rp 16,175.00
2 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Harga Satuan Rp 17,330.00

8 Anl. SNI 1M3 Urugan tanah Alas Lantai


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Tanah urug M3 Rp 56,400.00 1.200 Rp 67,680.00
Jumlah A Rp 67,680.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.500 Rp 32,350.00
2 Mandor OH Rp 77,000.00 0.050 Rp 3,850.00
Jumlah B Rp 36,200.00
Harga Satuan A+B Rp 103,880.00

9 Anl. SNI 1M3 Urugan Pasir Alas Pondasi Batu Kali


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
Harga Satuan A+B Rp 253,784.00

10 Anl. SNI 1M3 Urugan Pasir Alas Lantai


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
Harga Satuan A+B Rp 253,784.00

11 Anl. SNI 1M3 Urugan Pasir Alas Pondasi Alas Poer Plat
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pasir urugan M3 Rp 194,670.00 1.200 Rp 233,604.00
Jumlah A Rp 233,604.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 20,180.00
Harga Satuan A+B Rp 253,784.00

12 Anl. SNI 1M3 Memasang pondasi batu gunung, campuran 1PC : 5 Psr
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu belah 15 cm / 20 cm M3 Rp 112,200.00 1.200 Rp 134,640.00
2 Semen portland Kg Rp 1,692.00 136.000 Rp 230,112.00
3 Pasir Pasangan M3 Rp 236,740.00 0.544 Rp 128,786.56
Jumlah A Rp 493,538.56
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.500 Rp 97,050.00
2 Tukang batu OH Rp 83,490.00 0.750 Rp 62,617.50
3 Kepala tukang OH Rp 97,400.00 0.075 Rp 7,305.00
4 Mandor OH Rp 77,000.00 0.075 Rp 5,775.00
Jumlah B Rp 172,747.50
Harga Satuan A+B Rp 666,286.06

13 Anl. SNI 1M3 Memasang batu kosong


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu Belah 15 cm / 20 cm M3 Rp 112,200.00 1.200 Rp 134,640.00
2 Pasir urug M3 Rp 194,670.00 0.432 Rp 84,097.44
Jumlah A Rp 218,737.44
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.780 Rp 50,466.00
2 Tukang batu OH Rp 83,490.00 0.390 Rp 32,561.10
3 Kepala tukang OH Rp 97,400.00 0.039 Rp 3,798.60
4 Mandor OH Rp 77,000.00 0.039 Rp 3,003.00
Jumlah B Rp 89,828.70
Harga Satuan A+B Rp 308,566.14

14 Anl. SNI 1M3 Membuat Rabat Beton Lantai Bangunan


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
2 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
4 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
5 Air Ltr Rp 175.00 200 Rp 35,000.00
Jumlah A Rp 941,951.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.200 Rp 77,640.000
2 Tukang Batu OH Rp 83,490.00 0.200 Rp 16,698.000
3 Kepala tukang OH Rp 97,400.00 0.020 Rp 1,948.000
4 Mandor OH Rp 77,000.00 0.060 Rp 4,620.000
Jumlah B Rp 100,906.000
Harga Satuan A+B Rp 1,042,857.60
15 Anl. SNI 1M3 Membuat Poor Plat Beton Bertulang (150Kg Besi + Bekisting)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Papan Kayu kelas III M3 Rp 2,100,000.00 0.200 Rp 420,000.000
2 Paku campur 5 - 12 cm Kg Rp 20,000.00 1.500 Rp 30,000.000
3 Minyak bekisting Ltr Rp 11,400.00 0.400 Rp 4,560.000
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
6 Besi Beton Polos Kg Rp 21,000.00 150 Rp 3,150,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
8 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 4,549,136.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang Kayu OH Rp 83,490.00 1.300 Rp 108,537.000
4 Tukang Besi OH Rp 83,490.00 1.050 Rp 87,664.500
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 335,034.450
Harga Satuan A+B Rp 4,884,171.05
16 Anl. SNI 1M3 Membuat Lantai Kerja / Rabat beton 1 Pc : 3 Ps : 5 Krk
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
2 Pasir Pasangan M3 Rp 236,740.00 0.540 Rp 127,839.60
3 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
Jumlah A Rp 906,951.60
B. Tenaga Kerja
1 Pekerja OH Rp 81,500.00 1.200 Rp 97,800.000
2 Tukang Batu OH Rp 67,900.00 0.200 Rp 13,580.000
3 Kepala tukang OH Rp 2,100,000.00 0.020 Rp 42,000.000
4 Mandor OH Rp 2,100,000.00 0.060 Rp 126,000.000
Jumlah B Rp 279,380.000
Harga Satuan A+B Rp 1,186,331.60

17 Anl. SNI 1M3 Membuat Kolom Bertulang 50 x 50 cm ( 200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.400 Rp 840,000.00
2 Paku Campur 5 - 12 cm Kg Rp 20,000.00 4.000 Rp 80,000.00
3 Minyak bekisting Ltr Rp 11,400.00 2.000 Rp 22,800.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Pasir Beton M3 Rp 236,740.00 0.520 Rp 123,104.80
6 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.800 Rp 208,000.00
8 Plywood 9 mm Lbr Rp 143,000.00 3.500 Rp 500,500.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,580,541.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang Kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 2.100 Rp 175,329.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 451,920.450
Harga Satuan A+B Rp 7,032,462.25
18 Anl. SNI 1M3 Kolom Beton Bertulang 15 x 15 cm (200Kg + Bekisting)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu kelas III M3 Rp 2,100,000.00 0.002 Rp 4,200.00
2 Paku campur 5 - 12 cm Kg Rp 20,000.00 0.010 Rp 200.00
3 Semen portland Kg Rp 1,692.00 366.000 Rp 619,272.00
4 Minyak Bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
5 Pasir Beton M3 Rp 236,740.00 0.520 Rp 123,104.80
6 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 230,000.00 0.200 Rp 46,000.00
8 Plywood 9mm Lbr Rp 143,000.00 3.500 Rp 500,500.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 5,549,141.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang Kayu OH Rp 83,490.00 0.020 Rp 1,669.800
4 Tukang Besi OH Rp 83,490.00 0.020 Rp 1,669.800
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 142,172.550
Harga Satuan A+B Rp 5,691,314.35

19 Anl. SNI 1M3 Kolom Beton Bertulang 20 x 20 cm (200Kg + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu kelas III M3 Rp 2,100,000.00 0.400 Rp 840,000.00
2 Paku campur 5 - 12 cm Kg Rp 20,000.00 0.010 Rp 200.00
3 Semen portland Kg Rp 1,692.00 366.000 Rp 619,272.00
4 Minyak Bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
5 Pasir Beton M3 Rp 236,740.00 0.520 Rp 123,104.80
6 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 230,000.00 0.200 Rp 46,000.00
8 Plywood 9mm Lbr Rp 143,000.00 3.500 Rp 500,500.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,384,941.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang Kayu OH Rp 83,490.00 0.020 Rp 1,669.800
4 Tukang Besi OH Rp 83,490.00 0.020 Rp 1,669.800
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 142,172.550
Harga Satuan A+B Rp 6,527,114.35

20 Anl. SNI 1M3 Membuat Sloef Bertulang 25 x 50cm (200Kg Besi + Bekisting)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.270 Rp 567,000.00
2 Paku 5 cm - 12 cm Kg Rp 18,000.00 2.000 Rp 36,000.00
3 Minyak Bekisting Ltr Rp 10,900.00 2.000 Rp 21,800.00
4 Semen portland Kg Rp 1,692.00 366.000 Rp 619,272.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Pasir Beton M3 Rp 236,740.00 0.520 Rp 123,104.80
7 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
8 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.800 Rp 208,000.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,213,201.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
2 Tukang kayu OH Rp 83,490.00 1.560 Rp 130,244.400
2 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
3 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
4 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 279,208.350
Harga Satuan A+B Rp 6,492,410.15

21 Anl. SNI 1M3 Membuat Sloef Bertulang 15 x 20 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.270 Rp 567,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 2.000 Rp 40,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 366.000 Rp 619,272.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Pasir Beton M3 Rp 236,740.00 0.520 Rp 123,104.80
7 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
8 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.800 Rp 208,000.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,213,641.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.560 Rp 130,244.400
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 385,963.350
Harga Satuan A+B Rp 6,599,605.15

22 Anl. SNI 1M3 Membuat Balok uk. 25 x 50 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.320 Rp 672,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 2.000 Rp 22,800.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
7 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
8 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
9 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,431,776.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 6.350 Rp 410,845.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.333 Rp 32,434.200
6 Mandor OH Rp 77,000.00 0.318 Rp 24,486.000
Jumlah B Rp 745,369.450
Harga Satuan A+B Rp 7,177,146.05

23 Anl. SNI 1M3 Membuat Balok uk. 20 x 40 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.320 Rp 672,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
7 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
8 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
9 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,427,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 393,477.450
Harga Satuan A+B Rp 6,820,694.05

24 Anl. SNI 1M3 Membuat Balok uk. 20 x 30 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.320 Rp 672,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
7 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
8 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
9 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,427,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 393,477.450
Harga Satuan A+B Rp 6,820,694.05

25 Anl. SNI 1M3 Membuat Balok uk. 15 x 20 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.320 Rp 672,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
7 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
8 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
9 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,427,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 393,477.450
Harga Satuan A+B Rp 6,820,694.05

26 Anl. SNI 1M3 Membuat Balok uk. 15 x 15 cm (200Kg Besi + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.320 Rp 672,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
6 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
7 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
8 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
9 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,427,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.650 Rp 137,758.500
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 393,477.450
Harga Satuan A+B Rp 6,820,694.05

27 Anl. SNI 1M3 Membuat Plat Meja Westafel Mutu (150Kg Besi + Bekisting)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.180 Rp 378,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.000 Rp 60,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.200 Rp 13,680.00
4 Plywood 9mm Lbr Rp 143,000.00 1.800 Rp 257,400.00
5 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
6 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
7 Besi Beton Polos Kg Rp 21,000.00 150 Rp 3,150,000.00
8 Koral Beton M3 Rp 260,000.00 0.810 Rp 210,600.00
9 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 4,803,656.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 1.300 Rp 108,537.000
4 Tukang Besi OH Rp 83,490.00 1.050 Rp 87,664.500
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 335,034.450
Harga Satuan A+B Rp 5,138,691.05

28 Anl. SNI 1M3 Membuat Tangga Beton Mutu K200


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.250 Rp 525,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.000 Rp 60,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.200 Rp 13,680.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
6 Besi Beton Polos Kg Rp 21,000.00 200 Rp 4,200,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
8 Plywood 9 mm Lbr Rp 143,000.00 2.500 Rp 357,500.00
9 Dolken Btg Rp 8,000.00 10.000 Rp 80,000.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 6,180,756.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Tukang kayu OH Rp 83,490.00 2.300 Rp 192,027.000
4 Tukang Besi OH Rp 83,490.00 1.400 Rp 116,886.000
5 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
6 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 447,745.950
Harga Satuan A+B Rp 6,628,502.55

29 Anl. SNI 1M3 Membuat Plat Lantai T.12 cm (150Kg Besi + Bekisting)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.140 Rp 294,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
6 Besi Beton Polos Kg Rp 21,000.00 150 Rp 3,150,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
8 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
9 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 4,999,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
4 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 138,832.950

Harga Satuan A+B Rp 5,138,049.55

30 Anl. SNI 1M3 Membuat Plat Lantai T.10 cm (150Kg + Bekisting)


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Balok Kayu Kelas III M3 Rp 2,100,000.00 0.140 Rp 294,000.00
2 Paku 5 cm - 12 cm Kg Rp 20,000.00 3.200 Rp 64,000.00
3 Minyak bekisting Ltr Rp 11,400.00 1.600 Rp 18,240.00
4 Semen portland Kg Rp 1,692.00 336.000 Rp 568,512.00
5 Pasir Beton M3 Rp 236,740.00 0.540 Rp 127,839.60
6 Besi Beton Polos Kg Rp 21,000.00 150 Rp 3,150,000.00
7 Koral Beton (Maks. 30mm) M3 Rp 260,000.00 0.810 Rp 210,600.00
8 Plywood 9 mm Lbr Rp 143,000.00 2.800 Rp 400,400.00
9 Dolken Btg Rp 8,000.00 16.000 Rp 128,000.00
10 Air Ltr Rp 175.00 215 Rp 37,625.00
Jumlah A Rp 4,999,216.60
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.650 Rp 106,755.000
2 Tukang Batu OH Rp 83,490.00 0.275 Rp 22,959.750
3 Kepala tukang OH Rp 97,400.00 0.028 Rp 2,727.200
4 Mandor OH Rp 77,000.00 0.083 Rp 6,391.000
Jumlah B Rp 138,832.950
Harga Satuan A+B Rp 5,138,049.55

31 Anl. SNI 1 Bh Pemasangan bak kontrol


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu gunung M3 Rp 112,200.00 0.135 Rp 15,147.00
2 Semen portland Kg Rp 1,692.00 9.120 Rp 15,431.04
3 Koral Beton/Suplit M3 Rp 230,000.00 0.120 Rp 27,600.00
4 Pasir pasangan M3 Rp 236,740.00 0.184 Rp 43,560.16
Jumlah A Rp 101,738.20
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.216 Rp 13,975.20
2 Tukang batu OH Rp 83,490.00 0.072 Rp 6,011.28
3 Kepala Tukang OH Rp 97,400.00 0.072 Rp 7,012.80
4 Mandor OH Rp 77,000.00 0.108 Rp 8,316.00
Jumlah B Rp 35,315.28
Harga Satuan A+B Rp 137,053.48

32 Anl. SNI 1M1 Mengerjakan saluran keliling bangunan diplaster + dilicin


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu Gunung M3 Rp 112,200.00 0.132 Rp 14,810.40
2 Semen portland Kg Rp 1,692.00 0.571 Rp 966.13
3 Pasir pasangan M3 Rp 236,740.00 0.086 Rp 20,359.64
Jumlah A Rp 36,136.17
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.598 Rp 38,690.60
2 Tukang batu OH Rp 83,490.00 0.279 Rp 23,293.71
3 Kepala Tukang OH Rp 97,400.00 0.027 Rp 2,629.80
4 Mandor OH Rp 77,000.00 0.220 Rp 16,940.00
Jumlah B Rp 81,554.11
Harga Satuan A+B Rp 117,690.28

33 Anl. SNI 1M2 Memasang dinding bata merah tebal 1/2 bata cam. 1 Pc : 3 PP
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu bata Bh Rp 750.00 70.000 Rp 52,500.00
2 Semen portland Kg Rp 1,692.00 14.370 Rp 24,314.04
3 Pasir pasangan M3 Rp 236,740.00 0.040 Rp 9,469.60
Jumlah A Rp 86,283.64
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Tukang batu OH Rp 83,490.00 0.100 Rp 8,349.00
3 Kepala Tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Jumlah B Rp 29,888.00
Harga Satuan A+B Rp 116,171.64

34 Anl. SNI 1M2 Memasang dinding bata merah tebal 1/2 bata cam. 1 Pc : 5 PP
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Batu bata Bh Rp 750.00 70.000 Rp 52,500.00
2 Semen portland Kg Rp 1,692.00 9.680 Rp 16,378.56
3 Pasir pasangan M3 Rp 236,740.00 0.045 Rp 10,653.30
Jumlah A Rp 79,531.86
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Tukang batu OH Rp 83,490.00 0.100 Rp 8,349.00
3 Kepala Tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Jumlah B Rp 29,888.00
Harga Satuan A+B Rp 109,419.86

35 Anl. SNI 1M2 Memasang plesteran, campuran 1 PC : 3 PP, tebal 15 mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Semen portland Kg Rp 1,692.00 7.776 Rp 13,156.99
2 Pasir pasangan M3 Rp 236,740.00 0.023 Rp 5,445.02
Jumlah A Rp 18,602.01
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Tukang batu OH Rp 83,490.00 0.150 Rp 12,523.50
3 Kepala Tukang OH Rp 97,400.00 0.015 Rp 1,461.00
4 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Jumlah B Rp 34,549.50
Harga Satuan A+B Rp 53,151.51

36 Anl. SNI 1M2 Memasang plesteran, campuran 1 PC : 5 PP, tebal 15 mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Semen portland Kg Rp 1,692.00 5.184 Rp 8,771.33
2 Pasir pasangan M3 Rp 236,740.00 0.026 Rp 6,155.24
Jumlah A Rp 14,926.57
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Tukang batu OH Rp 83,490.00 0.150 Rp 12,523.50
3 Kepala Tukang OH Rp 97,400.00 0.015 Rp 1,461.00
4 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Jumlah B Rp 34,549.50
Harga Satuan A+B Rp 49,476.07

37 Anl. SNI 1M2 Memasang Plesteran Beton, campuran 1 PC : 5 PP, tebal 15 mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Semen portland Kg Rp 1,692.00 5.184 Rp 8,771.33
2 Pasir pasangan M3 Rp 236,740.00 0.026 Rp 6,155.24
Jumlah A Rp 14,926.57
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.300 Rp 19,410.00
2 Tukang batu OH Rp 83,490.00 0.150 Rp 12,523.50
3 Kepala Tukang OH Rp 97,400.00 0.015 Rp 1,461.00
4 Mandor OH Rp 77,000.00 0.015 Rp 1,155.00
Jumlah B Rp 34,549.50
Harga Satuan A+B Rp 49,476.07

38 Anl. SNI 1M2 Mengerjakan acian tembok 1 PC : 8 kapur


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Cemen portland Kg Rp 1,692.00 3.250 Rp 5,499.00
2 Kapur tonasa Kg Rp 12,200.00 0.500 Rp 6,100.00
3 Amplas Lbr Rp 3,850.00 0.500 Rp 1,925.00
Jumlah A Rp 13,524.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.200 Rp 12,940.00
2 Tukang batu OH Rp 83,490.00 0.100 Rp 8,349.00
3 Kepala Tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.010 Rp 770.00
Jumlah B Rp 23,033.00
Harga Satuan A+B Rp 36,557.00

39 Anl. SNI 1M2 Pasang lantai Homogeneous Tile ukuran 80 x 80 cm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Homogeneous Tile 80 x 80 Bh Rp 138,333.33 3.100 Rp 428,833.33
2 Semen portland Kg Rp 1,692.00 9.600 Rp 16,243.20
3 Pasir Pasangan M3 Rp 236,740.00 0.045 Rp 10,653.30
4 Semen warna Kg Rp 22,900.00 1.300 Rp 29,770.00
Jumlah A Rp 485,499.83
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.240 Rp 15,528.00
2 Tukang batu OH Rp 83,490.00 0.120 Rp 10,018.80
3 Kepala Tukang OH Rp 97,400.00 0.012 Rp 1,168.80
4 Mandor OH Rp 77,000.00 0.012 Rp 924.00
Jumlah B Rp 27,639.60
Harga Satuan A+B Rp 513,139.43

40 Anl. SNI 1M2 Pasang lantai Homogeneous Tile 20 x 20 cm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Tegel keramik 20 x 20 Anti Bh Rp 22,700.00 20.000 Rp 454,000.00
2 Semen portland Kg Rp 1,692.00 8.190 Rp 13,857.48
3 Pasir Pasangan M3 Rp 236,740.00 0.018 Rp 4,261.32
4 Semen warna Kg Rp 22,900.00 1.940 Rp 44,426.00
Jumlah A Rp 516,544.80
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.250 Rp 16,175.00
2 Tukang batu OH Rp 83,490.00 0.125 Rp 10,436.25
3 Kepala Tukang OH Rp 97,400.00 0.013 Rp 1,266.20
4 Mandor OH Rp 77,000.00 0.013 Rp 1,001.00
Jumlah B Rp 28,878.45
Harga Satuan A+B Rp 545,423.25

41 Anl. SNI 1M1 Pasangan Kusen pintu dan jendela alluminium


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Kusen Allumunium M1 Rp 90,200.00 1.100 Rp 99,220.00
2 Skrup fixer Bh Rp 1,300.00 2.000 Rp 2,600.00
3 Sealent Tube Rp 35,000.00 0.060 Rp 2,100.00
Jumlah A Rp 103,920.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.043 Rp 2,782.10
2 Tukang besi konstruksi OH Rp 83,490.00 0.043 Rp 3,590.07
3 Kepala tukang OH Rp 97,400.00 0.004 Rp 389.60
4 Mandor OH Rp 77,000.00 0.002 Rp 154.00
Jumlah B Rp 6,915.77
Harga Satuan A+B Rp 110,835.77

42 Anl. SNI 1M2 membuat dan memasang 1m2 daun pintu panel kayu kelas II
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Papan Kayu Kelas II M3 Rp 4,000,000.00 0.020 Rp 80,000.00
2 Lem kayu Kg Rp 25,410.00 0.500 Rp 12,705.00
Jumlah A Rp 92,705.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.800 Rp 51,760.00
2 Tukang kayu OH Rp 83,490.00 1.500 Rp 125,235.00
3 Kepala tukang OH Rp 97,400.00 0.050 Rp 4,870.00
4 Mandor OH Rp 77,000.00 0.040 Rp 3,080.00
Jumlah B Rp 184,945.00
Harga Satuan A+B Rp 277,650.00

43 Anl. SNI 1M2 Pasangan Daun pintu PVC


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pintu PVC M2 Rp 290,000.00 1.000 Rp 290,000.00
Jumlah A Rp 290,000.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 1.050 Rp 67,935.00
2 Tukang besi OH Rp 83,490.00 1.050 Rp 87,664.50
3 Kepala tukang OH Rp 97,400.00 0.105 Rp 10,227.00
4 Mandor OH Rp 77,000.00 0.050 Rp 3,850.00
Jumlah B Rp 169,676.50
Harga Satuan A+B Rp 459,676.50

