You are on page 1of 12

BAUER

Soil Improvement
BAUER Soil Improvement
a fast and economic solution

2 BAUER Soil Improvement


I
n the 1960s Bauer started per-
forming ground improvement.
The first vibrator for vibrocom-
paction was created in 1962
under the supervision of Dr.-Ing.
Karlheinz Bauer. In areas where
the subsoil has an insufficient
bearing capacity, vibrocompac-
tion or vibroreplacement can
be a faster and cost efficient
solution in comparison to deep
foundations. Soil improvement is
often used for land reclamation
projects as well as oil and gas or
infrastructure projects.

BAUER Soil Improvement 3


More than 45 years
experience
Some of our highlight projects:
1962 Development and construction of the first Bauer vibrator for
vibrocompaction, based on a hydraulic driven engine

1971 Collini-Center, Mannheim, Germany


Vibrocompaction up to a depth of 12 m

1975 Las Palmas, Grand Canary


Vibrocompaction of 250,000 m³ of the so called “Picon” material
(a volcanic slag)

1978 Thuwal, Kingdom of Saudi Arabia


Vibrocompaction with 160,000 lin.m for a new harbor construction
working from a ponton

1988 Cardiff, United Kingdom


Installation of 24,000 lin.m of stone columns with a length of 9 m to 10 m
for the ring road

1990 Singapore
Securing of dams against settlement and shear failure by installing
230,000 lin.m of stone columns

1995 Vancouver, Canada


Delta Port, vibrocompaction of 1.5 Mio. m³ of fill, working from a ponton to
a depth of approximately 31 m

1999 Schleuse Hohenwarte, Germany


28,000 lin.m of vibrocompaction up to a depth of 30 m

2004 Palm Jumeirah, Dubai, UAE


Soil improvement of the crown, 500,000 m² vibrocompaction

2005 Peribonka Dam, Canada


Vibrocompaction of 700,000 m³ of the fills and partially the river
deposits at the main dam base up to a depth of 35 m

2009 Cleveland Clinic, Al Sowah Island, Abu Dhabi, UAE


Vibrocompaction of 90,000 m² to a depth of approximately 10 m

2012 Davao City, Philippines


Vibrocompaction of 100,000 lin.m up to a depth of 18 m

Ocean Reef Island, Panama


Vibrocompaction of 100,000 m² up to a depth of 15 m
General
S
oil improvement is a special foun- planned construction. In addition, Bauer offers two different techniques:
dation technique to improve the a mitigation of earthquake induced
soil characteristics such as the liquefaction can be obtained. In com- • Vibrodisplacement to install stone
relative density or Young’s modulus parison to piles or barrettes (which de- columns and
of elasticity. The technique is required scribe columnar elements that transfer • Vibrocompaction also known as
in cases where the bearing capacity loads), the subsoil will be considered vibroflotation
of the subsoil is not adequate for the as an improved soil continuum.

Clay Silt Sand Gravel Stone


100%

90%
Values of P (%), by Weight

80%

70% Vibrodisplacement

60%

50%
Vibrocompaction

40%

30%

20%

10%

0%
0.001 0.01 0.1 1 10 100
Particle Size (mm)
The table shows which ground conditions suit vibrocompaction and which suit vibrodisplacement (stone columns)

Vibrocompaction
Applicable in non-cohesive soil with a During the movement of the vibrator with the result that the void ratio of the
maximum fine content of 10 % such the solid part of the matrix will be matrix decreases.
as sands or gravels. floated and afterwards compacted,

Vibro Compaction

Matrix Flotation Matrix


(loose material) (dense material)

Vibroreplacement
Applicable in mixed grained or cohe- strength values ranging from 20 to coarse grained backfill material (stone
sive soils, such as sandy silts to fine- 100 kN/m² by assembling compacted aggregates).
grained soils with undrained shear

BAUER Soil Improvement 5


Why Soil Improvement?
D
uring the planning stage of recommends possible types of foun- subsoil does not have sufficient bea-
a construction project, a soil dation. Normally, the subsoil provides ring capacity, various solutions are
investigation is usually carried adequate bearing capacity without available, such as soil improvement
out at the proposed site by a geo- special foundation measures being or deep foundations.
technical specialist who assesses the required. If the geotechnical specia-
bearing capacity of the subsoil and list comes to the conclusion that the

Advantages of Soil Improvement


• No excavation material, there- • In general, no groundwater low- By providing high level technical
fore no cost impact resulting ering required during installation supervision and workmanship
from transportation and no phase. Therefore no requirements throughout the project execution
dealing with contaminated soils. for permits and no risk to adjacent and understanding the interaction
buildings. between subsoil and structure, it is
• Simple foundation conditions, possible to fulfill the design require-
similar to natural subsoils with • Environmentally compatible by ments like increasing the bearing
an adequate bearing capacity. using only natural materials. capacity and mitigating liquefac-
The technique is highly adaptable. tion.

In many cases, soil improvement offers an economical and fast method for improving the engineering characteristics of
the prevailing subsoil.

Pile

Subsoil with Improved subsoil


an adequate (by vibrocompaction
bearing capacity or vibroreplacement)

Subsoil with an
adequate bearing
capacity

Different subsoil conditions and possible foundation solutions

6 BAUER Soil Improvement


Techniques
Vibrocompaction
Granular or weakly cohesive sedi- process, the soil is „floated“ by a wa- The upper meters of subsoil cannot
ments (fines less than a maximum of ter or air flush, the vibrator sinks and be compacted effectively by the vibro-
10 %) such as gravel or sand often a settlement depression is formed compaction technique only. These
have very uneven layer densities in at surface level. This is filled with areas must be compacted by surface
their natural state. With vibrocom- additional material. By extracting the compaction techniques like rollers or
paction the relative density can be vibrator in stages, a compacted zone similar.
increased up to around 80 %. In the 2-4 m diameter is created.

