AMPLIACION Y REMODELACION DEL CENTRO COMERCIAL

EL QUINDE SHOPPING PLAZA


CAJAMARCA
Id Modo de Nombre de tarea Duración Comienzo Fin 26 jun '17 3 jul '17 10 jul '17 17 jul '17 24 jul '17 31 jul '17 7 ago '17 14 ago '17 21 ago '17 28 ago '17 4 sep '17 11 sep '17 18 sep '17 25 sep '17 2 oct '17 9 oct '17 16 oct '17 23 oct '17 30 oct '17 6 nov '17 13 nov '17 20 nov '17 27 nov '17 4 dic '17 11 dic '17 18 dic '17 25 dic '17 1 ene '18 8 ene '18 15 ene '18 22 ene '18
tarea MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D L
1 Cronograma Master - CC EL QUINDE 195 días jue 6/07/17 mar 16/01/18
2 Inicio de Obra 0 días jue 6/07/17 jue 6/07/17 Inicio de Obra 6/07

3 Obras Preliminares 11 días jue 6/07/17 dom 16/07/17


4 Fachada Hoyos Rubio 0 días dom 15/10/17 dom 15/10/17 Fachada Hoyos Rubio 15/10

5 Frente Hoyos Rubio 91 días lun 17/07/17 dom 15/10/17


6 Tramites Municipales 21 días lun 17/07/17 dom 6/08/17
7 Pistas, Veredas, Jardines, Peatonales 42 días lun 7/08/17 dom 17/09/17
8 Plataforma Metálica para Equipos 14 días lun 17/07/17 dom 30/07/17
9 Reubicacion de Equipos 7 días lun 31/07/17 dom 6/08/17
10 Demolición de Porticos 14 días lun 7/08/17 dom 20/08/17
11 Provisión y Habilitación de EEMM 28 días lun 17/07/17 dom 13/08/17
12 Muro Cortina Montaje EEMM 14 días lun 14/08/17 dom 27/08/17
13 Muro Cortina Instalación de Cristales 21 días lun 28/08/17 dom 17/09/17
14 Ingreso CC Montaje EEMM 14 días lun 21/08/17 dom 3/09/17
15 Ingreso CC Instalación de Cristales 21 días lun 4/09/17 dom 24/09/17
16 Totem Desmontaje de Letreros 7 días lun 7/08/17 lun 14/08/17
17 Totem Montaje EEMM 21 días lun 14/08/17 dom 3/09/17
18 Totem Instalación de Coberturas 21 días lun 4/09/17 dom 24/09/17
19 Alero Montaje EEMM 21 días lun 28/08/17 dom 17/09/17
20 Alero Instalación de Alucobond 21 días lun 18/09/17 dom 8/10/17
21 Trabajos en IIEE y Comunicaciones 42 días lun 21/08/17 dom 1/10/17
22 Trabajos en IISS y ACI 42 días lun 21/08/17 dom 1/10/17
23 Estacionamiento Motos y Bicicletas 21 días lun 21/08/17 dom 10/09/17
24 Reubicación de Tranquera Eléctrica 14 días lun 18/09/17 dom 1/10/17
25 Pintura en Fachada 42 días lun 4/09/17 dom 15/10/17
26 Frente Teresa Journet 91 días lun 17/07/17 dom 15/10/17
27 Tramites Municipales 21 días lun 17/07/17 dom 6/08/17
28 Pistas, Veredas, Jardines, Peatonales 28 días lun 7/08/17 dom 3/09/17
29 Totem Desmontaje de Letreros 7 días lun 7/08/17 lun 14/08/17
30 Totem Montaje EEMM 21 días lun 14/08/17 dom 3/09/17
31 Totem Instalación de Coberturas 21 días lun 4/09/17 dom 24/09/17
32 Alero Montaje EEMM 21 días lun 28/08/17 dom 17/09/17
33 Alero Instalación de Alucobond 21 días lun 18/09/17 dom 8/10/17
34 Rampa Demolisión 14 días lun 17/07/17 dom 30/07/17
35 Rampa Construcción 21 días lun 31/07/17 dom 20/08/17
36 Rampa Acabados 14 días lun 21/08/17 dom 3/09/17
37 Pintura en Fachada 42 días lun 4/09/17 dom 15/10/17
38 Trabajos en IIEE y Comunicaciones 42 días lun 21/08/17 dom 1/10/17
39 Trabajos en IISS y ACI 42 días lun 21/08/17 dom 1/10/17
40 Remodelacion Interior 0 días dom 15/10/17 dom 15/10/17 Remodelacion Interior 15/10