44 Anl. 1 m2 Rangka baja ringan


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Main Truss C.75-75 m1 Rp 15,000.00 2.800 Rp 42,000.00
2 Roof Bottom/Reng R.33 - 0.45 m1 Rp 8,500.00 5.100 Rp 43,350.00
3 Self Drilling Screw dia 6 x 20 m Buah Rp 400.00 25.000 Rp 10,000.00
4 Self Drilling Screw dia 4 x 16 m Buah Rp 350.00 35.000 Rp 12,250.00
5 Dynabol dia 12 x 120 mm Buah Rp 1,500.00 1.000 Rp 1,500.00
Jumlah A Rp 109,100.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.060 Rp 3,882.00
2 Mandor OH Rp 77,000.00 0.030 Rp 2,310.00
3 Kepala Tukang OH Rp 97,400.00 0.060 Rp 5,844.00
4 Tukang Besi OH Rp 83,490.00 0.060 Rp 5,009.40
Jumlah B Rp 17,045.40
Harga Satuan A+B Rp 126,145.40
45 Anl. 1M2 Pekerjaan Pasang Atap Ssakura roof
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Atap zincalume (Sakura Roof) Lembar Rp 36,500.00 1.620 Rp 59,130.00
2 Paku sakura Kg Rp 26,100.00 0.020 Rp 522.00
Jumlah A Rp 59,652.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.200 Rp 12,940.00
2 Tukang besi OH Rp 83,490.00 1.000 Rp 83,490.00
3 Kepala Tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.001 Rp 77.00
Jumlah B Rp 97,481.00
Harga Satuan A+B Rp 157,133.00

46 Anl. SNI 1 M1 Pekerjaan Listplank


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 (Nusa Plank 30 x 405 cm) Kg Rp 8,750.00 0.0100 Rp 87.50
2 Sekrup/Baut Kg Rp 20,600.00 0.0600 Rp 1,236.00
2 Meni Besi Kg Rp 15,700.00 0.100 Rp 1,570.00
Jumlah A Rp 2,893.50
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.100 Rp 6,470.00
2 Tukang kayu OH Rp 83,490.00 0.200 Rp 16,698.00
3 Kepala Tukang OH Rp 97,400.00 0.020 Rp 1,948.00
4 Mandor OH Rp 77,000.00 0.005 Rp 385.00
Jumlah B Rp 25,501.00
Harga Satuan A+B Rp 28,394.50

47 Anl. SNI 1M2 Pasang rangka plafond gypsum board


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Hollow 40x40 mm M1 Rp 17,700.00 0.625 Rp 11,062.50
3 Wall angel Btg Rp 12,500.00 0.359 Rp 4,487.50
4 Draywall screw Dos Rp 55,000.00 0.024 Rp 1,320.00
5 Kawat gantung Roll Rp 500,000.00 0.004 Rp 2,000.00
6 Paku ramset Dos Rp 120,000.00 0.018 Rp 2,160.00
7 Angel bracket Biji Rp 600.00 0.960 Rp 576.00
Jumlah A Rp 21,606.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.100 Rp 6,470.00
2 Tukang gypsum OH Rp 83,490.00 0.050 Rp 4,174.50
3 Kepala Tukang OH Rp 97,400.00 0.050 Rp 4,870.00
4 Mandor OH Rp 77,000.00 0.005 Rp 385.00
Jumlah B Rp 15,899.50
Harga Satuan A+B Rp 37,505.50

48 Anl. SNI 1M2 Pasang langit-langit gypsum board Uk. 120 x 60 cm T=9mm
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Gypsum board Lbr Rp 81,500.00 0.364 Rp 29,666.00
2 Paku skrup fixser Dos Rp 1,300.00 0.110 Rp 143.00
Jumlah A Rp 29,809.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.100 Rp 6,470.00
2 Tukang gypsum OH Rp 83,490.00 0.050 Rp 4,174.50
3 Kepala Tukang OH Rp 97,400.00 0.050 Rp 4,870.00
4 Mandor OH Rp 77,000.00 0.005 Rp 385.00
Jumlah B Rp 15,899.50
Harga Satuan A+B Rp 45,708.50

49 Anl. SNI 1M1 Pasang list plafond gypsum board


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 List Gypsum Profil m1 Rp 4,500.00 1.050 Rp 4,725.00
2 Skrup Kg Rp 42,500.00 0.010 Rp 425.00
Jumlah A Rp 5,150.00
B. Tenaga Kerja
1 Pekerja OH Rp 1,675.00 0.100 Rp 167.50
2 Tukang gypsum OH Rp 1,692.00 0.050 Rp 84.60
3 Kepala Tukang OH Rp 236,740.00 0.050 Rp 11,837.00
4 Mandor OH Rp 194,670.00 0.005 Rp 973.35
Jumlah B Rp 13,062.45
Harga Satuan A+B Rp 18,212.45

50 Anl. Memasang 1 Buah pasang kunci tanam kaca stainless stell


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kunci tanam kaca Bh Rp 250,000.00 1.000 Rp 250,000.00
2 Perlengkapan + Pekerja 30% Rp 75,000.00 1.000 Rp 75,000.00
Jumlah A Rp 325,000.00
Harga Satuan Rp 325,000.00

51 Anl. Memasang 1 Buah pasang engsel pintu aluminium


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Engsel pintu alluminium Bh Rp 25,000.00 1.000 Rp 25,000.00
2 Perlengkapan + Pekerja 30% Rp 7,500.00 1.000 Rp 7,500.00
Jumlah A Rp 32,500.00
Harga Satuan Rp 32,500.00

52 Anl. Memasang 1 Buah pasang engsel pintu panel


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Engsel Bh Rp 25,000.00 1.000 Rp 25,000.00
2 Perlengkapan + Pekerja 30% Rp 7,500.00 1.000 Rp 7,500.00
Jumlah A Rp 32,500.00
Harga Satuan Rp 32,500.00

53 Anl. Memasang 1 Buah pasang kunci tanam biasa


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kunci tanam biasa Bh Rp 82,000.00 1.000 Rp 82,000.00
2 Perlengkapan + Pekerja 30% Rp 24,600.00 1.000 Rp 24,600.00
Jumlah A Rp 106,600.00
Harga Satuan Rp 106,600.00

54 Anl. Memasang 1 Buah pasang kunci tanam biasa kamar mandi


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kunci tanam kamar mandi Bh Rp 69,400.00 1.000 Rp 69,400.00
2 Perlengkapan + Pekerja 30% Rp 20,820.00 1.000 Rp 20,820.00
Jumlah A Rp 90,220.00
Harga Satuan Rp 90,220.00

55 Anl. Memasang 1 Buah pasang engsel jendela & ventilasi kaca aluminium
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Engsel jendela kc. Alluminium Bh Rp 25,000.00 1.000 Rp 25,000.00
2 Perlengkapan + Pekerja 30% Rp 7,500.00 1.000 Rp 7,500.00
Jumlah A Rp 32,500.00
Harga Satuan Rp 32,500.00

56 Anl. Memasang 1 Buah pasang grendel jendela/ventilasi


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Grendel jendela Bh Rp 7,500.00 1.000 Rp 7,500.00
2 Perlengkapan + Pekerjaan 30% Rp 2,250.00 1.000 Rp 2,250.00
Jumlah A Rp 9,750.00
Harga Satuan Rp 9,750.00

57 Anl. SNI 1M2 Pengecetan tembok (1 lap. plamir, 1 lap. cat dasar, 2 lap. cat penutup)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Plamir Kg Rp 8,600.00 0.100 Rp 860.00
2 Cat dasar Kg Rp 9,600.00 0.100 Rp 960.00
3 Cat penutup 2x Kg Rp 24,000.00 0.360 Rp 8,640.00
Jumlah A Rp 10,460.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.020 Rp 1,294.00
2 Tukang cat OH Rp 83,490.00 0.063 Rp 5,259.87
3 Kepala Tukang OH Rp 97,400.00 0.006 Rp 584.40
4 Mandor OH Rp 77,000.00 0.003 Rp 231.00
Jumlah B Rp 7,369.27
Harga Satuan A+B Rp 17,829.27

58 Anl. SNI 1M2 Pengecetan plafond ( lap. cat dasar, 2 lap. cat penutup)
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Plamir Kg Rp 8,600.00 0.150 Rp 1,290.00
2 Cat dasar Kg Rp 9,600.00 0.170 Rp 1,632.00
3 Cat penutup 2x Kg Rp 24,000.00 0.260 Rp 6,240.00
Jumlah A Rp 9,162.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.070 Rp 4,529.00
2 Tukang cat OH Rp 83,490.00 0.009 Rp 751.41
3 Kepala Tukang OH Rp 97,400.00 0.006 Rp 584.40
4 Mandor OH Rp 77,000.00 0.003 Rp 231.00
Jumlah B Rp 6,095.81
Harga Satuan A+B Rp 15,257.81

59 Anl. Memasang 1 Buah kloset Duduk


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kloset Duduk Bh Rp 2,200,000.00 1.000 Rp 2,200,000.00
2 Perlengkapan + Pekerja 30% Rp 660,000.00 1.000 Rp 660,000.00
Jumlah A Rp 2,860,000.00
Harga Satuan Rp 2,860,000.00

60 Anl. Memasang 1 Buah Washtafel


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Washtafel Bh Rp 1,227,000.00 1.000 Rp 1,227,000.00
2 Perlengkapan + Pekerja 30% Rp 368,100.00 0.180 Rp 66,258.00
3 Semen portland Kg Rp 1,692.00 6.000 Rp 10,152.00
4 Pasir pasang M3 Rp 236,740.00 0.010 Rp 2,367.40
Jumlah A Rp 1,305,777.40
Harga Satuan Rp 1,305,777.40

61 Anl. Memasang 1 Buah Urinoir


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Urinoir Ex. Toto Bh Rp 1,700,000.00 1.000 Rp 1,700,000.00
2 Perlengkapan + Pekerja 30% Rp 510,000.00 0.180 Rp 91,800.00
3 Semen portland Kg Rp 1,692.00 6.000 Rp 10,152.00
Jumlah A Rp 1,801,952.00
Harga Satuan Rp 1,801,952.00
62 Anl. Memasang 1 buah floor drain
No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Floor drain Bh Rp 30,132.00 1.000 Rp 30,132.00
2 Perlengkapan + Pekerja 30% Rp 9,039.60 1.000 Rp 9,039.60
Jumlah A Rp 39,171.60
Harga Satuan Rp 39,171.60

63 Anl. Memasang 1 buah roof drain


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 roof drain Bh Rp 30,132.00 1.000 Rp 30,132.00
2 Perlengkapan + Pekerja 30% Rp 9,039.60 1.000 Rp 9,039.60
Jumlah A Rp 39,171.60
Harga Satuan A+B Rp 39,171.60

64 Anl. Memasang 1 buah kran diameter 3/4" atau 1/2"


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Kran air Bh Rp 26,565.00 1.000 Rp 664.13
2 Seal tape Bh Rp 400,000.00 0.025 Rp 10,000.00
Jumlah A Rp 10,664.13
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.010 Rp 647.00
2 Tukang Pipa OH Rp 83,490.00 0.100 Rp 8,349.00
3 Kepala Tukang OH Rp 97,400.00 0.010 Rp 974.00
4 Mandor OH Rp 77,000.00 0.005 Rp 385.00
Jumlah B Rp 10,355.00
Harga Satuan A+B Rp 21,019.13

65 Anl. Memasang 1 buah Jet Washer


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Jet Washer Bh Rp 400,000.00 1.000 Rp 400,000.00
2 Perlengkapan + Pekerja 30% Rp 120,000.00 1.000 Rp 120,000.00
Jumlah A Rp 520,000.00
Harga Satuan Rp 520,000.00

66 Anl. Memasang 1M' pipa PVC tipe AW dia 1/2"


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pipa PVC tipe AW dia 1/2" M' Rp 4,042.00 1.200 Rp 4,850.40
2 Perlengkapan 20% Rp 808.40 0.180 Rp 145.51
Jumlah A Rp 4,995.91
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.036 Rp 2,329.20
2 Tukang Pipa OH Rp 83,490.00 0.060 Rp 5,009.40
3 Kepala Tukang OH Rp 97,400.00 0.006 Rp 584.40
4 Mandor OH Rp 77,000.00 0.002 Rp 154.00
Jumlah B Rp 8,077.00
Harga Satuan A+B Rp 13,072.91

67 Anl. Memasang 1M' pipa PVC tipe AW dia 2"


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pipa PVC tipe AW dia 2" M' Rp 18,755.00 1.200 Rp 22,506.00
2 Perlengkapan 20% Rp 3,751.00 0.180 Rp 675.18
Jumlah A Rp 23,181.18
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.036 Rp 2,329.20
2 Tukang Pipa OH Rp 83,490.00 0.060 Rp 5,009.40
3 Kepala Tukang OH Rp 97,400.00 0.006 Rp 584.40
4 Mandor OH Rp 77,000.00 0.002 Rp 154.00
Jumlah B Rp 8,077.00
Harga Satuan A+B Rp 31,258.18

68 Anl. Memasang 1M1 pipa PVC tipe AW dia 4"


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pipa PVC tipe AW dia 4" M' Rp 41,937.00 1.200 Rp 50,324.40
2 Perlengkapan 20% Rp 8,387.40 0.180 Rp 1,509.73
Jumlah A Rp 51,834.13
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.081 Rp 5,240.70
2 Tukang Pipa OH Rp 83,490.00 0.135 Rp 11,271.15
3 Kepala Tukang OH Rp 97,400.00 0.014 Rp 1,363.60
4 Mandor OH Rp 77,000.00 0.004 Rp 308.00
Jumlah B Rp 18,183.45
Harga Satuan A+B Rp 70,017.58

69 Anl. Memasang 1M1 Relling Tangga Steanless


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pipa Stainless Stell dia 2" M' Rp 28,000.00 2.320 Rp 64,960.00
2 Besi Hollow M' Rp 16,000.00 0.625 Rp 10,000.00
Jumlah A Rp 74,960.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.650 Rp 42,055.00
2 Tukang Besi OH Rp 83,490.00 0.650 Rp 54,268.50
3 Kepala Tukang OH Rp 97,400.00 0.060 Rp 5,844.00
4 Mandor OH Rp 77,000.00 0.032 Rp 2,464.00
Jumlah B Rp 104,631.50
Harga Satuan A+B Rp 179,591.50

70 Anl. Memasang 1M1 Relling Void Steanless


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Pipa Stainless Stell dia 2" M' Rp 28,000.00 2.320 Rp 64,960.00
2 Besi Hollow M' Rp 16,000.00 0.625 Rp 10,000.00
Jumlah A Rp 74,960.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.650 Rp 42,055.00
2 Tukang Besi OH Rp 83,490.00 0.650 Rp 54,268.50
3 Kepala Tukang OH Rp 97,400.00 0.060 Rp 5,844.00
4 Mandor OH Rp 77,000.00 0.032 Rp 2,464.00
Jumlah B Rp 104,631.50
Harga Satuan A+B Rp 179,591.50

71 Anl. Memasang 1M2 Paving Block tebal 8mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
A. Bahan
1 Paving Block M2 Rp 120,000.00 1.010 Rp 121,200.00
2 Pasir Urug M3 Rp 194,670.00 0.100 Rp 19,467.00
Jumlah A Rp 140,667.00
B. Tenaga Kerja
1 Pekerja OH Rp 64,700.00 0.250 Rp 16,175.00
2 Tukang Batu OH Rp 83,490.00 0.500 Rp 41,745.00
3 Kepala Tukang OH Rp 97,400.00 0.050 Rp 4,870.00
4 Mandor OH Rp 77,000.00 0.025 Rp 1,925.00
Jumlah B Rp 64,715.00
Harga Satuan A+B Rp 205,382.00

72 Anl. Memasang 1 M2 Kaca Tempered 12 mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kaca Tempered 12mm M2 Rp 1,640,000.00 1.000 Rp 1,640,000.00
2 Perlengkapan + Pekerja 30% Rp 492,000.00 1.000 Rp 492,000.00
3 Sealent M1 Rp 27,000.00 6.000 Rp 162,000.00
Jumlah A Rp 2,294,000.00
Harga Satuan Rp 2,294,000.00

73 Anl. Memasang 1 M2 Kaca Tempered 6 mm


No. Uraian Satuan Harga Satuan Indeks Jumlah Harga
1 Kaca Tempered 8mm M2 Rp 743,000.00 1.000 Rp 743,000.00
2 Perlengkapan + Pekerja 30% Rp 222,900.00 1.000 Rp 222,900.00
3 Sealent M1 Rp 27,000.00 6.000 Rp 162,000.00
Jumlah A Rp 1,127,900.00
Harga Satuan Rp 1,127,900.00

Kendari, Oktober 2016

Mengetahui: Di Buat Oleh :


DOSEN PEMBIMBING MAHASISWA D3 ARSITEKTUR

Ir. Andi Muh. Amil Andi Nur Alan


NIP. 19640807 200312 1 002 Stb. E3B1 13 042
RENCANA ANGGARAN BIAYA

Nama : ANDI NUR ALAN


Stambuk : E3B1 13 042
Judul Tugas Akhir : Perancangan Kantor Badan Pertanahan Nasional di Kabupaten Konawe
Tahun : 2016

NO. URAIAN PEKERJAAN SAT. VOL HARGA SAT. JUMLAH SAT.


(Rp) (Rp)
1 2 3 4 5 6
A. PEKERJAAN PERSIAPAN
1 Pemb. Pagar Sementara dari Seng Gel. T. 2 m M ¹ 320.00 Rp 218,906.00 Rp 70,049,920.00

2 Penyediaan Air Kerja / P3K Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00

3 Pembuatan Barak Kerja M² 120.00 Rp 279,505.10 Rp 33,540,612.00

4 Pek. Pengukuran dan Pemasangan Bowplank M ¹ 454.4 Rp 56,478.00 Rp 25,663,603.20

5 Perlengkapan Adm. & Foto Dokumentasi Ls 1.00 Rp 3,000,000.00 Rp 3,000,000.00

6 Mobilisasi/Demobilisasi Alat & Tenaga Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00

7 Papan Nama Proyek Ls 1.00 Rp 700,000.00 Rp 700,000.00

Jumlah Pekerjaan Persiapan Rp 140,454,135.20

B. PEKERJAAN TANAH DAN PASIR


1 Pekerjaan Galian Tanah Pondasi Garis M³ 286.36 Rp 51,990.00 Rp 14,888,012.37

2 Pekerjaan Galian Tanah Poor Plat M³ 332.80 Rp 104,737.05 Rp 34,856,490.24

3 Pek. Urugan Kembali Tanah Bekas Galian M³ 334.98 Rp 17,330.00 Rp 5,805,238.06

4 Pek. Urugan Tanah Alas Lantai M³ 325.46 Rp 103,880.00 Rp 33,808,784.80

5 Pek. Urugan Pasir Alas Pondasi Garis M³ 38.14 Rp 253,784.00 Rp 9,678,052.84

6 Pek. Urugan Pasir Alas Pondasi Poer Plat M³ 8.320 Rp 253,784.00 Rp 2,111,482.88

7 Pek. Urugan Pasir Alas Lantai M³ 124.85 Rp 253,784.00 Rp 31,684,678.62

Jumlah Pekerjaan Tanah dan Pasir Rp 132,832,739.81

C. PEKERJAAN BETON + BEKISTING


1 Pek. Rabat Beton Lantai Bangunan M³ 96.84 Rp 1,042,857.60 Rp 100,989,287.13

2 Pek. Poor Plat Beton Bertulang M³ 59.31 Rp 4,884,171.05 Rp 289,692,395.40

3 Pek. Rabat Beton/Lantai Kerja Bawah Pooer Plat M³ 48.26 Rp 1,186,331.60 Rp 57,247,617.69

4 Pek. Sloef Bertulang 25 x 50 cm M³ 65.00 Rp 6,492,410.15 Rp 422,006,659.75

5 Pek. Sloef Bertulang 15 x 20 cm M³ 4.10 Rp 6,599,605.15 Rp 27,045,181.90

6 Pek. Kolom beton Bertulang 50 x 50 cm M³ 139.50 Rp 7,032,462.25 Rp 981,028,483.88

7 Pek. Kolom Beton Bertulang 15 x 15cm M³ 8.51 Rp 5,691,314.35 Rp 48,404,628.55

8 Pek. Kolom Beton Bertulang 20 x 20cm M³ 4.24 Rp 6,527,114.35 Rp 27,688,019.07

9 Pek. Balok uk. 25 x 50 cm M³ 63.75 Rp 7,177,146.05 Rp 457,543,060.69

10 Pek. Balok uk. 20 x 40 cma M³ 26.88 Rp 6,820,694.05 Rp 183,340,256.06

11 Pek. Balok uk. 20 x 30 cm M³ 17.64 Rp 6,820,694.05 Rp 120,317,043.04

12 Pek. RingBalok uk. 20 x 40 cm M³ 35.04 Rp 6,820,694.05 Rp 238,997,119.51

13 Pek. RingBalok uk. 15 x 20 cm M³ 11.11 Rp 6,820,694.05 Rp 75,784,731.59

14 Pek. Plat Meja Westafel Mutu M³ 0.75 Rp 5,138,691.05 Rp 3,838,602.21

15 Pek. Tangga Beton Mutu M³ 7.77 Rp 6,628,502.55 Rp 51,479,602.20

16 Pek. Plat Lantai T.12 cm Camp. 1PC : 2Psr : 3Krl M³ 78.91 Rp 5,138,049.55 Rp 405,456,592.02

17 Pek. Plat Lantai T.10 cm Camp. 1PC : 2Psr : 3Krl M³ 47.83 Rp 5,138,049.55 Rp 245,768,940.69

Jumlah Pekerjaan Beton Rp 3,736,628,221.39

D. PEKERJAAN PEMASANGAN DAN PLESTERAN


1 Pas. Batu Kosong M³ 76.27 Rp 308,566.14 Rp 23,534,339.50

2 Pas. Pondasi Batu Gunung M³ 175.42 Rp 666,286.06 Rp 116,880,566.93

3 Pas. Dinding Batu Bata Merah 1/2 Bata (1PC : 3 PP) M² 129.00 Rp 116,171.64 Rp 14,986,141.56

4 Pas. Dinding Batu Bata Merah 1/2 Bata (1PC : 5 PP) M² 2023.20 Rp 109,419.86 Rp 221,378,041.91
5 Pek. Plesteran (1PC : 3PP) M² 258.00 Rp 53,151.51 Rp 13,713,090.10