Vibroreplacement
Using vibroreplacement technique, the surrounding soil. This creates a the most suitable technique depends
the added material is transported crushed rock or gravel column which primarily on the ground conditions, the
directly to the vibrator tip (bottom improves the surrounding soil due to loads to be carried and the boundary
feed method), compacted by multiple the higher rigidity of the additional conditions.
displacement stages and pressed into installed material. The selection of

BAUER Soil Improvement 7


Design
R
egarding vibrocompaction we improved layers by using the theory called improvement factor by a given
investigate the “improved” soil of Priebe, which is common prac- friction angle of the stone column
by field tests such as CPTu or tice all over the world. The following (φs), the area ratio and an assumed
SPT. In case of vibroreplacement we diagram (Priebe, 1995) gives you an Poisson’s ratio of the soil (μB).
estimate the soil conditions of the impression of how to assess the so-

5
φs = 45,0°
Improvement Factor n

φs = 42,5° μB = 1/3
4
φs = 40,0°
φs = 37,5°
3
φs = 35,0°

1
1 2 3 4 5 6 7 8 9 10
Area Ratio A/Ac

As an alternative for the assessment


of the settlement it might be reason-
able to use FE-Applications. The
results can give you a better impres-
sion of the behaviour of the stone
column in different layers. Through
FE-Calculations you can also assess
the bulking effect in soft layers.

8 BAUER Soil Improvement


Testing
T
he execution of the so-called investigate the success of soil im- example the cone resistance against
Cone Penetration Tests (CPT) provement, especially for vibrocompac- depth and friction ratio.
is the most common practice to tion. The resulting graphs display for

Cone Resistance qc [MPa]


0 5 10 15 20 25 30 35 40 45 50
0

10
Depth [m]

15

20

25

The graphs of a CPT can be used to of a soil improvement by vibrore- load test) or as an alternative you can
evaluate for example the soil type placement, a zone load test can be use a kentledge test. The settlement
and the Young’s modulus. In addition, executed. In this case for example, a during the different load stages will
it is possible to assess the liquefac- concrete plate will be manufactured, be recorded, so you receive the load
tion mitigation due to soil improve- set in place to cover a number of stone settlement behaviour of the improved
ment works. To prove the success columns and loaded in stages (dead soil.

Concrete block (kentledge)

Beam

Load cell
Hydraulic jack Kentledge support
Load dispatcher (e.g. timber mat)

Reference beam
Dial gauge extensometers Reinforced concrete test base

BAUER Soil Improvement 9


Quality
B
ased on extensive experience production data for documentation
Bauer uses methods, equipment purposes is also carried out by the
and techniques which allow safe B-Tronic system.
execution of soil improvement pro- By deploying our professional employ-
jects. All process-specific production ees on all our projects, Bauer guaran-
data are monitored and displayed on tees the quality of the soil improvement
the B-Tronic monitor inside the ope- works. Documentation and quality
rator cabin for quality purposes. Elec- management happens in accordance
tronic data acquisition of all relevant to the rules of DIN EN ISO 9001.

Equipment
TR 75/TR 85
170

TR 17
700

Head piece
R9

with 2“ flushing
155
0

connection
696
7000

5850

Follower pipe
7000

5850

18850
29070

10000

Ø300
3000

Ø406
Joint
945

(Isolator)
1200

2232

Poker with wear


shield and flush
holes
3001

Ø320
[115]

580

900

The horizontal centrifugal forces of with customized Bauer base ma- the HD 460. Bauer uses two different
the deep vibrator are generated by chines, the required hydraulic power vibrator types, the TR 17 and the
a hydraulic motor and an oscillator can be provided by the base machine TR 75/TR 85. The TR 17 can reach a
inside the vibrator section. When de- itself (BG, BF or MC) or by a separate penetration depth of up to 25 m and
ploying deep vibrators in conjunction hydraulic power pack, for example the TR 75/TR 85 up to 45 m.

10 BAUER Soil Improvement


Projects Worldwide
Palm Jumeirah,
Dubai, UAE
For the „Palm“ the Emirate of Dubai builts a
7,000,000 m² artificial island off Jumeirah Beach
to house hotels and luxury villas. Most of the area
was compacted by 17 Bauer deep vibrators.

Port of Balboa, Panama


In the port of Balboa on the pacific coast of Pa-
nama, Bauer Fundaciones Panama compacted
some 15 hectare of newly reclaimed land down
to a depth of 22 m. The improved ground is being
utilized to extend the second largest container
terminal in Latin America and will in future be ca-
pable of withstanding all kinds of loads that such
use demands.

Cleveland Clinic,
Abu Dhabi, UAE
In Abu Dhabi, on Al Sowah Island, the 90,000 m²
Cleveland Clinic is under construction. Bauer
deployed as many as ten TR 85 deep vibrators
when carrying out vibroflotation densification to
provide ground improvement of the 10 m thick
alluvial sand layer.

Highend I to III,
Schindellegi, Switzerland
In Schindellegi, Highend I to III, a housing estate
at the hillside was constructed. For the necessary
ground improvement 12,800 lin.m vibroreplace-
ment (stone columns) were installed, comprising
of 1,117 columns with a length of up to 12 m.

BAUER Soil Improvement 11


BAUER Spezialtiefbau GmbH
BAUER - Strasse 1
86529 Schrobenhausen, Germany
Tel.: + 49 8252 97- 0
Fax: + 49 8252 97-1496
BST@bauer.de
www.bauer.de

http://www.bauer.de/en/bst/
5/2014
905.026.2

http://www.youtube.com/BAUERGruppe

You might also like