6 Pek. Plesteran (1PC : 5PP) M² 4046.396 Rp 49,476.07 Rp 200,199,763.65

7 Pek. Acian Dinding Plesteran M² 4304.40 Rp 36,557.00 Rp 157,355,804.57

8 Pek. Pas. Lantai Homogeneous Tile 80/80 cm M² 1942.51 Rp 513,139.43 Rp 996,778,480.64

9 Pek. Pas. Lantai Homogeneous Tile 20/20 cm M² 88.80 Rp 545,423.25 Rp 48,433,584.60

10 Pek. Pas. Dinding Homogeneous Tile Km/wc 20/25 cm M² 192.12 Rp 545,423.25 Rp 104,786,714.79

11 Pek. Pas. Realing Void Stainless Stell M ¹ 107.88 Rp 166,340.00 Rp 17,944,759.20

12 Pek. Pas. Realing Tangga Stainless Stell M ¹ 279.52 Rp 179,591.50 Rp 50,199,416.08

13 Pek. Pas. Alucopan M² 542.96 Rp 647,930.25 Rp 351,801,569.19

Jumlah Pekerjaan Pemasangan dan Plesteran Rp 2,317,992,272.73

E. PEK. KUSEN DAN DAUN PINTU/JENDELA


1 Pek. Kusen Pintu dan Jendela Alluminium M ¹ 1318.10 Rp 110,835.77 Rp 146,092,628.44

2 Pek. Daun Pintu Panel M² 66.26 Rp 277,650.00 Rp 18,397,089.00

3 Pek. Pas. Glass Tempered 6mm M² 265.22 Rp 1,127,900.00 Rp 299,136,336.87

4 Pek. Pas. Glass Tempered 12mm M² 10.75 Rp 2,294,000.00 Rp 24,653,159.20

5 Pek. Daun Pintu PVC M² 19.89 Rp 459,676.50 Rp 9,142,965.59

Jumlah Pekerjaan Kusen dan Daun Pintu/Jendela Rp 497,422,179.09

F. PEKERJAAN KUDA-KUDA, ATAP DAN PLAFOND


1 Pek. Baja Ringan M² 850.25 Rp 193,160.00 Rp 164,235,062.64

2 Pek. Atap Sakura roof M² 854.36 Rp 80,962.20 Rp 69,170,654.69

3 Pek. Listplank M ¹ 156.80 Rp 101,994.48 Rp 15,992,733.68

4 Pek. Rangka Plafond Gypsum Board M² 1965.96 Rp 37,505.50 Rp 73,734,200.26

4 Pek. Pasangan Plafond Gypsum Board M² 1965.96 Rp 15,899.50 Rp 31,257,733.32

5 Pek. list Plafond Gypsum Board M ¹ 1216.70 Rp 14,712.50 Rp 17,900,698.75

Jumlah Pekerjaan Kuda-Kuda, Atap dan Plafond Rp 372,291,083.35

G. PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Pas. Kunci Tanam Pada Kaca Tempered - Stainless Stell Bh 4.00 Rp 325,000.00 Rp 1,300,000.00

2 Pas. Engsel Pintu Kaca Alluminium Model U. Uk 4" Bh 8.00 Rp 32,500.00 Rp 260,000.00

3 Pas. Engsel Pintu Panel Bh 146.00 Rp 32,500.00 Rp 4,745,000.00

4 Pas. Kunci Tanam Biasa Bh 31.00 Rp 106,600.00 Rp 3,304,600.00

5 Pas. Kunci Tanam Biasa Kamar Mandi Bh 7.00 Rp 90,220.00 Rp 631,540.00

6 Pas. Engsel Jendela & Ventilasi Alluminium H. Uk 4" Bh 123.00 Rp 32,500.00 Rp 3,997,500.00

6 Pas. Grendel Jendela & Ventilasi Bh 58.00 Rp 9,750.00 Rp 565,500.00

Jumlah Pekerjaan Penggantung dan Pengunci Rp 14,804,140.00

H. PEKERJAAN PENGECETAN
1 Pekerjaan Cat Dinding 3x Sapu M² 4304.40 Rp 17,829.27 Rp 76,744,238.47

2 Pekerjaan Cat Plafond 3x Sapu M² 1965.96 Rp 15,257.81 Rp 29,996,198.37

Jumlah Pekerjaan Pengecetan Rp 106,740,436.85

I. PEKERJAAN SANITASI
1 Pas. Klosed Duduk Bh 13.00 Rp 2,860,000.00 Rp 37,180,000.00

2 Pas. Westafel Bh 15.00 Rp 1,305,777.40 Rp 19,586,661.00

3 Pas. Floor Drain Bh 18.00 Rp 39,171.60 Rp 705,088.80

4 Pas. Roof Drain Bh 83.00 Rp 39,171.60 Rp 3,251,242.80

5 Pas. Jet Washer Bh 13.00 Rp 520,000.00 Rp 6,760,000.00

6 Pas. Urinoir Bh 9.00 Rp 1,801,952.00 Rp 16,217,568.00

7 Pas. Kran Air Bh 11.00 Rp 21,019.13 Rp 231,210.38

8 Pas. Pipa Air Bersih dia 1/2" M¹ 105.50 Rp 13,072.91 Rp 1,379,192.22

9 Pas. Pipa Disposal Cair dia 4" M¹ 101.70 Rp 70,017.58 Rp 7,120,788.09

10 Pas. Pipa Disposal Padat dia 4" M¹ 90.00 Rp 70,017.58 6,301,582.38

11 Pas. Pipa Saluran Air Hujan dia 4" M¹ 274.40 Rp 70,017.58 Rp 19,212,824.50

12 Pas. Septictank dan Peresapan Unit 2.00 Rp 6,240,000.00 Rp 12,480,000.00

Jumlah Pekerjaan Sanitasi Rp 130,426,158.16


J. PEKERJAAN ELEKTRIKAL
1 Pek. Pas. Titik Instalasi Titik 237.00 Rp 136,200.00 Rp 32,279,400.00

2 Pek. Pas. Downlight 18 W Bh 198.00 Rp 32,000.00 Rp 6,336,000.00

3 Pek. Pas. RME 2XLTLD 36W/84, 220V Bh 39.00 Rp 136,200.00 Rp 5,311,800.00

4 Pek. Pas. Single Swict Bh 23.00 Rp 27,940.00 Rp 642,620.00

5 Pek. Pas. Double Swict Bh 24.00 Rp 40,000.00 Rp 960,000.00

6 Pek. Pas. Outlet Daya 500W Bh 86.00 Rp 27,940.00 Rp 2,402,840.00

7 Pek. Pas. Kabel 2,5 mm (NYA) M¹ 1063.00 Rp 12,535.00 Rp 13,324,705.00

8 Pek. Pas. Pipa Instalasi Listrik PVC 3/8" M¹ 1063 Rp 2,500.00 Rp 2,657,500.00

9 Pek. Pas. MCB Bh 1.00 Rp 800,000.00 Rp 800,000.00

10 Pek. Pas. ROR Heat Detector Bh 71.00 Rp 74,750.00 Rp 5,307,250.00

11 Pek. Pas. ROR Smoke Detector Bh 2.00 Rp 345,000.00 Rp 690,000.00

12 Pek. Pas. Ceiling Speaker 6 W Bh 41.00 Rp 168,750.00 Rp 6,918,750.00

Jumlah Pekerjaan Elektrikal Rp 77,630,865.00

K. PEKERJAAN LAIN-LAIN
1 Pek. Saluran Keliling Bangunan M ¹ 174.1 Rp 117,690.28 Rp 20,489,878.10

2 Pek. Pembuatan Bak Kontrol Bh 20.00 Rp 137,053.48 Rp 2,741,069.60

3 Pek. Pembersihan Akhir Tapak Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00

Jumlah Pekerjaan Lain-Lain Rp 28,230,947.70

Kendari, Oktober 2016

Di Buat Oleh :
MAHASISWA D3 ARSITEKTUR

Andi nur alan


E3B1 13 042
REKAPITULASI BIAYA

Nama : ANDI NUR ALAN


Stambuk : E3B1 13 042
Judul Tugas Akhir : Perancangan Kantor Badan Pertanahan Nasional di Kabupaten Konawe
Tahun : 2016

JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp)
A. PEKERJAAN PERSIAPAN Rp 140,454,135.20
B. PEKERJAAN TANAH DAN PASIR Rp 132,832,739.81
C PEKERJAAN BETON Rp 3,736,628,221.39
D PEKERJAAN PEMASANGAN DAN PELASTERAN Rp 2,317,992,272.73
E PEK. KUSEN DAN DAUN PINTU/JENDELA Rp 497,422,179.09
F PEKERJAAN KUDA-KUDA, ATAP DAN PLAFOND Rp 372,291,083.35
G PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 14,804,140.00
H PEKERJAAN PENGECETAN Rp 106,740,436.85
I PEKERJAAN SANITASI Rp 130,426,158.16
J PEKERJAAN ELEKTRIKAL Rp 77,630,865.00
K PEKERJAAN LAIN-LAIN Rp 28,230,947.70
REAL COST Rp 7,555,453,179.26
IMB 2 % Rp 151,109,063.59
PPN 10 % Rp 755,545,317.93
PERENCANAAN 5 % Rp 377,772,658.96
PENGAWASAN 3.5 % Rp 264,440,861.27
TOTAL COST Rp 9,104,321,081.01
DIBULATKAN Rp 9,104,321,000.00

TERBILANG : Sembilan Milyar Seratus empat Juta Tiga Ratus Dua Puluh Satu Ribu Rupiah

Kendari, Oktober 2016

Mengetahui: Di Buat Oleh :


DOSEN PEMBIMBING MAHASISWA D3 ARSITEKTUR

Ir. Andi Muh. Amil Andi Nur Alan


NIP. 19640807 200312 1 002 E3B1 13 042
270 2.7

Slooef 25x40 10.00 27


1.3 18 23.4

42.66
14.508
2 59.168

33.3 6.28
25.42
37
25.6
9.6
1928

2065.2
DAFTAR ANALISA SNI
NAMA : ANDI NUR ALAN
PEKERJAAN : E3B1 13 042
LOKASI : Perencanaan Kantor Badan Pertanahan Nasional Kabu
TAHUN ANGGARAN : 2016

A PEKERJAAN PERSIAPAN

1 1 M2 PAGAR SEMENTARA DARI SENG GELOMBANG 6 KAKI

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISIEN

A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Kayu L 02 OH 0.400
3 Kepala Tukang L 03 OH 0.020
4 Mandor L 04 OH 0.020
Jumlah Tenag
B BAHAN
1 Dolken Kayu Ø 8 - 10/400 cm Batang 1.250
2 Semen Portland Kg 2.500
3 Seng Gelombang 6 Kaki Lembar 1.200
4 Pasir Beton m3 0.005
5 Koral Beton m3 0.009
6 Kayu 5/7 m3 0.072
7 Paku Biasa 2" - 5" Kg 0.060
8 Meni Besi Liter 0.450
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
2 1 M' PENGUKURAN DAN PEMASANGAN BOWPLANK

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Kayu 5/7 m3 0.012
2 Paku Biasa 2" - 3" Kg 0.020
3 Papan 3/20 Kls 3 m3 0.007
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

B PEKERJAAN TANAH DAN PASIR

1 1 M3 GALIAN TANAH BIASA SEDALAM 1M

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.750
2 Mandor L 04 OH 0.025
Jumlah Tenag
B BAHAN

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M3 GALIAN TANAH BIASA SEDALAM 2M

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.900
2 Mandor L 04 OH 0.045
Jumlah Tenag
B BAHAN

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M3 GALIAN TANAH BIASA SEDALAM 3M

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 1.050
2 Mandor L 04 OH 0.067
Jumlah Tenag
B BAHAN

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M3 PEKERJAAN URUGAN KEMBALI GALIAN TANAH

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN

A TENAGA
1 Pekerja L 01 OH 0.500
2 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M3 PEKERJAAN URUGAN DENGAN TANAH URUG

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.300
2 Mandor L 04 OH 0.010
Jumlah Tenag
B BAHAN
1 Tanah Urug m3 1.200
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 1 M3 PEKERJAAN PEMADATAN TANAH (PER 20CM)

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.500
2 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 1 M3 PEKERJAAN URUGAN DENGAN PASIR URUG

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN

A TENAGA
1 Pekerja L 01 OH 0.300
2 Mandor L 04 OH 0.010
Jumlah Tenag
B BAHAN
1 Pasir Urug m3 1.200
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

C PEKERJAAN PONDASI

1 1 M3 PEK. PASANGAN PONDASI BATU GUNUNG 1 PC: 5 PSR

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN
A TENAGA
1 Pekerja L 01 OH 1.500
2 Tukang Batu L 02 OH 0.750
3 Kepala Tukang L 03 OH 0.075
4 Mandor L 04 OH 0.075
Jumlah Tenag
B BAHAN
1 Batu Gunung Moramo m3 1.200
2 Semen Portland Kg 136.000
3 Pasir Pasang m3 0.544
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M3 PEK. PASANGAN BATU KOSONG (ANSTAMPING)

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 0.780
2 Tukang Batu L 02 OH 0.390
3 Kepala Tukang L 03 OH 0.039
4 Mandor L 04 OH 0.039
Jumlah Tenag
B BAHAN
1 Batu Gunung Moramo m3 1.200
2 Pasir Urug m3 0.432
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

D PEKERJAAN BETON

1 1 M3 PEK BETON TANPA TULANG MUTU F'C = 26.4 MPA (K300) W/C = 0.52

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 1.650
2 Tukang Batu L 02 OH 0.275
3 Kepala Tukang L 03 OH 0.028
4 Mandor L 04 OH 0.083
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 413.000
2 Pasir Beton m3 0.486
3 Krikil m3 0.756
4 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M3 PEK BETON TANPA TULANG MUTU F'C = 14.5 MPA (K175) W/C = 0.66

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.650
2 Tukang Batu L 02 OH 0.275
3 Kepala Tukang L 03 OH 0.028
4 Mandor L 04 OH 0.083
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 326.000
2 Pasir Beton m3 0.543
3 Krikil m3 0.762
4 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M3 PEK. PONDASI BETON BERTULANG (164.36Kg BESI + BEKISTING) 150cm x 150cm K300

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN

A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.262
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.200
2 Paku 5cm - 12cm Kg 1.500
3 Minyak Bekisting Liter 0.400
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M3 PEK. PONDASI BETON BERTULANG (193.32Kg BESI + BEKISTING) 100cm x 100cm K300

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN

A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.262
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.200
2 Paku 5cm - 12cm Kg 1.500
3 Minyak Bekisting Liter 0.400
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M3 PEK. SLOOF BETON BERTULANG (164.219 Kg BESI + BEKISTING) 30cm x 50cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 5.650
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.560
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.323
6 Mandor L 04 OH 0.283
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.270
2 Paku 5cm - 12cm Kg 2.000
3 Minyak Bekisting Liter 0.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
6 1 M3 PEK. SLOOF BETON BERTULANG (205.98 Kg BESI + BEKISTING) 20cm x 30cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 5.650
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.560
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.323
6 Mandor L 04 OH 0.283
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.270
2 Paku 5cm - 12cm Kg 2.000
3 Minyak Bekisting Liter 0.600
4 Besi Beton Variabel Kg 205.980
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 1 M3 PEK. SLOOF BETON BERTULANG (271.98 Kg BESI + BEKISTING) 15cm x 25cm K300

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 5.650
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.560
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.323
6 Mandor L 04 OH 0.283
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.270
2 Paku 5cm - 12cm Kg 2.000
3 Minyak Bekisting Liter 0.600
4 Besi Beton Variabel Kg 271.980
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

8 1 M3 PEK. SLOOF BETON BERTULANG (277.11 Kg BESI + BEKISTING) 15cm x 20cm K175

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 5.650
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.560
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.323
6 Mandor L 04 OH 0.283
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.270
2 Paku 5cm - 12cm Kg 2.000
3 Minyak Bekisting Liter 0.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 326.000
7 Pasir Beton m3 0.543
8 Krikil m3 0.762
9 Air Liter 215.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

9 1 M3 PEK. KOLOM BETON BERTULANG (144.88 Kg BESI + BEKISTING) 40cm x 40cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 7.050
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 2.100
5 Kepala Tukang L 03 OH 0.403
6 Mandor L 04 OH 0.353
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.400
2 Paku 5cm - 12cm Kg 4.000
3 Minyak Bekisting Liter 2.000
4 Besi Beton Variabel Kg 144.880
5 Kawat Beton Kg 4.500
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.150
11 Multiplek 6mm Lembar 3.500
12 Dolken Kayu Ø 8 - 10/400 cm Batang 20.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

10 1 M3 PEK. KOLOM BETON BERTULANG (158.74 Kg BESI + BEKISTING) 50cm x 50cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 7.050
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 2.100
5 Kepala Tukang L 03 OH 0.403
6 Mandor L 04 OH 0.353
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.400
2 Paku 5cm - 12cm Kg 4.000
3 Minyak Bekisting Liter 2.000
4 Besi Beton Variabel Kg 158.740
5 Kawat Beton Kg 4.500
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.150
11 Multiplek 6mm Lembar 3.500
12 Dolken Kayu Ø 8 - 10/400 cm Batang 20.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

11 1 M3 PEK. KOLOM BETON BERTULANG (258.83 Kg BESI + BEKISTING) 25cm x 25cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 7.050
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 2.100
5 Kepala Tukang L 03 OH 0.403
6 Mandor L 04 OH 0.353
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.400
2 Paku 5cm - 12cm Kg 4.000
3 Minyak Bekisting Liter 2.000
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 4.500
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.150
11 Multiplek 6mm Lembar 3.500
12 Dolken Kayu Ø 8 - 10/400 cm Batang 20.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

12 1 M3 PEK. KOLOM BETON BERTULANG (185.36 Kg BESI + BEKISTING) 15cm x 15cm K175

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.270
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.265
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 326.000
7 Pasir Beton m3 0.543
8 Krikil m3 0.762
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.120
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 32.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

13 1 M3 PEK. BALOK BETON BERTULANG ( 170.013 Kg BESI + BEKISTING) 30cm x 55cm K300

NO. 11/PRT/M/2013

NO URAIAN KODE SATUAN KOEFISI


EN

A TENAGA
1 Pekerja L 01 OH 6.350
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.333
6 Mandor L 04 OH 0.318
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 200.000
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.140
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 16.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

14 1 M3 PEK. BALOK BETON BERTULANG (201.37 Kg BESI + BEKISTING) 20cm x 35cm K300

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN

A TENAGA
1 Pekerja L 01 OH 6.350
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.333
6 Mandor L 04 OH 0.318
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.140
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 16.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

15 1 M3 PEK. BALOK BETON BERTULANG (205.98 Kg BESI + BEKISTING) 20cm x 30cm K300

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 6.350
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.333
6 Mandor L 04 OH 0.318
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 205.980
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.140
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 16.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

16 1 M3 PEK. BALOK BETON BERTULANG (213.06 Kg BESI + BEKISTING) 15cm x 25cm K300
NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 6.350
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.333
6 Mandor L 04 OH 0.318
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.140
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 16.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

17 1 M3 PEK. BALOK BETON BERTULANG (218.74 Kg BESI + BEKISTING) 15cm x 25cm K300

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 6.350
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.650
4 Tukang Besi L 02 OH 1.400
5 Kepala Tukang L 03 OH 0.333
6 Mandor L 04 OH 0.318
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 218.740
5 Kawat Beton Kg 3.000
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.140
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 16.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

18 1 M3 PEK. BALOK LATEI BERTULANG (190 Kg BESI + BEKISTING) 15cm x 15cm

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.290
2 Tukang Batu L 02 OH 0.033
3 Tukang Kayu L 02 OH 0.033
4 Tukang Besi L 02 OH 0.033
5 Kepala Tukang L 03 OH 0.010
6 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.003
2 Paku 5cm - 12cm Kg 0.020
3 Minyak Bekisting Liter
4 Besi Beton Variabel Kg 190.000
5 Kawat Beton Kg 0.050
6 Semen Portland Kg 5.500
7 Pasir Beton m3 0.009
8 Krikil m3 0.015
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

19 1 M3 PEK. PLAT LANTAI TEBAL 12CM (90.37 Kg BESI + BEKISTING) K300

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.265
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 90.370
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.120
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 32.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

20 1 M3 PEK. PLAT LANTAI TEBAL 10CM (113.430 Kg BESI + BEKISTING) K300

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.265
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 0.000
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 413.000
7 Pasir Beton m3 0.486
8 Krikil m3 0.756
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.120
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 32.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

21 1 M3 PEK. PLAT KANOPI BETON (150 Kg BESI + BEKISTING)

NO. 11/PRT/M/2013

KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 5.300
2 Tukang Batu L 02 OH 0.275
3 Tukang Kayu L 02 OH 1.300
4 Tukang Besi L 02 OH 1.050
5 Kepala Tukang L 03 OH 0.265
6 Mandor L 04 OH 0.265
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.320
2 Paku 5cm - 12cm Kg 3.200
3 Minyak Bekisting Liter 1.600
4 Besi Beton Variabel Kg 150.000
5 Kawat Beton Kg 2.250
6 Semen Portland Kg 326.000
7 Pasir Beton m3 0.543
8 Krikil m3 0.762
9 Air Liter 215.000
10 Kayu Kelas II Balok m3 0.120
11 Multiplek 6mm Lembar 2.800
12 Dolken Kayu Ø 8 - 10/400 cm Batang 32.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

22 1 M2 PEK. BEKISTING UNTUK SLOOF


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.520
3 Tukang Kayu L 02 OH 0.260
5 Kepala Tukang L 03 OH 0.026
6 Mandor L 04 OH 0.026
Jumlah Tenag
B BAHAN
1 Kayu Kelas III m3 0.045
2 Paku 5cm - 12cm Kg 0.300
3 Minyak Bekisting Liter 0.100
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

23 1 M3 PEK. BETON TAK BERTULANG 1 : 3 : 5

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.200
3 Tukang Batu L 02 OH 0.200
5 Kepala Tukang L 03 OH 0.020
6 Mandor L 04 OH 0.060
Jumlah Tenag
B BAHAN
1 Semen Kg 230.000
2 Pasir Beton M3 0.637
3 Kerikil Beton M3 0.760
4 Air Liter 200.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

E PEKERJAAN BESI DAN ALUMINIUM

1 1 KG PAS. RANGKA KUDA-KUDA BAJA WF

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.060
2 Tukang Las Konstruksi L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Baja WF Kg 1.150
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 KG PAS. RANGKA GORDING KANAL C 150

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.060
2 Tukang Las Konstruksi L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Baja Gordeng Kanal C Kg 1.150
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 PEK. KUSEN ALUMINIUM OPEN BACK 4 x 1¾" SILVER /m'

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.043
2 Tukang Aluminium L 02 OH 0.430
3 Kepala Tukang L 03 OH 0.004
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Open Back 4" m' 1.100
2 Penutup Lurus Open Back 4" m' 1.100
3 Hollow 1/2 x 3/4 m' 1.100
4 Spycoat m' 0.150
5 Sealant Tube 0.060
6 Skrup Aluminium Buah 4.000
7 Baut Fixer Buah 2.000
8 Paku Rivet Buah 2.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 PEK. BINGKAI PINTU KACA ALUMINIUM SWING /m'


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.460
2 Tukang Aluminium L 02 OH 0.046
3 Kepala Tukang L 03 OH 0.420
4 Mandor L 04 OH 0.080
Jumlah Tenag
B BAHAN
1 Profil Batang Swing Aluminium m' 1.100
2 Spycoat m' 0.100
3 Skrup Aluminium Buah 2.000
4 Paku Rivet Buah 2.000
5 Karet C m' 1.100
6 Sealant Tube 0.040
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 PEK. BINGKAI JENDELA KACA ALUMINIUM KESMEN /m'

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.043
2 Tukang Aluminium L 02 OH 0.430
3 Kepala Tukang L 03 OH 0.004
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Profil Batang Kesmen Aluminium m' 1.100
2 Spycoat m' 0.100
3 Skrup Aluminium Buah 2.000
4 Paku Rivet Buah 2.000
5 Karet C m' 1.100
6 Sealant Tube 0.025
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 PEK. PASANGAN KACA CLEAR 5MM /M2

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.015
2 Tukang Aluminium L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.0008
Jumlah Tenag
B BAHAN
1 Kaca Clear 5 mm M2 1.100
2 Sealant Tube 0.050
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 PEK. PASANGAN KACA CLEAR 8MM /M2

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.017
2 Tukang Aluminium L 02 OH 0.170
3 Kepala Tukang L 03 OH 0.017
4 Mandor L 04 OH 0.0009
Jumlah Tenag
B BAHAN
1 Kaca Clear 8 mm M2 1.100
2 Sealant Tube 0.070
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

8 PEK. PASANGAN KACA TEMPRED 12MM /M2

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.025
2 Tukang Aluminium L 02 OH 0.250
3 Kepala Tukang L 03 OH 0.025
4 Mandor L 04 OH 0.0013
Jumlah Tenag
B BAHAN
1 Kaca Tempred 12 mm M2 1.100
2 Sealant Tube 0.070
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

9 PEK. PASANGAN KACA CERMIN 5MM /M2


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.015
2 Tukang Aluminium L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.0080
Jumlah Tenag
B BAHAN
1 Kaca Cermin 5mm M2 1.100
2 Sealant Tube 0.050
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

10 PEK. CAT MELAMIK BIDANG KAYU /M2

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.000
2 Tukang cat L 02 OH 0.250
3 Kepala tukang cat L 03 OH 0.150
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Dempul impra Kaleng 0.200
2 Cat dasar impra kaleng 0.150
3 Thinner Liter 0.700
4 Clear Sanding Sealer impra kaleng 0.300
5 Melamik Clear impra kaleng 0.200
6 Amplas Lembar 1.000
7 Triplek Sungkai m2 0.340
Jumlah
C PERALATAN
1 Alat bantu (kompresor) Ls 1.000

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

11 PEK. CAT DUCO BIDANG KAYU /M2

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.000
2 Tukang cat L 02 OH 0.250
3 Kepala tukang cat L 03 OH 0.150
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Dempul Kaleng 0.200
2 Cat dasar epoxy kaleng 0.150
3 Thinner Cobra Liter 0.700
4 Clear Nippe kaleng 0.300
5 Cat Nippe kaleng 0.200
6 Amplas Lembar 1.000
Jumlah
C PERALATAN
1 Alat bantu (kompresor) Ls 1.000

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

12 PEK. PASANGAN PINTU KACA TEMPRED 12MM SWING ( TYPE P.1) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Pas. Tempred 12mm m2 5.028
2 Engsel Pintu Tempred Set 2.000
3 Kunci Tanam Pintu Set 1.000
4 Handle Pintu Stainlees Set 1.000
5 Portal cover Pintu Fin Duco Merah m2 11.154
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

13 PEK. PASANGAN PINTU DOBEL TEAKWOOD FIN MELAMIK ( Type P.2) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Daun Pintu Double Teakwood m2 1.475
2 Kusen Alumunium m' 7.120
3 Kaca Clear 5 mm m2 0.534
4 Engsel Pintu Buah 6.000
5 Grendel Pintu Buah 1.000
6 Hendel Pintu Unit 1.000
7 Door Stoper Unit 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
14 PEK. PASANGAN PINTU DOBEL TEAKWOOD FIN MELAMIK ( Type P.4) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Daun Pintu Double Teakwood m2 2.939
2 Kusen Alumunium m' 15.320
3 Kaca Clear 5 mm m2 0.928
4 Engsel Pintu Buah 6.000
5 Grendel Pintu Buah 2.000
6 Hendel Pintu Unit 1.000
7 Door Stoper Unit 2.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

15 PEK. PASANGAN PINTU ALUMINIUM ( Type P.3) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Pintu Aluminium Ls 1.000
2 Kusen Alumunium m' 4.680
3 Engsel Pintu Buah 4.000
4 Grendel Pintu Buah 1.000
5 Hendel Pintu Unit 1.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

16 PEK. PASANGAN PINTU KACA BINGKAI ALUMINIUM SWING ( Type PJ1) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 18.560
2 Bingkai Pintu Kaca Aluminium Swing m' 11.200
3 Bingkai Jendela Kesmen m' 7.480
4 Penggantung Kesmen Set 3.000
5 Pas. Kaca Clear 5 mm m2 3.790
6 Engsel Pintu Buah 6.000
6 Engsel Jendela Buah 6.000
7 Grendel Pintu & jendela Buah 7.000
8 Door Closer Unit 2.000
9 Handle Pintu Unit 2.000
10 Kait Angin Buah 6.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

17 PEK. PASANGAN PINTU KACA BINGKAI ALUMINIUM SWING ( Type PJ2) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 33.980
2 Bingkai Pintu Kaca Aluminium Swing m' 11.200
3 Bingkai Jendela Kesmen m' 17.120
4 Penggantung Kesmen Set 1.000
5 Pas. Kaca Clear 5 mm m2 8.645
6 Engsel Pintu Buah 12.000
6 Engsel Jendela Buah 14.000
7 Grendel Pintu & jendela Buah 18.000
8 Door Closer Unit 2.000
9 Handle Pintu Unit 2.000
10 Kait Angin Buah 14.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

18 PEK. PASANGAN PINTU KACA BINGKAI ALUMINIUM SWING ( Type PJ3) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 29.040
2 Bingkai Pintu Kaca Aluminium Swing m' 11.200
3 Bingkai Jendela Kesmen m' 14.720
4 Penggantung Kesmen Set 1.000
5 Pas. Kaca Clear 5 mm m2 7.442
6 Engsel Pintu Buah 6.000
6 Engsel Jendela Buah 12.000
7 Grendel Pintu & jendela Buah 16.000
8 Door Closer Unit 2.000
9 Handle Pintu Unit 2.000
10 Kait Angin Buah 12.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

19 PEK. PASANGAN PINTU KACA BINGKAI ALUMINIUM SWING ( Type PJ4) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 19.120
2 Bingkai Pintu Kaca Aluminium Swing m' 11.200
3 Bingkai Jendela Kesmen m' 9.920
4 Penggantung Kesmen Set 1.000
5 Pas. Kaca Clear 5 mm m2 5.030
6 Engsel Pintu Buah 6.000
6 Engsel Jendela Buah 8.000
7 Grendel Pintu & jendela Buah 12.000
8 Door Closer Unit 2.000
9 Handle Pintu Unit 2.000
10 Kait Angin Buah 8.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

20 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J1) / Unit


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 14.000
2 Bingkai Jendela Kesmen m' 11.400
3 Pas. Kaca 5 mm m2 3.351
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah 8.000
6 Grendel Buah 4.000
7 Kait Angin Buah 8.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

21 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J2) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 13.940
2 Bingkai Jendela Kesmen m' 6.080
3 Pas. Kaca 5 mm m2 3.170
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah 4.000
6 Grendel Buah 2.000
7 Kait Angin Buah 4.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

22 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J3) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 9.000
2 Bingkai Jendela Kesmen m' 3.326
3 Pas. Kaca 5 mm m2 1.847
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah 2.000
6 Grendel Buah 2.000
7 Kait Angin Buah 2.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

22 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J3') / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 27.320
2 Bingkai Jendela Kesmen m' 11.400
3 Pas. Kaca 5 mm m2 7.248
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah 8.000
6 Grendel Buah 4.000
7 Kait Angin Buah 8.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

23 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J4) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 59.710
2 Bingkai Jendela Kesmen m'
3 Pas. Kaca 5 mm m2 15.216
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah
6 Grendel Buah
7 Kait Angin Buah
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
24 PEK. PASANGAN JENDELA KACA KESMEN ALUMINIUM (Type J5) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 17.360
2 Bingkai Jendela Kesmen m' 8.000
3 Pas. Kaca 5 mm m2 3.559
4 Penggantung Kesmen Unit 1.000
5 Engsel Jendela Buah 6.000
6 Grendel Buah 3.000
7 Kait Angin Buah 6.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

25 PEK. PASANGAN VENTILASI KACA ALUMINIUM (Type V1) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 5.100
2 Pas. Kaca 5 mm m2 0.540
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

26 PEK. PASANGAN VENTILASI KACA ALUMINIUM (Type V2) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 2.400
2 Pas. Kaca 5 mm m2 0.240
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

27 PEK. PASANGAN VENTILASI KACA ALUMINIUM (Type V3) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 3.400
2 Pas. Kaca 5 mm m2 0.540
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

28 PEK. PASANGAN VENTILASI KACA ALUMINIUM (Type LY) / Unit

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Ongkos Pasang + Alat Bantu Ls 1.000
Jumlah Tenag
B BAHAN
1 Kusen Aluminium 4" m' 7.500
2 Pas. Kaca 5 mm m2 1.147
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

28 PEK. 1 M2 PASANGAN JALUSI KISI KISI ALUMINIUM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.043
2 Tukang Khusus Aluminium L 02 OH 0.430
3 Kepala Tukang L 03 OH 0.004
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Aluminium Hollow 1/2 x 3/4" m' 1.000
2 Skrup Aluminium Bh 24.000
3 Paku Rivet Bh 24.000
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

30 PEK. M2 PAS ALUCOPAN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja OH 0.175
2 Tukang Besi OH 1.750
3 Kepala tukang OH 0.175
4 Mandor OH 0.009
Jumlah Tenag
B BAHAN
1 Alucopan Lbr 0.335
2 Sealant Tube 0.250
3 Skrup BH 12.000
4 Besi Holow m1 1.000
5 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

31 PEK. 1M1 RAILING TANGGA BESI HOLOW

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja OH 5.000
2 Tukang Besi OH 1.000
3 Kepala tukang OH 0.100
4 Mandor OH 0.100
Jumlah Tenag
B BAHAN
1 Stainlees Steel Dia 2" M' 1.000
2 Stainlees Steel Dia 1/2" M' 5.000
3 Stainlees Steel Dia 3/4" M' 1.000
4 Paku Sekerup buah 0.361
5 Baut 12 mm buah 2.000
6 Plat simpul Kg 2.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

F PEKERJAAN DINDING DAN PLESTERAN

1 1 M2 PEK. PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 PSR

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.300
2 Tukang Batu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Bata Merah m3 70.000
2 Semen Portland Kg 14.370
3 Pasir Pasang m3 0.040
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 PSR

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.300
2 Tukang Batu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Bata Merah m3 70.000
2 Semen Portland Kg 9.680
3 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M2 PEK. PLESTER 1 PC: 3 PSR, TEBAL 15 MM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.300
2 Tukang Batu L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 7.776
2 Pasir Pasang m3 0.023
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M2 PEK. PLESTER 1 PC: 5 PSR, TEBAL 15 MM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.300
2 Tukang Batu L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 5.184
2 Pasir Pasang m3 0.026
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M2 PEK. PLESTER 1 PC: 5 PSR, TEBAL 20 MM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.400
2 Tukang Batu L 02 OH 0.200
3 Kepala Tukang L 03 OH 0.020
4 Mandor L 04 OH 0.022
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 6.912
2 Pasir Pasang m3 0.035
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M2 PEK. ACIAN AIR SEMEN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Batu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.010
Jumlah Tenag
B BAHAN
1 Semen Portland Kg 3.250
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

G PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

1 1 M2 PEK. PEMASANGAN LANTAI GRANITE UKURAN 80x80

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Granite 80x80 Buah 1.562
2 Semen Portland Kg 9.800
3 Semen Warna Kg 1.300
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. PEMASANGAN LANTAI GRANITE UKURAN 60x60

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Granite 60x60 Buah 2.770
2 Semen Portland Kg 9.800
3 Semen Warna Kg 1.300
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M2 PEK. PEMASANGAN LANTAI KERAMIK UKURAN 30X30

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Keramik 30X30 Buah 11.110
2 Semen Portland Kg 10.000
3 Semen Warna Kg 1.500
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M2 PEK. PEMASANGAN LANTAI KERAMIK UKURAN 20X20 ANTI SLIP KM/WC

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Keramik 20X20 Anti Slip Buah 25.000
2 Semen Portland Kg 10.000
3 Semen Warna Kg 1.500
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M2 PEK. PEMASANGAN LANTAI KERAMIK UKURAN 40X40

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Keramik 40X40 Buah 6.250
2 Semen Portland Kg 10.000
3 Semen Warna Kg 1.500
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 1 M2 PEK. PEMASANGAN LANTAI KERAMIK UKURAN 25X20


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Keramik 25X20 Buah 20.000
2 Semen Portland Kg 10.000
3 Semen Warna Kg 1.500
4 Pasir Pasang m3 0.045
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 1 M2 PEK. PEMASANGAN PLINTLANTAI KERAMIK UKURAN 10x60

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.700
2 Tukang Batu L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.035
Jumlah Tenag
B BAHAN
1 Keramik 10X60 Buah 2.770
2 Semen Portland Kg 10.000
3 Semen Warna Kg 1.500
4 Pasir Pasang m3 0.045
5 List Aluminium 1 cm M1 1.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

H PEKERJAAN LANGIT-LANGIT (PLAFOND) DAN PARTISI GYPSUM BOARD

1 1 M2 PEK. RANGKA PLAFOND HOLOW 2X4 DAN 4X4 JARAK 60X120

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.350
2 Tukang Besi L 02 OH 0.350
3 Kepala Tukang L 03 OH 0.035
4 Mandor L 04 OH 0.018
Jumlah Tenag
B BAHAN
1 Rangka Metal Holow 4x4 2mm m1 3.400
2 Rangka Metal Holow 2x4 2mm m1 1.200
3 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. RANGKA PLAFOND (1,0 X 1,0 m) KAYU KELAS II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.150
2 Tukang Kayu L 02 OH 0.250
3 Kepala Tukang L 03 OH 0.025
4 Mandor L 04 OH 0.075
Jumlah Tenag
B BAHAN
1 Balok Kayu Kelas II m1 3.400
2 Paku Biasa 2 - 5 m1 1.200

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. PLAFOND VERSA BOARD (240x120) TEBAL 9MM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.050
3 Kepala Tukang L 03 OH 0.005
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Versa Board Lembar 0.364
2 Skrup Kg 0.110
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M2 PEK. PLAFOND GYPSUM BOARD (240X120) TEBAL 9MM JAYA BOARD SETARA
NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.050
3 Kepala Tukang L 03 OH 0.005
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Jaya Board Setara Lembar 0.364
2 Skrup Kg 0.110
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M2 PEK. PASANGAN DINDING PARTISI JAYA BOARD + RANGKA BESI HOLLOW SETARA

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.050
3 Kepala Tukang L 03 OH 0.005
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Hollow 4/4 Zincromate Batang 3.400
2 Hollow 2/4 Zincromate Batang 1.200
3 Jaya Board 9mm Lembar 0.720
4 Paku sekrup Buah 25.000
5 Ramset / dina bolt Buah 4.000
6 Cotton plaster Buah 0.100
7 Compoun Kg 0.130
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M21 LIST GYPSUM PROFIL

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.050
2 Tukang Kayu L 02 OH 0.050
3 Kepala Tukang L 03 OH 0.005
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 List Gypsum Profil m1 1.050
2 Skrup Kg 0.010
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

I PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP

1 1 M2 PEK. RANGKA BAJA RINGAN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Besi L 02 OH 0.450
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Main Truss C.75-75 m1 2.800
2 Roof Bottom/Reng R.33 - 0.45 m1 5.100
3 Self Drilling Screw dia 6 x 20 mm Buah 25.000
4 Self Drilling Screw dia 4 x 16 mm Buah 35.000
5 Dynabol dia 12 x 120 mm Buah 1.000
Jumlah
C PERALATAN
1 Gambar desain Ls 1.000
2 Mesin Bor Listrik/genset Ls 1.000
3 Mobilisasi Ls 1.000
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. PASANGAN ATAP SAKURA ROOF

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.120
2 Tukang Kayu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.006
Jumlah Tenag
B BAHAN
1 Atap zincalume (Sakura Roof) Lembar 1.620
2 Paku sakura Kg 0.020
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
3 1 M2 PEK. PASANGAN NOK SAKURA ROOF

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Nok Sakura Roof Lembar 1.000
2 Paku seng Kg 0.040
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M1 PEK. TALANG DATAR JURAI SENG BJLS 28 LEBAR 90 KLS II ATAU KLS III

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Kayu L 02 OH 0.400
3 Kepala Tukang L 03 OH 0.025
4 Mandor L 04 OH 0.010
Jumlah Tenag
B BAHAN
1 Seng plat m’ 1.050
2 Paku 1 cm - 2,5 cm Kg 0.015
3 Papan kayu kelas II atau III m3 0.019
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M1 PEK. LISPLANK (NUSA PLANK 30 X 405 CM) SETARA

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.150
2 Tukang Kayu L 02 OH 0.250
3 Kepala Tukang L 03 OH 0.250
4 Mandor L 04 OH 0.075
Jumlah Tenag
B BAHAN
1 (Nusa Plank 30 x 405 cm) M1 1.050
2 Paku Sekrup Kg 0.060
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 1 M2 PEK. RANGKA KASO BAJA RINGAN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Besi L 02 OH 0.450
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Roof Bottom/Reng R.33 - 0.45 m1 2.500
Self Drilling Screw dia 4 x 16 mm( Roof
2 Buah 5.000
Bottom Screw)
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 1 M2 PEK. LAPISAN NO DROP

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.020
2 Tukang Batu L 02 OH 0.063
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 No Drop Dasar kg 0.100
2 No Drop Penutup kg 0.260
3 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

J PEKERJAAN KAYU

1 1 M3 PEK. KUSEN PINTU DAN KUSEN JENDELA KAYU KELAS II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 6.000
2 Tukang Kayu L 02 OH 18.000
3 Kepala Tukang L 03 OH 1.600
4 Mandor L 04 OH 0.300
Jumlah Tenag
B BAHAN
1 Balok Kayu m3 1.200
2 Paku 10 cm Kg 1.250
3 Lem Kayu Kg 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. PEMBUATAN DAN PEMASANGAN DAUN PINTU PANEL KAYU KELAS I

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.000
2 Tukang Kayu L 02 OH 3.000
3 Kepala Tukang L 03 OH 0.300
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Papan Kayu m3 0.040
2 Lem Kayu Kg 0.500
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M2 PEK. PEMBUATAN DAN PEMASANGAN PINTU DAN JENDELA KACA KAYU KELAS II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.800
2 Tukang Kayu L 02 OH 2.400
3 Kepala Tukang L 03 OH 0.240
4 Mandor L 04 OH 0.040
Jumlah Tenag
B BAHAN
1 Papan Kayu m3 0.024
2 Lem Kayu Kg 0.300
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M3 PEK. KONSTRUKSI GORDING KAYU KELAS II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 6.700
2 Tukang Kayu L 02 OH 20.100
3 Kepala Tukang L 03 OH 2.010
4 Mandor L 04 OH 0.335
Jumlah Tenag
B BAHAN
1 Balok Kayu m3 1.100
2 Besi Strip Tebal 5mm Kg 15.000
3 Paku 12 Kg 3.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M2 PEK. KONSTRUKSI RENG DAN KASAU KAYU KELAS II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Kasau 5/7 kayu kls II m3 0.0105
2 Reng 3/4 kayu kls II m3 0.0036
3 Paku campur Kg 0.1000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 1 M1 PEK. LISPLANK UKURAN (3 X 20) CM KAYU KELAS I ATAU II

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.100
2 Tukang Kayu L 02 OH 0.200
3 Kepala Tukang L 03 OH 0.020
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Papan kayu kelas II m’ 0.010
2 Paku Campur Kg 0.100
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

K PEKERJAAN KUNCI DAN KACA

1 PEMASANGAN 1 BUAH ENGSEL PINTU KUPU-KUPU

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.015
2 Tukang Kayu L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.0008
Jumlah Tenag
B BAHAN
1 Engsel Pintu Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 PEMASANGAN 1 BUAH ENGSEL JENDELA KUPU-KUPU


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.010
2 Tukang Kayu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.0005
Jumlah Tenag
B BAHAN
1 Engsel Jendela Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 PEMASANGAN 1 BUAH KAIT ANGIN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.015
2 Tukang Kayu L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.0080
Jumlah Tenag
B BAHAN
1 Kait Aingin Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
4 PEMASANGAN 1 BUAH DOOR STOPER

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.010
2 Tukang Kayu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.0050
Jumlah Tenag
B BAHAN
1 Door Stoper Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 PEMASANGAN 1 BUAH KUNCI PINTU ( Unit )

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.010
2 Tukang Kayu L 02 OH 0.500
3 Kepala Tukang L 03 OH 0.050
4 Mandor L 04 OH 0.0050
Jumlah Tenag
B BAHAN
1 Hendel dan Kunci Unit 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 PEMASANGAN 1 BUAH GRENDEL PINTU

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.015
2 Tukang Kayu L 02 OH 0.150
3 Kepala Tukang L 03 OH 0.015
4 Mandor L 04 OH 0.0080
Jumlah Tenag
B BAHAN
1 Grendel Pintu Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

L PEKERJAAN PENGECATAN

1 1 M2 PEK. CAT TEMBOK BARU (1 LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP (INTER

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.020
2 Tukang Cat L 02 OH 0.063
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Plamuur Kg 0.100
2 Cat Dasar Kg 0.100
3 Cat Penutup Vinilex Kg 0.260
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 1 M2 PEK. CAT TEMBOK BARU ( 1 LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP (EXTER

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.020
2 Tukang Cat L 02 OH 0.063
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Plamuur Kg 0.100
2 Cat Dasar Kg 0.100
3 Cat Penutup Vinilex Kg 0.260
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 1 M2 PEK. CAT PLAFOND BARU ( 1 LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP (INTE

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.020
2 Tukang Cat L 02 OH 0.063
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Plamuur Cornis A Plus Kg 0.100
2 Cat Dasar Kg 0.100
3 Cat Penutup Vinilex Kg 0.260
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 1 M2 PEK. PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PE

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.070
2 Tukang Cat L 02 OH 0.009
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Cat Menie Kg 0.200
2 Plamuur Boyo Kg 0.150
3 Cat Dasar Kg 0.170
4 Cat Penutup Altex Kg 0.260
5 Kuas Buah 0.010
6 Pengencer Kg 0.030
7 Amplas Lembar 0.200
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 1 M2 PEK. PELABURAN BIDANG KAYU DENGAN VERNIS

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.160
2 Tukang Cat L 02 OH 0.160
3 Kepala Tukang L 03 OH 0.016
4 Mandor L 04 OH 0.003
Jumlah Tenag
B BAHAN
1 Vernis Liter 0.150
2 Dempul Kg 0.050
3 Amplas Lembar 0.100
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

M PEKERJAAN SANITASI DAN PLUMBING

1 PEMASANGAN 1 BUAH CLOSET DUDUK (EX. TOTO)

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 3.300
2 Tukang Batu L 02 OH 1.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.160
Jumlah Tenag
B BAHAN
1 Closet Duduk Toto Unit 1.000
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 PEMASANGAN 1 BUAH CLOSET JONGKOK (EX. TOTO)

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.000
2 Tukang Batu L 02 OH 1.500
3 Kepala Tukang L 03 OH 0.150
4 Mandor L 04 OH 0.160
Jumlah Tenag
B BAHAN
1 Closet Jongkok Toto Unit 1.000
2 Semen Portland Kg 6.000
3 Pasir Pasang m3 0.010
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

2 PEMASANGAN 1 BUAH URINOIR (EX. TOTO)

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.000
2 Tukang Batu L 02 OH 1.000
3 Kepala Tukang L 03 OH 0.100
4 Mandor L 04 OH 0.050
Jumlah Tenag
B BAHAN
1 Urinoir Toto Unit 1.000
2 Semen Portland Kg 6.000
3 Pasir Pasang m3 0.010
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 PEMASANGAN 1 BUAH WASTAFEL (EX. TOTO)

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 1.200
2 Tukang Batu L 02 OH 1.450
3 Kepala Tukang L 03 OH 0.150
4 Mandor L 04 OH 0.060
Jumlah Tenag
B BAHAN
1 Wastafel Toto Unit 1.200
2 Semen Portland Kg 6.000
3 Pasir Pasang m3 0.010
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

4 PEMASANGAN 1 BUAH KRAN AIR

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.010
2 Tukang Batu L 02 OH 0.400
3 Kepala Tukang L 03 OH 0.040
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Kran Air Buah 1.000
2 Sealttape Buah 0.025
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 PEMASANGAN 1 BUAH BAK CUCI PIRING STAINLESS STELL

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.030
2 Tukang Batu L 02 OH 0.300
3 Kepala Tukang L 03 OH 0.030
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Bak Cuci Piring Unit 1.000
2 Waterdrain Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

6 PEMASANGAN 1 BUAH FLOOR DRAIN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.010
2 Tukang Batu L 02 OH 0.100
3 Kepala Tukang L 03 OH 0.010
4 Mandor L 04 OH 0.005
Jumlah Tenag
B BAHAN
1 Floor Drain Unit 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATA 45 X 45 CM TINGGI 50CM

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 3.200
2 Tukang Batu L 02 OH 1.150
3 Kepala Tukang L 03 OH 0.011
4 Mandor L 04 OH 0.016
Jumlah Tenag
B BAHAN
1 Bata Merah Buah 70.000
2 Semen Portland Kg 77.000
3 Pasir Pasang m3 0.130
4 Pasir Peton m3 0.090
5 Kerikil m3 0.020
6 Besi Tulangan Ø 6 Kg 2.600
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

8 PEMASANGAN 1 BUAH BAK AIR FIBERGLASS VOL 1M3

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.300
2 Tukang Batu L 02 OH 0.450
3 Kepala Tukang L 03 OH 0.045
4 Mandor L 04 OH 0.015
Jumlah Tenag
B BAHAN
1 Bak Air Fiberglass Unit 1.000
2 Aksesoris % 12.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
9 1 M1 PEK. PAMASANGAN SALURAN KELILING BANGUNAN DIPLESTER LICIN

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.598
2 Tukang Batu L 02 OH 0.279
3 Kepala Tukang L 03 OH 0.028
4 Mandor L 04 OH 0.022
Jumlah Tenag
B BAHAN
1 Batu Gunung m3 0.132
2 Semen Portland Kg 15.550
3 Pasir Pasang m3 0.086
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

10 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 1/2"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 1/2" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN
Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

11 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 3"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 3" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

12 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 3/4"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 3/4" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

13 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 1"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 1" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

14 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 4"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 4" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

15 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 2"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 2" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

16 1 M1 PAS. PIPA PVC TYPE AW DIAMETER 2 1/2"

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.360
2 Tukang Batu L 02 OH 0.060
3 Kepala Tukang L 03 OH 0.006
4 Mandor L 04 OH 0.002
Jumlah Tenag
B BAHAN
1 Pipa PVC AW 2 1/2" m1 1.200
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

N PEKERJAAN INSTALASI

1 PEMASANGAN 1 BUAH STOP KONTAK DINDING

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Stop Kontak Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
2 PEMASANGAN 1 BUAH STOP KONTAK LANTAI

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Stop Kontak Lantai Buah 1.000

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

3 PEMASANGAN 1 BUAH SAKLAR GANDA

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Saklar Ganda Buah 1.000

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
4 PEMASANGAN 1 BUAH SAKLAR TUNGGAL

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Saklar Tunggal Buah 1.000

Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

5 PEMASANGAN 1 TITIK STOP KONTAK

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Listrik L 02 OH 0.600
Jumlah Tenag
B BAHAN
1 Kabel Listrik NYM 2 x 2,5 mm Roll 0.090
3 Pipa Maspion C 5/8 M1 0.100
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
6 PEMASANGAN 1 TITIK LAMPU TL

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Listrik L 02 OH 0.600
Jumlah Tenag
B BAHAN
1 Kabel Listrik NYM 2 x 1.5 mm Roll 0.090
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

7 PEMASANGAN 1 BUAH RUMAH RM PANJANG 120 + LAMPU TL 34 WATT PHILIPS

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
2 Rumah Lampu RM Set Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
8 PEMASANGAN 1 BUAH RUMAH RM PANJANG 60

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
2 Rumah Lampu RM Set Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

9 PEMASANGAN 1 BUAH LAMPU TL TYPE PHILIPS TORNADO 24 WATT

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Lampu TL Philips Buah 1.000
2 Rumah Lampu Mikawa 4'' Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
10 PEMASANGAN 1 BUAH LAMPU TL TYPE PHILIPS TORNADO 20 WATT

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Lampu TL Philips 20 Watt Buah 1.000
2 Rumah Lampu Mikawa 4'' Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

11 PEMASANGAN 1 BUAH LAMPU TL TYPE PHILIPS 18 WATT

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Lampu TL Philips Buah 1.000
2 Rumah Lampu Mikawa 4'' Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

12 PEMASANGAN 1 BUAH LAMPU TL TYPE OSIWA 90CM LAMPU DROP CELLING WARM
NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Lampu TL Osiwa Buah 1.000
2 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

13 PEMASANGAN 1 BUAH MCB PEMBATAS

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH
2 Tukang Listrik L 02 OH
Jumlah Tenag
B BAHAN
1 Kabel Listrik NYM 2 x 2,5 mm Roll
2 Panel MCB + Isi Buah
3 Pipa Maspion C 5/8 M1
4 Aksesoris Ls
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
14 PEMASANGAN 1 BUAH STOP KONTAK DATA

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Outlet Data Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

15 PEMASANGAN 1 BUAH STOP KONTAK TELEPON

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Outlet Telepon Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

16 PEMASANGAN 1 BUAH STOP KONTAK ANTENA


NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Outlet Anten Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

17 PEMASANGAN 1 BUAH CELLING SPEAKER

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Celing Speaker Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

18 PEMASANGAN 1 BUAH STOP KONTAK TV

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA

Jumlah Tenag
B BAHAN
1 Stop Kontak TV Buah 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

19 PEMASANGAN 1 TITIK STOP KONTAK TV

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Listrik L 02 OH 0.600
Jumlah Tenag
B BAHAN
1 Kabel Roll 0.100
3 Pipa Maspion C 5/8 M1 0.250
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

20 PEMASANGAN 1 TITIK STOP KONTAK DATA

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Listrik L 02 OH 0.600
Jumlah Tenag
B BAHAN
1 Kabel Roll 0.200
3 Pipa Maspion C 5/8 M1 0.250
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

21 PEMASANGAN 1 TITIK STOP KONTAK TELEPON

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Pekerja L 01 OH 0.200
2 Tukang Listrik L 02 OH 0.600
Jumlah Tenag
B BAHAN
1 Kabel Roll 0.200
3 Pipa Maspion C 5/8 M1 0.250
4 Aksesoris Ls 1.000
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN

O PEKERJAAN LAIN-LAIN
1 MEMASANG 1 M2 PAVING BLOK

NO. 11/PRT/M/2013
KOEFISI
NO URAIAN KODE SATUAN EN
A TENAGA
1 Tukang Batu OH 0.090
2 Kepala Tukang OH 0.009
3 Pekerja OH 0.054
4 Mandor OH 0.027
Jumlah Tenag
B BAHAN
1 Paving block M2 1.100
2 Pasir urug M3 0.120
Jumlah
C PERALATAN

Jumlah Pe
D JUMLAH (A + B + C)
E OVERHEAT & PROFIT ( 10% )
F HARGA SATUAN PEKERJAAN
SNI

rtanahan Nasional Kabupaten Konawe

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 34,000
Rp 100,000 Rp 2,000
Rp 75,000 Rp 1,500
Jumlah Tenaga Kerja Rp 50,500

Rp 3,000 Rp 3,750
Rp -
Rp 30,000 Rp 36,000
Rp -
Rp -
Rp -
Rp 18,000 Rp 1,080
Rp -
Jumlah Bahan Rp 40,830

Jumlah Peralatan Rp -
Rp 91,330
Rp 9,133
Rp 100,463
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja Rp 16,375

Rp 1,700,000 Rp 20,400
Rp 18,000 Rp 360
Rp 2,100,000 Rp 14,700
Jumlah Bahan Rp 35,460

Jumlah Peralatan Rp -
Rp 51,835
Rp 5,184
Rp 57,019

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 48,750
Rp 75,000 Rp 1,875
Jumlah Tenaga Kerja Rp 50,625

Jumlah Bahan

Jumlah Peralatan
Rp 50,625
Rp 5,063
Rp 55,688

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 58,500
Rp 75,000 Rp 3,375
Jumlah Tenaga Kerja Rp 61,875

Jumlah Bahan

Jumlah Peralatan
Rp 61,875
Rp 3,094
Rp 64,969
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 68,250
Rp 75,000 Rp 5,025
Jumlah Tenaga Kerja Rp 73,275

Jumlah Bahan

Jumlah Peralatan
Rp 73,275
Rp 3,664
Rp 76,939

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 32,500
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja Rp 36,250

Jumlah Bahan

Jumlah Peralatan
Rp 36,250
Rp 1,813
Rp 38,063

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 75,000 Rp 750
Jumlah Tenaga Kerja Rp 20,250

Rp 50,000 Rp 60,000
Jumlah Bahan Rp 60,000

Jumlah Peralatan
Rp 80,250
Rp 8,025
Rp 88,275

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 32,500
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja Rp 36,250

Jumlah Bahan
Jumlah Peralatan
Rp 36,250
Rp 3,625
Rp 39,875

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 75,000 Rp 750
Jumlah Tenaga Kerja Rp 20,250

Rp 183,333 Rp 220,000
Jumlah Bahan Rp 220,000

Jumlah Peralatan
Rp 240,250
Rp 24,025
Rp 264,275

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Rp 65,000 Rp 97,500
Rp 85,000 Rp 63,750
Rp 100,000 Rp 7,500
Rp 75,000 Rp 5,625
Jumlah Tenaga Kerja Rp 174,375

Rp 200,000 Rp 240,000
Rp 1,380 Rp 187,680
Rp 183,333 Rp 99,733
Jumlah Bahan Rp 527,413

Jumlah Peralatan
Rp 701,788
Rp 70,179
Rp 771,967

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 50,700
Rp 85,000 Rp 33,150
Rp 100,000 Rp 3,900
Rp 75,000 Rp 2,925
Jumlah Tenaga Kerja Rp 90,675

Rp 200,000 Rp 240,000
Rp 183,333 Rp 79,200
Jumlah Bahan Rp 319,200

Jumlah Peralatan
Rp 409,875
Rp 40,988
Rp 450,863

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 107,250
Rp 85,000 Rp 23,375
Rp 100,000 Rp 2,800
Rp 75,000 Rp 6,225
Jumlah Tenaga Kerja Rp 139,650

Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Jumlah Bahan Rp 845,443

Jumlah Peralatan -
Rp 985,093
Rp 98,509
Rp 1,083,603

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Rp 65,000 Rp 107,250
Rp 85,000 Rp 23,375
Rp 100,000 Rp 2,800
Rp 75,000 Rp 6,225
Jumlah Tenaga Kerja Rp 139,650

Rp 1,380 Rp 449,880
Rp 233,333 Rp 126,677
Rp 200,000 Rp 152,440
Rp 50 Rp 10,750
Jumlah Bahan Rp 739,747

Jumlah Peralatan -
Rp 879,397
Rp 87,940
Rp 967,336

m x 150cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 23,375
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,200
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 613,700

Rp 2,100,000 Rp 420,000
Rp 18,000 Rp 27,000
Rp 10,900 Rp 4,360
Rp 18,000 Rp -
Rp 24,200 Rp 54,450
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Jumlah Bahan Rp 1,351,253

Jumlah Peralatan
Rp 1,964,953
Rp 196,495
Rp 2,161,449

m x 100cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 23,375
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,200
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 613,700

Rp 2,100,000 Rp 420,000
Rp 18,000 Rp 27,000
Rp 10,900 Rp 4,360
Rp 18,000 Rp -
Rp 24,200 Rp 54,450
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Jumlah Bahan Rp 1,351,253
Jumlah Peralatan
Rp 1,964,953
Rp 196,495
Rp 2,161,449

x 50cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 367,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 132,600
Rp 85,000 Rp 119,000
Rp 100,000 Rp 32,300
Rp 75,000 Rp 21,225
Jumlah Tenaga Kerja Rp 695,750

Rp 2,100,000 Rp 567,000
Rp 18,000 Rp 36,000
Rp 10,900 Rp 6,540
Rp 18,000 Rp -
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,200
Rp 50 Rp 10,750
Jumlah Bahan Rp 1,527,523

Jumlah Peralatan -
Rp 2,223,273
Rp 222,327
Rp 2,445,601
30cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 367,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 132,600
Rp 85,000 Rp 119,000
Rp 100,000 Rp 32,300
Rp 75,000 Rp 21,225
Jumlah Tenaga Kerja Rp 695,750

Rp 2,100,000 Rp 567,000
Rp 18,000 Rp 36,000
Rp 10,900 Rp 6,540
Rp 18,000 Rp 3,707,640
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,200
Rp 50 Rp 10,750
Jumlah Bahan Rp 5,235,163

Jumlah Peralatan
Rp 5,930,913
Rp 593,091
Rp 6,524,005

25cm K300
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 367,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 132,600
Rp 85,000 Rp 119,000
Rp 100,000 Rp 32,300
Rp 75,000 Rp 21,225
Jumlah Tenaga Kerja Rp 695,750

Rp 2,100,000 Rp 567,000
Rp 18,000 Rp 36,000
Rp 10,900 Rp 6,540
Rp 18,000 Rp 4,895,640
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,200
Rp 50 Rp 10,750
Jumlah Bahan Rp 6,423,163

Jumlah Peralatan
Rp 7,118,913
Rp 711,891
Rp 7,830,805

20cm K175

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 367,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 132,600
Rp 85,000 Rp 119,000
Rp 100,000 Rp 32,300
Rp 75,000 Rp 21,225
Jumlah Tenaga Kerja Rp 695,750

Rp 2,100,000 Rp 567,000
Rp 18,000 Rp 36,000
Rp 10,900 Rp 6,540
Rp 18,000 Rp -
Rp 24,200 Rp 72,600
Rp 1,380 Rp 449,880
Rp 233,333 Rp 126,677
Rp 200,000 Rp 152,440
Rp 50 Rp 10,750
Jumlah Bahan Rp 1,421,887

Jumlah Peralatan
Rp 2,117,637
Rp 211,764
Rp 2,329,400

40cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 458,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 178,500
Rp 100,000 Rp 40,300
Rp 75,000 Rp 26,475
Jumlah Tenaga Kerja Rp 867,150
Rp 2,100,000 Rp 840,000
Rp 18,000 Rp 72,000
Rp 10,900 Rp 21,800
Rp 18,000 Rp 2,607,840
Rp 24,200 Rp 108,900
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 345,000
Rp 90,000 Rp 315,000
Rp 3,000 Rp 60,000
Jumlah Bahan Rp 5,215,983

Jumlah Peralatan
Rp 6,083,133
Rp 608,313
Rp 6,691,447

50cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 458,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 178,500
Rp 100,000 Rp 40,300
Rp 75,000 Rp 26,475
Jumlah Tenaga Kerja Rp 867,150

Rp 2,100,000 Rp 840,000
Rp 18,000 Rp 72,000
Rp 10,900 Rp 21,800
Rp 18,000 Rp 2,857,320
Rp 24,200 Rp 108,900
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 345,000
Rp 90,000 Rp 315,000
Rp 3,000 Rp 60,000
Jumlah Bahan Rp 5,465,463

Jumlah Peralatan
Rp 6,332,613
Rp 633,261
Rp 6,965,875

25cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 458,250
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 178,500
Rp 100,000 Rp 40,300
Rp 75,000 Rp 26,475
Jumlah Tenaga Kerja Rp 867,150

Rp 2,100,000 Rp 840,000
Rp 18,000 Rp 72,000
Rp 10,900 Rp 21,800
Rp 18,000 Rp -
Rp 24,200 Rp 108,900
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 345,000
Rp 90,000 Rp 315,000
Rp 3,000 Rp 60,000
Jumlah Bahan Rp 2,608,143

Jumlah Peralatan
Rp 3,475,293
Rp 347,529
Rp 3,822,823

15cm K175

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 22,950
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,500
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 613,575

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp -
Rp 24,200 Rp 54,450
Rp 1,380 Rp 449,880
Rp 233,333 Rp 126,677
Rp 200,000 Rp 152,440
Rp 50 Rp 10,750
Rp 2,300,000 Rp 276,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 96,000
Jumlah Bahan Rp 2,165,237

Jumlah Peralatan
Rp 2,778,812
Rp 277,881
Rp 3,056,693

x 55cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 412,750
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 119,000
Rp 100,000 Rp 33,300
Rp 75,000 Rp 23,850
Jumlah Tenaga Kerja Rp 752,525

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp 3,600,000
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 322,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 48,000
Jumlah Bahan Rp 5,887,083

Jumlah Peralatan
Rp 6,639,608
Rp 663,961
Rp 7,303,569

35cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 412,750
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 119,000
Rp 100,000 Rp 33,300
Rp 75,000 Rp 23,850
Jumlah Tenaga Kerja Rp 752,525

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp -
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 322,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 48,000
Jumlah Bahan Rp 2,287,083
Jumlah Peralatan
Rp 3,039,608
Rp 303,961
Rp 3,343,569

30cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 412,750
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 119,000
Rp 100,000 Rp 33,300
Rp 75,000 Rp 23,850
Jumlah Tenaga Kerja Rp 752,525

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp 3,707,640
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 322,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 48,000
Jumlah Bahan Rp 5,994,723

Jumlah Peralatan
Rp 6,747,248
Rp 674,725
Rp 7,421,973

25cm K300
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 412,750
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 119,000
Rp 100,000 Rp 33,300
Rp 75,000 Rp 23,850
Jumlah Tenaga Kerja Rp 752,525

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp -
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 322,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 48,000
Jumlah Bahan Rp 2,287,083

Jumlah Peralatan
Rp 3,039,608
Rp 303,961
Rp 3,343,569

25cm K300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 412,750
Rp 85,000 Rp 23,375
Rp 85,000 Rp 140,250
Rp 85,000 Rp 119,000
Rp 100,000 Rp 33,300
Rp 75,000 Rp 23,850
Jumlah Tenaga Kerja Rp 752,525

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp 3,937,320
Rp 24,200 Rp 72,600
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 322,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 48,000
Jumlah Bahan Rp 6,224,403

Jumlah Peralatan
Rp 6,976,928
Rp 697,693
Rp 7,674,621

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 18,850
Rp 85,000 Rp 2,805
Rp 85,000 Rp 2,805
Rp 85,000 Rp 2,805
Rp 100,000 Rp 1,000
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja Rp 29,390
Rp 2,100,000 Rp 6,300
Rp 18,000 Rp 360
Rp -
Rp 18,000 Rp 3,420,000
Rp 24,200 Rp 1,210
Rp 1,380 Rp 7,590
Rp 233,333 Rp 2,100
Rp 200,000 Rp 3,000
Jumlah Bahan Rp 3,440,560

Jumlah Peralatan
Rp 3,469,950
Rp 346,995
Rp 3,816,945

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 23,375
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,500
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 614,000

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp 1,626,660
Rp 24,200 Rp 54,450
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 276,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 96,000
Jumlah Bahan Rp 3,897,593

Jumlah Peralatan
Rp 4,511,593
Rp 451,159
Rp 4,962,753

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 23,375
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,500
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 614,000

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp -
Rp 24,200 Rp 54,450
Rp 1,380 Rp 569,940
Rp 233,333 Rp 113,493
Rp 200,000 Rp 151,260
Rp 50 Rp 10,750
Rp 2,300,000 Rp 276,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 96,000
Jumlah Bahan Rp 2,270,933

Jumlah Peralatan
Rp 2,884,933
Rp 288,493
Rp 3,173,427

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 344,500
Rp 85,000 Rp 23,375
Rp 85,000 Rp 110,500
Rp 85,000 Rp 89,250
Rp 100,000 Rp 26,500
Rp 75,000 Rp 19,875
Jumlah Tenaga Kerja Rp 614,000

Rp 2,100,000 Rp 672,000
Rp 18,000 Rp 57,600
Rp 10,900 Rp 17,440
Rp 18,000 Rp 2,700,000
Rp 24,200 Rp 54,450
Rp 1,380 Rp 449,880
Rp 233,333 Rp 126,677
Rp 200,000 Rp 152,440
Rp 50 Rp 10,750
Rp 2,300,000 Rp 276,000
Rp 90,000 Rp 252,000
Rp 3,000 Rp 96,000
Jumlah Bahan Rp 4,865,237

Jumlah Peralatan
Rp 5,479,237
Rp 547,924
Rp 6,027,160
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 33,800
Rp 85,000 Rp 22,100
Rp 100,000 Rp 2,600
Rp 75,000 Rp 1,950
Jumlah Tenaga Kerja Rp 60,450

Rp 2,100,000 Rp 94,500
Rp 18,000 Rp 5,400
Rp 10,900 Rp 1,090
Jumlah Bahan Rp 100,990

Jumlah Peralatan
Rp 161,440
Rp 16,144
Rp 177,584

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 78,000
Rp 85,000 Rp 17,000
Rp 100,000 Rp 2,000
Rp 75,000 Rp 4,500
Jumlah Tenaga Kerja Rp 101,500

Rp 1,380 Rp 317,400
Rp 233,333 Rp 148,633
Rp 200,000 Rp 152,000
Rp 50 Rp 10,000
Jumlah Bahan Rp 618,033
Jumlah Peralatan
Rp 719,533
Rp 71,953
Rp 791,487

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 3,900
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 225
Jumlah Tenaga Kerja Rp 9,825

Rp 15,500 Rp 17,825
Jumlah Bahan Rp 17,825

Jumlah Peralatan -
Rp 27,650
Rp 2,765
Rp 30,415

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 3,900
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 225
Jumlah Tenaga Kerja Rp 9,825
Rp 12,500 Rp 14,375
Jumlah Bahan Rp 14,375

Jumlah Peralatan -
Rp 24,200
Rp 2,420
Rp 26,620

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 2,795
Rp 85,000 Rp 36,550
Rp 100,000 Rp 430
Rp 75,000 Rp 161
Jumlah Tenaga Kerja Rp 39,936

Rp 59,337 Rp 65,271
Rp 21,575 Rp 23,733
Rp 20,833 Rp 22,917
Rp 10,787 Rp 1,618
Rp 40,000 Rp 2,400
Rp 600 Rp 2,400
Rp 700 Rp 1,400
Rp 250 Rp 500
Jumlah Bahan Rp 120,238

Jumlah Peralatan -
Rp 160,174
Rp 16,017
Rp 176,192
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 29,900
Rp 85,000 Rp 3,910
Rp 100,000 Rp 42,000
Rp 75,000 Rp 6,000
Jumlah Tenaga Kerja Rp 81,810

Rp 79,200 Rp 87,120
Rp 10,787 Rp 1,079
Rp 600 Rp 1,200
Rp 250 Rp 500
Rp 6,462 Rp 7,108
Rp 40,000 Rp 1,600
Jumlah Bahan Rp 98,607

Jumlah Peralatan -
Rp 180,417
Rp 18,042
Rp 198,459

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 2,795
Rp 85,000 Rp 36,550
Rp 100,000 Rp 430
Rp 75,000 Rp 161
Jumlah Tenaga Kerja Rp 39,936

Rp 32,362 Rp 35,598
Rp 10,787 Rp 1,079
Rp 600 Rp 1,200
Rp 250 Rp 500
Rp 6,462 Rp 7,108
Rp 40,000 Rp 1,000
Jumlah Bahan Rp 46,485

Jumlah Peralatan -
Rp 86,421
Rp 8,642
Rp 95,063

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 975
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 60
Jumlah Tenaga Kerja Rp 15,285

Rp 110,000 Rp 121,000
Rp 40,000 Rp 2,000
Jumlah Bahan Rp 123,000

Jumlah Peralatan -
Rp 138,285
Rp 13,829
Rp 152,114

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,105
Rp 85,000 Rp 14,450
Rp 100,000 Rp 1,700
Rp 75,000 Rp 68
Jumlah Tenaga Kerja Rp 17,323

Rp 400,000 Rp 440,000
Rp 40,000 Rp 2,800
Jumlah Bahan Rp 442,800

Jumlah Peralatan -
Rp 460,123
Rp 46,012
Rp 506,135

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,625
Rp 85,000 Rp 21,250
Rp 100,000 Rp 2,500
Rp 75,000 Rp 98
Jumlah Tenaga Kerja Rp 25,473

Rp 1,875,000 Rp 2,062,500
Rp 40,000 Rp 2,800
Jumlah Bahan Rp 2,065,300

Jumlah Peralatan -
Rp 2,090,773
Rp 209,077
Rp 2,299,850
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 975
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 600
Jumlah Tenaga Kerja Rp 15,825

Rp 115,000 Rp 126,500
Rp 40,000 Rp 2,000
Jumlah Bahan Rp 128,500

Jumlah Peralatan -
Rp 144,325
Rp 14,433
Rp 158,758

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 65,000
Rp 85,000 Rp 21,250
Rp 100,000 Rp 15,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja Rp 105,000

Rp 45,000 Rp 9,000
Rp 42,000 Rp 6,300
Rp 32,000 Rp 22,400
Rp 75,000 Rp 22,500
Rp 85,000 Rp 17,000
Rp 1,000 Rp 1,000
Rp 80,000 Rp 27,200
Jumlah Bahan Rp 105,400
Rp 10,000 Rp 10,000

Jumlah Peralatan 10,000.00


Rp 220,400
Rp 22,040
Rp 242,440

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 65,000
Rp 85,000 Rp 21,250
Rp 100,000 Rp 15,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja Rp 105,000

Rp 42,000 Rp 8,400
Rp 40,000 Rp 6,000
Rp 40,000 Rp 28,000
Rp 75,000 Rp 22,500
Rp 85,000 Rp 17,000
Rp 1,000 Rp 1,000
Jumlah Bahan Rp 82,900

Rp 10,000 Rp 10,000

Jumlah Peralatan 10,000.00


Rp 197,900
Rp 19,790
Rp 217,690

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 1,875,000 Rp 9,427,500
Rp 500,000 Rp 1,000,000
Rp 510,000 Rp 510,000
Rp 225,000 Rp 225,000
Rp 500,000 Rp 5,577,000
Jumlah Bahan Rp 16,739,500

Jumlah Peralatan -
Rp 16,839,500
Rp 1,683,950
Rp 18,523,450

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 660,000 Rp 973,500
Rp 176,192 Rp 1,254,484
Rp 152,114 Rp 81,153
Rp 44,000 Rp 264,000
Rp 8,000 Rp 8,000
Rp 132,000 Rp 132,000
Rp 47,000 Rp 47,000
Jumlah Bahan Rp 2,760,137

Jumlah Peralatan -
Rp 2,810,137
Rp 281,014
Rp 3,091,150
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 660,000 Rp 1,939,938
Rp 176,192 Rp 2,699,255
Rp 152,114 Rp 141,131
Rp 44,000 Rp 264,000
Rp 8,000 Rp 16,000
Rp 132,000 Rp 132,000
Rp 47,000 Rp 94,000
Jumlah Bahan Rp 5,192,324

Jumlah Peralatan -
Rp 5,242,324
Rp 524,232
Rp 5,766,556

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 600,000 Rp 600,000
Rp 176,192 Rp 824,577
Rp 44,000 Rp 176,000
Rp 8,000 Rp 8,000
Rp 132,000 Rp 132,000
Jumlah Bahan Rp 1,740,577
Jumlah Peralatan -
Rp 1,790,577
Rp 179,058
Rp 1,969,634

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 3,270,116
Rp 198,459 Rp 2,222,736
Rp 95,063 Rp 711,075
Rp 150,000 Rp 450,000
Rp 152,114 Rp 576,510
Rp 44,000 Rp 264,000
Rp 27,000 Rp 162,000
Rp 8,000 Rp 56,000
Rp 162,000 Rp 324,000
Rp 132,000 Rp 264,000
Rp 8,800 Rp 52,800
Jumlah Bahan Rp 8,353,237

Jumlah Peralatan -
Rp 8,453,237
Rp 845,324
Rp 9,298,561

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 5,986,990
Rp 198,459 Rp 2,222,736
Rp 95,063 Rp 1,627,487
Rp 150,000 Rp 150,000
Rp 152,114 Rp 1,314,991
Rp 44,000 Rp 528,000
Rp 27,000 Rp 378,000
Rp 8,000 Rp 144,000
Rp 162,000 Rp 324,000
Rp 132,000 Rp 264,000
Rp 8,800 Rp 123,200
Jumlah Bahan Rp 13,063,404

Jumlah Peralatan -
Rp 13,163,404
Rp 1,316,340
Rp 14,479,744

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 5,116,604
Rp 198,459 Rp 2,222,736
Rp 95,063 Rp 1,399,334
Rp 150,000 Rp 150,000
Rp 152,114 Rp 1,132,029
Rp 44,000 Rp 264,000
Rp 27,000 Rp 324,000
Rp 8,000 Rp 128,000
Rp 162,000 Rp 324,000
Rp 132,000 Rp 264,000
Rp 8,800 Rp 105,600
Jumlah Bahan Rp 11,430,303

Jumlah Peralatan -
Rp 11,530,303
Rp 1,153,030
Rp 12,683,333

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 3,794,528
Rp 198,459 Rp 1,064,711
Rp 95,063 Rp 1,488,000
Rp 150,000 Rp 152,114
Rp 152,114 Rp 221,320
Rp 44,000 Rp 162,000
Rp 27,000 Rp 64,000
Rp 8,000 Rp 1,944,000
Rp 162,000 Rp 264,000
Rp 132,000 Rp 17,600
Rp 8,800 Rp 70,400
Jumlah Bahan Rp 9,242,673

Jumlah Peralatan -
Rp 9,342,673
Rp 934,267
Rp 10,276,940
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 176,192 Rp 2,466,682
Rp 95,063 Rp 1,083,724
Rp 152,114 Rp 509,732
Rp 150,000 Rp 150,000
Rp 27,000 Rp 216,000
Rp 8,000 Rp 32,000
Rp 8,800 Rp 70,400
Jumlah Bahan Rp 4,528,538

Jumlah Peralatan -
Rp 4,578,538
Rp 457,854
Rp 5,036,392

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 2,456,111
Rp 95,063 Rp 577,986
Rp 152,114 Rp 482,200
Rp 150,000 Rp 150,000
Rp 27,000 Rp 108,000
Rp 8,000 Rp 16,000
Rp 8,800 Rp 35,200
Jumlah Bahan Rp 3,825,496
Jumlah Peralatan -
Rp 3,925,496
Rp 392,550
Rp 4,318,046

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 200,000 Rp 200,000
Jumlah Tenaga Kerja Rp 200,000

Rp 176,192 Rp 1,585,724
Rp 95,063 Rp 316,181
Rp 152,114 Rp 280,954
Rp 150,000 Rp 150,000
Rp 27,000 Rp 54,000
Rp 8,000 Rp 16,000
Rp 8,800 Rp 17,600
Jumlah Bahan Rp 2,420,459

Jumlah Peralatan -
Rp 2,620,459
Rp 262,046
Rp 2,882,505

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 200,000 Rp 200,000
Jumlah Tenaga Kerja Rp 200,000
Rp 176,192 Rp 4,813,554
Rp 95,063 Rp 1,083,724
Rp 152,114 Rp 1,102,519
Rp 150,000 Rp 150,000
Rp 27,000 Rp 216,000
Rp 8,000 Rp 32,000
Rp 8,800 Rp 70,400
Jumlah Bahan Rp 7,468,196

Jumlah Peralatan -
Rp 7,668,196
Rp 766,820
Rp 8,435,016

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 10,520,399
Rp 95,063 Rp -
Rp 152,114 Rp 2,314,559
Rp 150,000 Rp 150,000
Rp 27,000 Rp -
Rp 8,000 Rp -
Rp 8,800 Rp -
Jumlah Bahan Rp 12,984,958

Jumlah Peralatan -
Rp 13,084,958
Rp 1,308,496
Rp 14,393,454
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 100,000 Rp 100,000
Jumlah Tenaga Kerja Rp 100,000

Rp 176,192 Rp 3,058,686
Rp 95,063 Rp 760,508
Rp 152,114 Rp 541,372
Rp 150,000 Rp 150,000
Rp 27,000 Rp 162,000
Rp 8,000 Rp 24,000
Rp 8,800 Rp 52,800
Jumlah Bahan Rp 4,749,366

Jumlah Peralatan -
Rp 4,849,366
Rp 484,937
Rp 5,334,302

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 176,192 Rp 898,577
Rp 152,114 Rp 82,141
Jumlah Bahan Rp 980,718

Jumlah Peralatan -
Rp 1,030,718
Rp 103,072
Rp 1,133,790

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 176,192 Rp 422,860
Rp 152,114 Rp 36,507
Jumlah Bahan Rp 459,367

Jumlah Peralatan -
Rp 509,367
Rp 50,937
Rp 560,304

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 50,000 Rp 50,000
Jumlah Tenaga Kerja Rp 50,000

Rp 176,192 Rp 599,051
Rp 152,114 Rp 82,141
Jumlah Bahan Rp 681,193

Jumlah Peralatan -
Rp 731,193
Rp 73,119
Rp 804,312

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 200,000 Rp 200,000
Jumlah Tenaga Kerja Rp 200,000

Rp 176,192 Rp 1,321,437
Rp 152,114 Rp 174,474
Jumlah Bahan Rp 1,495,911

Jumlah Peralatan -
Rp 1,695,911
Rp 169,591
Rp 1,865,502

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 2,795
Rp 85,000 Rp 36,550
Rp 100,000 Rp 430
Rp 75,000 Rp 161
Jumlah Tenaga Kerja Rp 39,936

Rp 20,833 Rp 20,833
Rp 600 Rp 14,400
Rp 250 Rp 6,000
Rp 15,000 Rp 15,000
Jumlah Bahan Rp 56,233
Jumlah Peralatan -
Rp 96,170
Rp 9,617
Rp 105,787

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 11,375
Rp 85,000 Rp 148,750
Rp 100,000 Rp 17,500
Rp 75,000 Rp 675
Jumlah Tenaga Kerja Rp 178,300

Rp 896,500 Rp 300,328
Rp 40,000 Rp 10,000
Rp 700 Rp 8,400
Rp 42,000 Rp 42,000
Rp 50,000 Rp 50,000
Jumlah Bahan Rp 410,728

Jumlah Peralatan -
Rp 589,028
Rp 58,903
Rp 647,930

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 325,000
Rp 85,000 Rp 85,000
Rp 100,000 Rp 10,000
Rp 75,000 Rp 7,500
Jumlah Tenaga Kerja Rp 325,000

Rp 62,500 Rp 62,500
Rp 45,500 Rp 227,500
Rp 49,000 Rp 49,000
Rp 26,100 Rp 9,417
Rp 1,500 Rp 3,000
Rp 25,000 Rp 50,000
Jumlah Bahan Rp 401,417

Jumlah Peralatan -
Rp 726,417
Rp 72,642
Rp 799,059

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja Rp 30,125

Rp 600 Rp 42,000
Rp 1,380 Rp 19,831
Rp 183,333 Rp 7,333
Jumlah Bahan Rp 69,164

Jumlah Peralatan
Rp 99,289
Rp 9,929
Rp 109,218

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja Rp 30,125

Rp 600 Rp 42,000
Rp 1,380 Rp 13,358
Rp 183,333 Rp 8,250
Jumlah Bahan Rp 63,608

Jumlah Peralatan
Rp 93,733
Rp 9,373
Rp 103,107

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja Rp 34,875

Rp 1,380 Rp 10,731
Rp 183,333 Rp 4,217
Jumlah Bahan Rp 14,948
Jumlah Peralatan
Rp 49,823
Rp 4,982
Rp 54,805

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja Rp 34,875

Rp 1,380 Rp 7,154
Rp 183,333 Rp 4,767
Jumlah Bahan Rp 11,921

Jumlah Peralatan
Rp 46,796
Rp 4,680
Rp 51,475

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 26,000
Rp 85,000 Rp 17,000
Rp 100,000 Rp 2,000
Rp 75,000 Rp 1,650
Jumlah Tenaga Kerja Rp 46,650

Rp 1,380 Rp 9,539
Rp 183,333 Rp 6,417
Jumlah Bahan Rp 15,955

Jumlah Peralatan
Rp 62,605
Rp 6,261
Rp 68,866

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 750
Jumlah Tenaga Kerja Rp 23,250

Rp 1,380 Rp 4,485
Jumlah Bahan Rp 4,485

Jumlah Peralatan
Rp 27,735
Rp 2,774
Rp 30,509
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja Rp 81,375

Rp 138,333 Rp 216,077
Rp 1,380 Rp 13,524
Rp 21,000 Rp 27,300
Rp 183,333 Rp 8,250
Jumlah Bahan Rp 265,151

Jumlah Peralatan
Rp 346,526
Rp 34,653
Rp 381,178

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja Rp 81,375

Rp 46,250 Rp 128,113
Rp 1,380 Rp 13,524
Rp 21,000 Rp 27,300
Rp 183,333 Rp 8,250
Jumlah Bahan Rp 177,187
Jumlah Peralatan
Rp 258,562
Rp 25,856
Rp 284,418

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja Rp 81,375

Rp 5,455 Rp 60,600
Rp 1,380 Rp 13,800
Rp 21,000 Rp 31,500
Rp 183,333 Rp 8,250
Jumlah Bahan Rp 114,150

Jumlah Peralatan
Rp 195,525
Rp 19,553
Rp 215,078

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja 81,375.00
Rp 2,200 Rp 55,000
Rp 1,380 Rp 13,800
Rp 21,000 Rp 31,500
Rp 183,333 Rp 8,250
Jumlah Bahan 108,550.00

Jumlah Peralatan
Rp 189,925
Rp 18,993
Rp 208,918

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja 81,375.00

Rp 11,667 Rp 72,917
Rp 1,380 Rp 13,800
Rp 21,000 Rp 31,500
Rp 183,333 Rp 8,250
Jumlah Bahan 126,466.67

Jumlah Peralatan
Rp 207,842
Rp 20,784
Rp 228,626
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja 81,375.00

Rp 3,400 Rp 68,000
Rp 1,380 Rp 13,800
Rp 21,000 Rp 31,500
Rp 183,333 Rp 8,250
Jumlah Bahan 121,550.00

Jumlah Peralatan
Rp 202,925
Rp 20,293
Rp 223,218

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 45,500
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 2,625
Jumlah Tenaga Kerja 81,375.00

Rp 46,250 Rp 128,113
Rp 1,380 Rp 13,800
Rp 21,000 Rp 31,500
Rp 183,333 Rp 8,250
Rp 4,167 Rp 4,167
Jumlah Bahan 185,829.17
Jumlah Peralatan
Rp 267,204
Rp 26,720
Rp 293,925

M BOARD

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 22,750
Rp 85,000 Rp 29,750
Rp 100,000 Rp 3,500
Rp 75,000 Rp 1,350
Jumlah Tenaga Kerja 57,350.00

Rp 6,250 Rp 21,250
Rp 5,000 Rp 6,000
Rp 2,500 Rp 2,500
Jumlah Bahan 29,750.00

Jumlah Peralatan
Rp 87,100
Rp 8,710
Rp 95,810

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 9,750
Rp 85,000 Rp 21,250
Rp 100,000 Rp 2,500
Rp 75,000 Rp 5,625
Jumlah Tenaga Kerja 39,125.00

Rp 37,000 Rp 125,800
Rp 72,000 Rp 86,400

Jumlah Bahan 212,200.00

Jumlah Peralatan
Rp 251,325
Rp 25,133
Rp 276,458

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 4,250
Rp 100,000 Rp 500
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 11,625.00

Rp 153,000 Rp 55,692
Rp 42,500 Rp 4,675
Jumlah Bahan 60,367.00

Jumlah Peralatan
Rp 71,992
Rp 10,799
Rp 82,791

ETARA
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 4,250
Rp 100,000 Rp 500
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 11,625.00

Rp 66,000 Rp 24,024
Rp 42,500 Rp 4,675
Jumlah Bahan 28,699.00

Jumlah Peralatan
Rp 40,324
Rp 4,032
Rp 44,356

W SETARA

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 4,250
Rp 100,000 Rp 500
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 11,625.00

Rp 6,250 Rp 21,250
Rp 5,000 Rp 6,000
Rp 66,000 Rp 47,520
Rp 200 Rp 5,000
Rp 1,500 Rp 6,000
Rp 15,000 Rp 1,500
Rp 3,300 Rp 429
Jumlah Bahan 87,699.00
Jumlah Peralatan
Rp 99,324
Rp 9,932
Rp 109,256

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 3,250
Rp 85,000 Rp 4,250
Rp 100,000 Rp 500
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 8,225.00

Rp 4,500 Rp 4,725
Rp 42,500 Rp 425
Jumlah Bahan 5,150.00

Jumlah Peralatan
Rp 13,375
Rp 1,338
Rp 14,713

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 38,250
Rp 100,000 Rp 1,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja 56,000.00

Rp 15,000 Rp 42,000
Rp 8,500 Rp 43,350
Rp 400 Rp 10,000
Rp 350 Rp 12,250
Rp 1,500 Rp 1,500
Jumlah Bahan 109,100.00

Rp 2,000 Rp 2,000
Rp 4,500 Rp 4,500
Rp 4,000 Rp 4,000
Jumlah Peralatan 10,500.00
Rp 175,600
Rp 17,560
Rp 193,160

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 7,800
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 450
Jumlah Tenaga Kerja 13,950.00

Rp 36,500 Rp 59,130
Rp 26,100 Rp 522
Jumlah Bahan 59,652.00

Jumlah Peralatan
Rp 73,602
Rp 7,360
Rp 80,962
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 16,375.00

Rp 20,900 Rp 20,900
Rp 28,200 Rp 1,128
Jumlah Bahan 22,028.00

Jumlah Peralatan
Rp 38,403
Rp 3,840
Rp 42,243

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 34,000
Rp 100,000 Rp 2,500
Rp 75,000 Rp 750
Jumlah Tenaga Kerja 50,250.00

Rp 48,900 Rp 51,345
Rp 26,000 Rp 390
Rp 2,300,000 Rp 43,700
Jumlah Bahan 95,435.00
Jumlah Peralatan
Rp 145,685
Rp 14,569
Rp 160,254

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 9,750
Rp 85,000 Rp 21,250
Rp 100,000 Rp 25,000
Rp 75,000 Rp 5,625
Jumlah Tenaga Kerja 61,625.00

Rp 28,125 Rp 29,531
Rp 26,100 Rp 1,566
Jumlah Bahan 31,097.25

Jumlah Peralatan
Rp 92,722
Rp 9,272
Rp 101,994

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 38,250
Rp 100,000 Rp 1,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja 56,000.00
Rp 8,500 Rp 21,250

Rp 350 Rp 1,750

Jumlah Bahan 23,000.00

Jumlah Peralatan -
Rp 79,000
Rp 7,900
Rp 86,900

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,300
Rp 85,000 Rp 5,355
Rp 100,000 Rp 630
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 7,510.00

Rp 67,500 Rp 6,750
Rp 67,500 Rp 17,550
Rp 15,000 Rp 15,000
Jumlah Bahan 39,300.00

Jumlah Peralatan
Rp 46,810
Rp 4,681
Rp 51,491
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 390,000
Rp 85,000 Rp 1,530,000
Rp 100,000 Rp 160,000
Rp 75,000 Rp 22,500
Jumlah Tenaga Kerja 2,102,500.00

Rp 3,800,000 Rp 4,560,000
Rp 18,000 Rp 22,500
Rp 15,000 Rp 15,000
Jumlah Bahan 4,597,500.00

Jumlah Peralatan
Rp 6,700,000
Rp 670,000
Rp 7,370,000

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 65,000
Rp 85,000 Rp 255,000
Rp 100,000 Rp 30,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja 353,750.00

Rp 3,700,000 Rp 148,000
Rp 15,000 Rp 7,500
Jumlah Bahan 155,500.00

Jumlah Peralatan
Rp 509,250
Rp 50,925
Rp 560,175

KELAS II

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 52,000
Rp 85,000 Rp 204,000
Rp 100,000 Rp 24,000
Rp 75,000 Rp 3,000
Jumlah Tenaga Kerja 283,000.00

Rp 3,700,000 Rp 88,800
Rp 15,000 Rp 4,500
Jumlah Bahan 93,300.00

Jumlah Peralatan
Rp 376,300
Rp 37,630
Rp 413,930

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 435,500
Rp 85,000 Rp 1,708,500
Rp 100,000 Rp 201,000
Rp 75,000 Rp 25,125
Jumlah Tenaga Kerja 2,370,125.00

Rp 3,800,000 Rp 4,180,000
Rp 110,000 Rp 1,650,000
Rp 18,000 Rp 54,000
Jumlah Bahan 4,234,000.00
Jumlah Peralatan
Rp 6,604,125
Rp 660,413
Rp 7,264,538

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 16,375.00

Rp 1,700,000 Rp 17,850
Rp 2,200,000 Rp 7,920
Rp 18,000 Rp 1,800
Jumlah Bahan 27,570.00

Jumlah Peralatan
Rp 43,945
Rp 4,395
Rp 48,340

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 6,500
Rp 85,000 Rp 17,000
Rp 100,000 Rp 2,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 25,875.00

Rp 2,300,000 Rp 23,000
Rp 18,000 Rp 1,800
Jumlah Bahan 24,800.00

Jumlah Peralatan
Rp 50,675
Rp 5,068
Rp 55,743

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 975
Rp 100,000 Rp 15,000
Rp 100,000 Rp 1,500
Rp 75,000 Rp 60
Jumlah Tenaga Kerja 17,535.00

Rp 44,000 Rp 44,000
Jumlah Bahan 44,000.00

Jumlah Peralatan
Rp 61,535
Rp 6,154
Rp 67,689
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 650
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 38
Jumlah Tenaga Kerja 10,187.50

Rp 27,000 Rp 27,000
Jumlah Bahan 27,000.00

Jumlah Peralatan
Rp 37,188
Rp 3,719
Rp 40,906

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 975
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 600
Jumlah Tenaga Kerja 15,825.00

Rp 8,800 Rp 8,800
Jumlah Bahan 8,800.00

Jumlah Peralatan
Rp 24,625
Rp 2,463
Rp 27,088
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 650
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 10,525.00

Rp 47,000 Rp 47,000
Jumlah Bahan 47,000.00

Jumlah Peralatan
Rp 57,525
Rp 5,753
Rp 63,278

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 650
Rp 85,000 Rp 42,500
Rp 100,000 Rp 5,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 48,525.00

Rp 132,000 Rp 132,000
Jumlah Bahan 132,000.00

Jumlah Peralatan
Rp 180,525
Rp 18,053
Rp 198,578

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 975
Rp 85,000 Rp 12,750
Rp 100,000 Rp 1,500
Rp 75,000 Rp 600
Jumlah Tenaga Kerja 15,825.00

Rp 8,000 Rp 8,000
Jumlah Bahan 8,000.00

Jumlah Peralatan
Rp 23,825
Rp 2,383
Rp 26,208

IS CAT PENUTUP (INTERIOR)

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,300
Rp 85,000 Rp 5,355
Rp 100,000 Rp 630
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 7,510.00

Rp 3,300 Rp 330
Rp 36,000 Rp 3,600
Rp 36,000 Rp 9,360
Rp 5,000 Rp 5,000
Jumlah Bahan 18,290.00

Jumlah Peralatan
Rp 25,800
Rp 2,580
Rp 28,380

PIS CAT PENUTUP (EXTERIOR)

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,300
Rp 85,000 Rp 5,355
Rp 100,000 Rp 630
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 7,510.00

Rp 3,300 Rp 330
Rp 67,500 Rp 6,750
Rp 67,500 Rp 17,550
Rp 5,000 Rp 5,000
Jumlah Bahan 29,630.00

Jumlah Peralatan
Rp 37,140
Rp 3,714
Rp 40,854

PIS CAT PENUTUP (INTERIOR)

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Rp 65,000 Rp 1,300
Rp 85,000 Rp 5,355
Rp 100,000 Rp 630
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 7,510.00

Rp 3,100 Rp 310
Rp 36,000 Rp 3,600
Rp 36,000 Rp 9,360
Rp 5,000 Rp 5,000
Jumlah Bahan 18,270.00

Jumlah Peralatan
Rp 25,780
Rp 2,578
Rp 28,358

T DASAR, 2 LAPIS CAT PENUTUP

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 4,550
Rp 85,000 Rp 765
Rp 100,000 Rp 600
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 6,140.00

Rp 17,200 Rp 3,440
Rp 15,000 Rp 2,250
Rp 59,000 Rp 10,030
Rp 59,000 Rp 15,340
Rp 9,000 Rp 90
Rp 3,000 Rp 90
Rp 9,000 Rp 1,800
Jumlah Bahan 33,040.00
Jumlah Peralatan
Rp 39,180
Rp 3,918
Rp 43,098

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 10,400
Rp 85,000 Rp 13,600
Rp 100,000 Rp 1,600
Rp 75,000 Rp 225
Jumlah Tenaga Kerja 25,825.00

Rp 58,000 Rp 8,700
Rp 15,000 Rp 750
Rp 9,000 Rp 900
Jumlah Bahan 10,350.00

Jumlah Peralatan
Rp 36,175
Rp 3,618
Rp 39,793

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 214,500
Rp 85,000 Rp 93,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 12,000
Jumlah Tenaga Kerja 321,000.00

Rp 2,400,000 Rp 2,400,000
Rp 125,000 Rp 125,000
Jumlah Bahan 2,525,000.00

Jumlah Peralatan
Rp 2,846,000
Rp 284,600
Rp 3,130,600

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 65,000
Rp 85,000 Rp 127,500
Rp 100,000 Rp 15,000
Rp 75,000 Rp 12,000
Jumlah Tenaga Kerja 219,500.00

Rp 186,000 Rp 186,000
Rp 1,380 Rp 8,280
Rp 183,333 Rp 1,833
Jumlah Bahan 187,833.33

Jumlah Peralatan
Rp 407,333
Rp 40,733
Rp 448,067
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 65,000
Rp 85,000 Rp 85,000
Rp 100,000 Rp 10,000
Rp 75,000 Rp 3,750
Jumlah Tenaga Kerja 163,750.00

Rp 1,700,000 Rp 1,700,000
Rp 1,380 Rp 8,280
Rp 183,333 Rp 1,833
Rp 25,000 Rp 25,000
Jumlah Bahan 1,735,113.33

Jumlah Peralatan
Rp 1,898,863
Rp 189,886
Rp 2,088,750

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 78,000
Rp 85,000 Rp 123,250
Rp 85,000 Rp 12,750
Rp 75,000 Rp 4,500
Jumlah Tenaga Kerja 218,500.00

Rp 1,600,000 Rp 1,920,000
Rp 1,380 Rp 8,280
Rp 183,333 Rp 1,833
Rp 50,000 Rp 50,000
Jumlah Bahan 1,980,113.33
Jumlah Peralatan
Rp 2,198,613
Rp 219,861
Rp 2,418,475

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 650
Rp 85,000 Rp 34,000
Rp 100,000 Rp 4,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 39,025.00

Rp 80,000 Rp 80,000
Rp 11,800 Rp 295
Jumlah Bahan 80,295.00

Jumlah Peralatan
Rp 119,320
Rp 11,932
Rp 131,252

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 1,950
Rp 85,000 Rp 25,500
Rp 100,000 Rp 3,000
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja 31,575.00

Rp 625,000 Rp 625,000
Rp 50,000 Rp 50,000
Jumlah Bahan 675,000.00

Jumlah Peralatan
Rp 706,575
Rp 70,658
Rp 777,233

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 650
Rp 85,000 Rp 8,500
Rp 100,000 Rp 1,000
Rp 75,000 Rp 375
Jumlah Tenaga Kerja 10,525.00

Rp 64,000 Rp 64,000
Jumlah Bahan 64,000.00

Jumlah Peralatan
Rp 74,525
Rp 7,453
Rp 81,978

0CM

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 208,000
Rp 85,000 Rp 97,750
Rp 100,000 Rp 1,100
Rp 75,000 Rp 1,200
Jumlah Tenaga Kerja 308,050.00

Rp 600 Rp 42,000
Rp 1,380 Rp 106,260
Rp 183,333 Rp 23,833
Rp 233,333 Rp 21,000
Rp 200,000 Rp 4,000
Rp 18,000 Rp 46,800
Jumlah Bahan 243,893.33

Jumlah Peralatan
Rp 551,943
Rp 55,194
Rp 607,138

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 19,500
Rp 85,000 Rp 38,250
Rp 100,000 Rp 4,500
Rp 75,000 Rp 1,125
Jumlah Tenaga Kerja 63,375.00

Rp 310,000 Rp 310,000
Rp -
Jumlah Bahan 310,000.00

Jumlah Peralatan
Rp 373,375
Rp 37,338
Rp 410,713
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 38,870
Rp 85,000 Rp 23,715
Rp 100,000 Rp 2,790
Rp 75,000 Rp 1,650
Jumlah Tenaga Kerja 67,025.00

Rp 200,000 Rp 26,400
Rp 1,380 Rp 21,459
Rp 183,333 Rp 15,840
Jumlah Bahan 63,699.00

Jumlah Peralatan
Rp 130,724
Rp 13,072
Rp 143,796

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 4,625 Rp 5,550
Rp 10,000 Rp 10,000
Jumlah Bahan 15,550.00
Jumlah Peralatan
Rp 44,800
Rp 4,480
Rp 49,280

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 38,000 Rp 45,600
Rp 10,000 Rp 10,000
Jumlah Bahan 55,600.00

Jumlah Peralatan
Rp 84,850
Rp 8,485
Rp 93,335

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 6,375 Rp 7,650
Rp 10,000 Rp 10,000
Jumlah Bahan 17,650.00

Jumlah Peralatan
Rp 46,900
Rp 4,690
Rp 51,590

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 8,625 Rp 10,350
Rp 10,000 Rp 10,000
Jumlah Bahan 20,350.00

Jumlah Peralatan
Rp 49,600
Rp 4,960
Rp 54,560

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 63,000 Rp 75,600
Rp 10,000 Rp 10,000
Jumlah Bahan 85,600.00

Jumlah Peralatan
Rp 114,850
Rp 11,485
Rp 126,335

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 20,000 Rp 24,000
Rp 10,000 Rp 10,000
Jumlah Bahan 34,000.00

Jumlah Peralatan
Rp 63,250
Rp 6,325
Rp 69,575
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 23,400
Rp 85,000 Rp 5,100
Rp 100,000 Rp 600
Rp 75,000 Rp 150
Jumlah Tenaga Kerja 29,250.00

Rp 28,250 Rp 33,900
Rp 10,000 Rp 10,000
Jumlah Bahan 43,900.00

Jumlah Peralatan
Rp 73,150
Rp 7,315
Rp 80,465

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 12,300 Rp 12,300
Jumlah Bahan 12,300.00

Jumlah Peralatan
Rp 12,300
Rp 1,230
Rp 13,530
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp -
Rp -
Jumlah Tenaga Kerja -

Rp 65,000 Rp 65,000
Rp -
Jumlah Bahan 65,000.00

Jumlah Peralatan
Rp 65,000
Rp 6,500
Rp 71,500

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 34,200 Rp 34,200
Rp -
Jumlah Bahan 34,200.00

Jumlah Peralatan
Rp 34,200
Rp 3,420
Rp 37,620
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 20,300 Rp 20,300
Rp -
Jumlah Bahan 20,300.00

Jumlah Peralatan
Rp 20,300
Rp 2,030
Rp 22,330

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 51,000
Jumlah Tenaga Kerja 64,000.00

Rp 980,000 Rp 88,200
Rp 1,825 Rp 183
Rp 500 Rp 500
Jumlah Bahan 88,882.50

Jumlah Peralatan
Rp 152,883
Rp 15,288
Rp 168,171
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 51,000
Jumlah Tenaga Kerja 64,000.00

Rp 690,000 Rp 62,100
Rp 500 Rp 500
Jumlah Bahan 62,600.00

Jumlah Peralatan
Rp 126,600
Rp 12,660
Rp 139,260

PS

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 500,000 Rp 500,000
Jumlah Bahan 500,000.00

Jumlah Peralatan
Rp 500,000
Rp 50,000
Rp 550,000
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 230,000 Rp 230,000
Jumlah Bahan 230,000.00

Jumlah Peralatan
Rp 230,000
Rp 23,000
Rp 253,000

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 45,000 Rp 45,000
Rp 35,000 Rp 35,000
Jumlah Bahan 80,000.00

Jumlah Peralatan
Rp 80,000
Rp 8,000
Rp 88,000
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 40,500 Rp 40,500
Rp 35,000 Rp 35,000
Jumlah Bahan 75,500.00

Jumlah Peralatan
Rp 75,500
Rp 7,550
Rp 83,050

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 29,700 Rp 29,700
Rp 35,000 Rp 35,000
Jumlah Bahan 64,700.00

Jumlah Peralatan
Rp 64,700
Rp 6,470
Rp 71,170

WARM
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 42,000 Rp 42,000
Rp 1,000 Rp 1,000
Jumlah Bahan 43,000.00

Jumlah Peralatan
Rp 43,000
Rp 4,300
Rp 47,300

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp -
Rp 85,000 Rp -
Jumlah Tenaga Kerja -

Rp 980,000 Rp -
Rp 2,800,000 Rp -
Rp 1,825 Rp -
Rp 1,000 Rp -
Jumlah Bahan -

Jumlah Peralatan
Rp -
Rp -
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 64,600 Rp 64,600
Jumlah Bahan 64,600.00

Jumlah Peralatan
Rp 64,600
Rp 6,460
Rp 71,060

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 42,600 Rp 42,600
Jumlah Bahan 42,600.00

Jumlah Peralatan
Rp 42,600
Rp 4,260
Rp 46,860
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 41,500 Rp 41,500
Jumlah Bahan 41,500.00

Jumlah Peralatan
Rp 41,500
Rp 4,150
Rp 45,650

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Jumlah Tenaga Kerja -

Rp 150,000 Rp 150,000
Jumlah Bahan 150,000.00

Jumlah Peralatan
Rp 150,000
Rp 15,000
Rp 165,000

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Jumlah Tenaga Kerja -

Rp 41,500 Rp 41,500
Jumlah Bahan 41,500.00

Jumlah Peralatan
Rp 41,500
Rp 4,150
Rp 45,650

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 51,000
Jumlah Tenaga Kerja 64,000.00

Rp 550,000 Rp 55,000
Rp 1,825 Rp 456
Rp 1,500 Rp 1,500
Jumlah Bahan 56,956.25

Jumlah Peralatan
Rp 120,956
Rp 12,096
Rp 133,052

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


Rp 65,000 Rp 13,000
Rp 85,000 Rp 51,000
Jumlah Tenaga Kerja 64,000.00

Rp 2,190,000 Rp 438,000
Rp 1,825 Rp 456
Rp 1,500 Rp 1,500
Jumlah Bahan 439,956.25

Jumlah Peralatan
Rp 503,956
Rp 50,396
Rp 554,352

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 65,000 Rp 13,000
Rp 85,000 Rp 51,000
Jumlah Tenaga Kerja 64,000.00

Rp 210,000 Rp 42,000
Rp 1,825 Rp 456
Rp 1,500 Rp 1,500
Jumlah Bahan 43,956.25

Jumlah Peralatan
Rp 107,956
Rp 10,796
Rp 118,752
HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Rp 85,000 Rp 7,650
Rp 100,000 Rp 900
Rp 65,000 Rp 3,510
Rp 75,000 Rp 2,025
Jumlah Tenaga Kerja 14,085.00

Rp 110,000 Rp 121,000
Rp 183,333 Rp 22,000
Jumlah Bahan 143,000.00

Jumlah Peralatan
Rp 157,085
Rp 15,709
Rp 172,794
DAFTAR HARGA BAHAN TAHUN 2015
NAMA : ANDI NUR ALAN
STAMBUK : E3B1 13 042
JUDUL TUGAS AK : Perencanaan Kantor Badan Pertanahan Nasional Kabupaten Konawe
TAHUN : 2016

HARGA SATUAN
NO URAIAN
(Rp)
I UPAH
1 Tukang Batu Rp 85,000
2 Tukang Kayu Rp 85,000
3 Tukang Besi Rp 85,000
4 Tukang Cat Rp 85,000
5 Tukang Pipa Rp 85,000
6 Tukang Listrik Rp 85,000
7 Tukang Las Konstruksi Rp 85,000
8 Tukang Aluminium Rp 85,000
9 Pekerja Rp 65,000
10 Kepala tukang Rp 100,000
11 Mandor Rp 75,000
II BAHAN
A Tanah Pasir Dan Batu
1 Tanah Urugan (didatangkan) Rp -
2 Tanah Timbunan Pilihan Rp -
3 Pasir Urug Rp -
4 Pasir Pasang Pohara Rp -
5 Pasir Beton Unaha Rp -
6 Kerikil Beton Rp -
7 Batu Pecah/Suplit 1/2 Rp -
8 Batu Gunung Moramo Rp -
9 Batu Bata Rp -

B Bahan Semen
1 Portland Cemen ( PC ) Tonasa Rp -
2 Semen Warna Nat Tegel Rp 21,000
3 Plamuur A Plus Rp -

C Bahan Kayu
1 Balok Kayu Kls II Kelapi / Setara 4m Rp 4,000,000
2 Balok Kayu Kls II Bisulo / Setara 4m Rp 2,300,000
3 Balok Kayu Kls II Meranti / Setara 4m Rp 3,800,000
4 Balok Kayu Kls II Bitti / Setara 4m Rp 3,500,000
5 Balok Kayu Kls II Ponto / Setara 4m Rp 3,800,000
6 Kaso 5/7 Kls II Ponto Merica 4m Rp 1,700,000
7 Reng 2/3 Kls II 4m Rp 2,200,000
8 Papan Kayu Kls I (Jati) 4m Rp 3,700,000
9 Papan Kayu Kls II 4m Rp 2,300,000
10 Kayu dolken diameter 8 - 10 cm Rp 3,000
11 Papan Kayu Kelas III Rp 2,100,000
12 Multipleks 3 mm Ex. Palem Permukaan Rata Rp 65,000
13 Multipleks 6 mm Ex. Palem Permukaan Rata Rp 90,000
14 Multipleks 9 mm Ex. Palem Permukaan Rata Rp 135,000
15 Multipleks 12 mm Ex. Palem Permukaan Rata Rp 185,000
16 Multipleks 15 mm Ex. Palem Permukaan Rata Rp 230,000
17 HPL Taco Type AA Rp 110,000
18 Daun Pintu Multipleks 15mm Dobel Rp 660,000
19 Multipleks sungkai 3 mm Rp 80,000

D Bahan Gypsum
1 Gypsum Board Merk Jaya Board 9mm / Setara Rp 66,000
2 GRC Board Merk Versa Board 9mm / Setara Rp 153,000
3 List Gypsum Profil Minimalis 10cm Rp 4,500
4 Gypsum Board Merk Gyprock 9mm / Setara Rp 57,000
5 Partisi HPL Rp 6,000,000

E Bahan Kramik dan Granite


1 Tegel Granit 60 x 60 Cm Merk Dux Rp -
2 Tegel Granit 80 x 80 Cm Merk Luana Rp 138,333
3 Tegel Granit 20 x 20 Cm Merk Ikad Anti Slip Rp -
4 Tegel Keramik 30 x 30 Cm Merk Ikad Rp -
5 Tegel Keramik 30 x 30 Cm Merk Ikad Anti Slip Rp -
6 Tegel Keramik 40 x 40 Cm Merk Ikad Rp -
7 Tegel Keramik Dinding 25 x 20 Cm Merk Ikad Rp 3,400
8 Tegel Keramik Dinding 30 x 20 Cm Merk Ikad Rp -
9 Tegel Keramik Dinding 40 x 10 Cm Merk Ikad Rp -
10 Tegel Keramik Batu Tempel Merk Centro 15 x 4 Rp -
11 Pasangan Paving Block Rp 70,000

F Bahan Penutup Atap


1 Seng gelombang 6 kaki Rp 30,000
2 Seng Plat BJLS 20 Lebar 50 cm Rp 48,900
3 Atap Zincalume (Sakura Roof) Rp 36,500
4 Nok sakura roof panjang 100 cm Rp 20,900
5 Atap polycarbonat Rp 475,000
6 Main Truss C.75-75 Rp 15,000
7 Roof Bottom/Reng R.33 - 0.45 Rp 8,500
8 Self Drilling Screw dia 6 x 20 mm( Truss Screw) Rp 400
9 Self Drilling Screw dia 4 x 16 mm( Roof Bottom Rp 350
10 Dynabol dia 12 x 120 mm Rp 1,500
11 Atap Onduvilla 40 x 106 cm Rp 50,000
12 Nok Onduvilla Panjang 100m Rp 30,000
13 Varge Piece Onduvilla Rp 25,000
14 Speedy Screw Rp 400
15 Aksesoris Rp 25,000
16 Talang Aluminium BJLS33 Rp 18,000
17 List Plank Kalsi Board 30cm Rp 28,125
18 Waterproofing Sika Rp 733,630

G Bahan Besi
1 Besi Beton Variabel Rp 18,000
2 Kawat Bindrat Rp 24,200
3 Paku Campur Rp 18,000
4 Besi Siku L 60.60.6 Rp 110,000
5 Paku tripleks Rp 26,000
6 Paku Seng Rp 28,200
7 Paku Sakura Roof Rp 26,100
8 Paku sekrup Rp 26,100
9 Angker/Baut/plat pengIkad kuda-kuda Rp 12,500
10 Pintu Plat 3 mm Rp 750,000
11 Skrup Fisher Rp 700
12 Fisher S6 Rp 9,000
13 Skrup Gypsum Hitam Rp -
14 Baja WF 250 Rp 15,500
15 Baja Gordeng Kanal C 150 2,3 Rp 12,500
16 Skrup Gypsum Hitam Rp 200
17 Cotton plaster Rp 15,000
18 Plat Simpul Rp 25,000
19 Baut 12mm Rp 1,500
20 Railing Tangga Stenlissteel Rp 500,000
21 Besi Holow 4x4 cm , 3mm Rp 42,000

H Bahan Kunci dan Penggantung


1 Engsel Pintu Merk Solid Rp -
2 Engsel Jendela Merk Solid Rp -
3 Kait Angin Merk Solid Rp -
4 Hendel Pintu Merk Vintage + Kunci Rp -
5 Door Stoper Merk Solid Rp -
6 Grendel Merk Vintage Rp 8,000
7 Hendel Pintu Kaca Tempred / 12mm Merk Soli Rp -
8 Kunci Pintu Kaca Tempred / 12mm Merk Solid Rp 510,000
9 Engsel Tanam Pintu Kaca Merk Solid Rp 500,000
10 Door Closer Merk Solid Rp 162,000
11 Kunci Tanam Pintu Rp 130,000

I Bahan Cat dan Finishing


1 Cat Meni Seng/Besi Rp 16,500
2 Meni kayu Rp 17,200
3 Minyak cat Rp 3,000
4 Minyak bekisting Rp 10,900
5 Kuas Rp 9,000
6 Kuas Roll Rp 15,000
7 Cat Kilap Kayu Merek Altex Rp 59,000
8 Cat Vernis Kayu Rp 58,000
9 Amplas Kayu Rp 9,000
10 Dempul Kayu Merk Boyo Rp 15,000
11 Cat Tembok Interior Vinilex Atau Setara Rp -
12 Cat Tembok Exterior Vinilex Atau Setara Rp -
13 Lem Fox Rp 15,000
14 Kapur Tonasa Rp 5,800
15 Cornis Plafond Rp -
16 Thinner Cobra Rp 40,000
17 Dempul Alfaglos Rp 42,000
18 Cat Nippe 2000 warna Merah Rp 85,000
19 Cat dasar Epoxy Suzuka Rp 40,000
20 Dempul impra Rp 45,000
21 Cat dasar impra Rp 42,000
22 Thinner Impra Rp 32,000
23 Clear Sanding Sealer impra Rp 75,000
24 Melamik Clear impra Rp 85,000
25 Amplas Rp 1,000
26 Harga Permeter Duco Portal Rp 1,100,000
27 Material Primer Rp 7,500
28 Waterproofing Membrane Rp 45,600
29 No Drop Rp -

J Bahan Kaca
1 Kaca Polos 5 mm Rp 110,000
2 Kaca Cermin 5 mm Rp 115,000
3 Kaca Polos 8 mm Rp 400,000
4 Kaca Tempred 12mm Rp -
5 Sealant Rp 40,000

K Bahan Sanitair
1 Kran air crom crystal Merk Onda Rp 80,000
2 Floor Drain staenlies steel Merk Onda Rp 64,000
3 Closed Jongkok + accecories Merk Toto Rp 186,000
4 Closed Duduk + accecories Merk Toto Rp 2,400,000
5 Wastafel lengkap, Kran + accecories Merk Toto Rp 1,600,000
6 Wastafel Cuci Piring + accessories Rp 625,000
7 Bak air fibre glass 70 x 70 x 66 cm Rp 310,000
8 Seal tape Rp 11,800
9 Tower staenlies steel 1500 ltr Merk Tirta Rp 4,000,000
10 Urinoir + accecories Merk Toto Rp 1,700,000
11 Jet Spray Merk Toto Rp 209,000
12 Stop Kran Rp 132,000
13 Fan Shower Merk Toto Rp 238,000
14 Shoap Holder Kramik Ex. Toto Rp 154,000
15 Water Drain Rp 50,000
16 Shower Fan Ex. Toto Rp 186,000

L Bahan Pipa, Pompa, Dan Aluminium


1 Pipa Ex. Maspion type C dia 5/8" Rp -
2 Pipa Ex. Wavin type AW dia 1/2" Rp -
3 Pipa Ex. Wavin type AW dia 3/4" Rp -
4 Pipa Ex. Wavin type AW dia 1" Rp -
5 Pipa Ex. Wavin type AW dia 1 1/2" Rp -
6 Pipa Ex. Wavin type AW dia 2" Rp -
7 Pipa Ex. Wavin type AW dia 2 1/2" Rp -
8 Pipa Ex. Wavin type AW dia 3" Rp -
9 Pipa Ex. Wavin type AW dia 4" Rp -
10 Staenlies steel 2" Rp -
11 Staenlies steel 1/2" Rp -
12 Staenlies steel 3/4" Rp -
13 Pipa Galvanis 6" Rp -
14 Pipa Galvanis 4" Rp -
15 Pipa Galvanis 3,5" Rp -
16 Pipa Galvanis 3" Rp -
17 Pipa Galvanis 2,5" Rp -
18 Besi Hollow 4/4 Rp -
19 Besi Hollow 4/2 Rp -
20 Aluminium Composite Seven (Alumetal) Rp 800,000
21 Aluminium 5/10 Rp -
22 Aluminium 5/5 Rp -
23 Aluminium 3/5 Rp -
24 Elbow Ex. Maspion 5/8 Rp 300
25 Elbow Ex. Ucika 1/2" Rp 2,500
26 Elbow Ex. Ucika 3/4" Rp 3,000
27 Elbow Ex. Ucika 1" Rp 4,000
28 Elbow Ex. Ucika 1 1/2" Rp 9,500
29 Elbow Ex. Ucika 1 1/4" Rp 7,000
30 Elbow Ex. Ucika 2" Rp 14,500
31 Elbow Ex. Ucika 2 1/2" Rp 22,000
32 Elbow Ex. Ucika 3" Rp 37,000
33 Elbow Ex. Ucika 4" Rp 72,000
34 Tee Ex. Ucika 1/2" Rp 2,500
35 Tee Ex. Ucika 3/4" Rp 3,000
36 Tee Ex. Ucika 1" Rp 4,000
37 Tee Ex. Ucika 1 1/2" Rp 9,500
38 Tee Ex. Ucika 1 1/4" Rp 7,000
39 Tee Ex. Ucika 2" Rp 14,500
40 Tee Ex. Ucika 2 1/2" Rp 22,000
41 Tee Ex. Ucika 3" Rp 37,000
42 Tee Ex. Ucika 4" Rp 72,000
43 Lem Pipa PVC Rp 28,000
44 Pompa Ex. Shimizu Media Bawah Tower Rp 1,145,000
45 Pompa Ex. Grunfos Media Sumur Bor Rp 5,390,000
46 Open Back 4" Rp 59,337
47 Penutup Lurus Open Back 4" Rp 21,575
48 Hollow 1/2 x 3/4 Rp -
49 Spycoat Rp 10,787
50 Skrup Aluminium Rp 600
51 Baut Fixer Rp 700
52 Paku Rivet Rp 250
53 Karet C Rp 6,462
54 Profil Aluminium Swing Rp 79,200
55 Profil Batang Kesmen Aluminium Rp 32,362
56 Daun Pintu Aluminium Full Rp 600,000
57 Penggantung Kesmen Rp 150,000
58 List U al ` Rp -
F
M Bahan Instalasi
1 Saklar Ganda Merk Panasonic Mata Kucing Rp 34,200
2 Saklar Tunggal Merk Panasonic Mata Kucing Rp 20,300
3 Stop Kontak Merk Panasonic Rp 12,300
4 Stop Kontak Lantai Panasonic / Setara Tutup Rp 65,000
5 Stop Kontak TV Merk Panasonic Rp 41,500
6 Stop Kontak Data Merk Panasonic Rp 64,600
7 Stop Kontak Telepon Merk Panasonic Rp 42,600
8 Rumah Lampu 4" Merk Mikawa Rp 35,000
9 Lampu TL Ex. Philips Tornado 24 Watt Rp 45,000
10 Lampu TL Ex. Philips Tornado 20 Watt Rp 40,500
11 Lampu TL Ex. Philips 18 Watt Rp 29,700
12 Lampu RM 120cm + 2 Lampu TL Philips 36 WattRp 500,000
13 Lampu RM 60cm + 2 Lampu TL Philips 18 Watt Rp 230,000
14 Lampu TL Philips Panjang 60cm 18 Watt White Rp 10,600
15 Lampu TL Philips Panjang 120cm 36 Watt Whit Rp 12,200
16 Lampu TL Osiwa Panjang 90cm Warm + Fiting Rp 42,000
17 Travo BTA Philips Rp 38,500
18 KWH Meter Rp 5,000,000
19 Instalasi listrik Rp 100,000
20 Kabel NYM Ex. Eterna White 2 x 2.5mm (Stop K Rp 980,000
21 Kabel NYM Ex. Eterna White 2 x 1.5mm (Lampu Rp 690,000
22 Kabel EAA 4 Urat (Telepon) Rp 210,000
23 Kabel RJ 45 Cat 6 1000EET (Data) Rp 2,190,000
24 Kabel Antena Rp 550,000
25 Penyambungan instalasi listrik PLN Rp 7,000,000
26 Panel BOX MCB + Isi Ex. Sneider Rp 2,800,000
27 Grounding System Kelistrikan Rp 8,000,000
28 Grounding & Pertanahan Rp 8,000,000
29 Kepala Penangkal Petir Rp 19,000,000
30 Celling Speaker Toa 6 Watt Rp 150,000
31 Attenuation Rp 1,300,000
32 Amplifire 100V Rp 1,500,000
33 Sewa Scafolding / Perancah 1 set/ Hari Rp 15,000
34 Sewa Molen / Jam Berdasarkan efisien kerja 5 Rp 320,000
35 Air Rp 50
36 Pemasangan MCB Rp 4,000,000
37 Sewa Kompresor Rp 10,000
HUN 2015

Kabupaten Konawe

SATUAN

OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH

M3
M3
M3
M3
M3
M3
M3
M3
Buah

Kg
Kg
Kg

M3
M3
M3
M3
M3
M3
M3
M3
M3
Batang
M3
Lembar
Lembar
Lembar
Lembar
Lembar
Lembar
M2
Lembar

Lembar
Lembar
M1
Lembar
Ls

Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
M2

Lembar
M1
Lembar
Lembar
Lembar
M1
M1
Buah
Buah
Buah
Lembar
Lembar
Lembar
Buah
Ls
M1
M1
Kg

Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Buah
Buah
Buah
Dos
Kg
Kg
Kg
Buah
Buah
Kg
Buah
m1
m1

Buah
Buah
Buah
Unit
Buah
Buah
Unit
Unit
Unit
Unit
Unit

Kg
Kg
Ltr
Ltr
Buah
Buah
Kg
Liter
Lbr
Kg
Kg
Kg
Kg
Kg
Kg
Kaleng
Kaleng
Kaleng
Kaleng
Kaleng
Kaleng
Kaleng
Kaleng
Kaleng
Lembar
M2
Kg
M2
Kg

M2
M2
M2
M2
Tube

Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah

M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M2
M1
M1
M1
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Liter
Buah
Buah
m'
m'
m'
m'
Buah
Buah
Buah
m'
m'
m'
Ls
Unit
M1

Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Ls
Titik
Roll
Roll
Roll
Roll
Roll
Ls
Unit
Ls
Ls
Ls
Unit
Ls
Ls
Ls
Ls
Ls
Ls
Ls
HARGA SATUAN
SATUAN KERJA 0
PEKERJAAN : ANDI NUR ALAN
LOKASI : E3B1 13 042
TAHUN ANGGARAN : Perencanaan Kantor Badan Per

NO URAIAN PEKERJAAN

A -
-
-

B -
-
-
-
-
-
-
-

C -
-
-

D -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

E -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

F -
-
-
-
-
-
-

G -
-
-
-
-
-
-
-

H -
-
-
-
-
-

I -
-
-
-
-
-
-
-

J -
-
-
-
-
-
-

K -
-
-
-
-
-
-
-
-

L -
-
-
-
-
-
-
-

M -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

N -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

O -
-
PEKERJAAN 1 UNIT SEPTICTANK
PEKERJAAN 1 UNIT PENANGKAL PETIR
PEKERJAAN PANGGUNG MULTIPLEK 18MM FIN HPL DAN
PEKERJAAN PAPANAMA STENLIS STEEL DAN LAMPU
PINTU PLAT SHAAF ATAS DAN KAMAR MANDI
TUAN
0
: ANDI NUR ALAN
: E3B1 13 042
: Perencanaan Kantor Badan Per

HARGA SATUAN ( Rp )

Rp 9,133
Rp 5,184

Rp 5,063
Rp 3,094
Rp 3,664
Rp 1,813
Rp 8,025
Rp 3,625
Rp 24,025

Rp 70,179
Rp 40,988

Rp 98,509
Rp 87,940
Rp 492,345
Rp 527,905
Rp 517,922
Rp 593,091
Rp 711,891
Rp 710,566
Rp 608,313
Rp 633,261
Rp 813,426
Rp 611,521
Rp 609,984
Rp 666,421
Rp 674,725
Rp 687,473
Rp 697,693
Rp 346,995
Rp 451,159
Rp 492,668
Rp 16,144
Rp 71,953
Rp 547,924

Rp 2,765
Rp 2,420
Rp 16,017
Rp 18,042
Rp 8,642
Rp 13,829
Rp 46,012
Rp 209,077
Rp 14,433
Rp 22,040
Rp 19,790
Rp 1,683,950
Rp 281,014
Rp 524,232
Rp 179,058
Rp 845,324
Rp 1,316,340
Rp 1,153,030
Rp 457,854
Rp 392,550
Rp 262,046
Rp 766,820
Rp 1,308,496
Rp 484,937
Rp 103,072
Rp 50,937
Rp 73,119
Rp 169,591
Rp 9,617
Rp 58,903
Rp 72,642
Rp 9,929
Rp 9,373
Rp 4,982
Rp 4,680
Rp 6,261
Rp 2,774

Rp 34,653
Rp 25,856
Rp 19,553
Rp 18,993
Rp 20,784
Rp 20,293
Rp 26,720

Rp 8,710
Rp 10,799
Rp 4,032
Rp 9,932
Rp 1,338

Rp 17,560
Rp 7,360
Rp 3,840
Rp 14,569
Rp 9,272
Rp 7,900
Rp 4,681

Rp 670,000
Rp 50,925
Rp 37,630
Rp 660,413
Rp 4,395
Rp 5,068

Rp 6,154
Rp 3,719
Rp 2,463
Rp 5,753
Rp 18,053
Rp 2,383
Rp 46,012
Rp 14,433

Rp 2,580
Rp 3,714
Rp 2,578
Rp 3,918
Rp 3,618
Rp 22,040
Rp 4,681

Rp 284,600
Rp 40,733
Rp 189,886
Rp 219,861
Rp 11,932
Rp 70,658
Rp 7,453
Rp 55,194
Rp 37,338
Rp 13,072
Rp 4,480
Rp 8,485
Rp 4,690
Rp 4,960
Rp 11,485
Rp 6,325
Rp 7,315

Rp 1,230
Rp 6,500
Rp 3,420
Rp 2,030
Rp 4,150
Rp 15,288
Rp 12,660
Rp 50,000
Rp 8,000
Rp 7,550
Rp 6,470
Rp 4,300
Rp -
Rp 6,460
Rp 4,260
Rp 4,150
Rp 15,000
Rp 12,096
Rp 50,396
Rp 10,796
Rp 23,000

Rp 15,709
Rp 8,000,000
Rp 16,000,000
Rp 10,000,000
Rp 10,000,000
Rp 12,500