41 Pit de Escalera 0 días mar 1/08/17 mar 1/08/17 Pit de Escalera 1/08

42 Frente Interiores 98 días lun 10/07/17 dom 15/10/17


43 Primer Nivel Desmontaje de FCR 28 días lun 17/07/17 dom 13/08/17
44 Primer Nivel IIEE Comunicaciones 28 días lun 24/07/17 dom 20/08/17
45 Primer Nivel ACI Detección 28 días lun 31/07/17 dom 27/08/17
46 Primer Nivel Montaje de FCR 28 días lun 7/08/17 dom 3/09/17
47 Primer Nivel IISS 14 días lun 4/09/17 dom 17/09/17
48 Primer Nivel Acond de Locales 35 días lun 28/08/17 dom 1/10/17
49 Segundo Nivel Desmontaje de FCR 28 días lun 14/08/17 dom 10/09/17
50 Segundo Nivel IIEE Comunicaciones 28 días lun 21/08/17 dom 17/09/17
51 Segundo Nivel ACI Detección 28 días lun 28/08/17 dom 24/09/17
52 Segundo Nivel Montaje de FCR 28 días lun 4/09/17 dom 1/10/17
53 Segundo Nivel IISS 14 días lun 2/10/17 dom 15/10/17
54 Segundo Nivel Acond de Locales 21 días lun 25/09/17 dom 15/10/17
55 Pintura en Cielo Raso ambos Niveles 42 días lun 4/09/17 dom 15/10/17
56 Implementación de Señalética 14 días lun 2/10/17 dom 15/10/17
57 Reposición de Pisos 14 días lun 2/10/17 dom 15/10/17
58 Teatinas Instalación de EEMM 14 días lun 14/08/17 dom 27/08/17
59 Celosías Instalación 14 días lun 28/08/17 dom 10/09/17
60 Teatinas Instalación de Policarbonato 14 días lun 28/08/17 dom 10/09/17
61 Reforzamiento de EEMM 21 días lun 28/08/17 dom 17/09/17
62 Areas Comunes Cambio de Coberturas 28 días lun 4/09/17 dom 1/10/17
63 Areas Comunes Flashing y Canaletas 14 días lun 2/10/17 dom 15/10/17
64 Lucarnas Instalación de EEMM 21 días lun 28/08/17 dom 17/09/17
65 Lucarnas Instalación de Coberturas 14 días lun 11/09/17 dom 24/09/17
66 Construcción PIT Escalera 23 días lun 10/07/17 mar 1/08/17
67 Ampliación ABL 0 días dom 31/12/17 dom 31/12/17 Ampliación ABL 31/12

68 Frente Ampliacion 184 días lun 17/07/17 mar 16/01/18

Cronograma Master - Ampliación y Remodelación del CC El Quinde Cajamarca - rev00 by IFTZ Fecha de Elaboración: mar 20/06/17
AMPLIACION Y REMODELACION DEL CENTRO COMERCIAL
EL QUINDE SHOPPING PLAZA
CAJAMARCA
Id Modo de Nombre de tarea Duración Comienzo Fin 26 jun '17 3 jul '17 10 jul '17 17 jul '17 24 jul '17 31 jul '17 7 ago '17 14 ago '17 21 ago '17 28 ago '17 4 sep '17 11 sep '17 18 sep '17 25 sep '17 2 oct '17 9 oct '17 16 oct '17 23 oct '17 30 oct '17 6 nov '17 13 nov '17 20 nov '17 27 nov '17 4 dic '17 11 dic '17 18 dic '17 25 dic '17 1 ene '18 8 ene '18 15 ene '18 22 ene '18
tarea MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D LMX J V S D LMX J V S D LMX J V S D LMX J V S D L MX J V S D L
69 Desmontaje de Instalaciones Existentes 35 días lun 17/07/17 dom 20/08/17
70 Corredor Desmontaje de Marquesina 21 días lun 17/07/17 dom 6/08/17
71 Demolición de postes y muretes 14 días lun 24/07/17 dom 6/08/17
72 Abertura en placa 14 días lun 24/07/17 dom 6/08/17
73 Cimentación Corte y Excavacion 21 días lun 24/07/17 dom 13/08/17
74 Cimentación Anclaje de Acero 21 días lun 31/07/17 dom 20/08/17
75 Cimentación Hab. Y Col. de Acero 21 días lun 7/08/17 dom 27/08/17
76 Cimentacion Vaciado 21 días lun 14/08/17 dom 3/09/17
77 Columnas Acero y Encofrado 14 días lun 28/08/17 dom 10/09/17
78 Columnas Primer Nivel Vaciado 14 días lun 4/09/17 dom 17/09/17
79 Losa Primer Nivel Acero y Encofrado 21 días lun 11/09/17 dom 1/10/17
80 Losa Primer Nivel Vaciado 0 días dom 1/10/17 dom 1/10/17 Losa Primer Nivel Vaciado 1/10

81 Losa Desencofrado Primer Nivel 7 días lun 16/10/17 dom 22/10/17


82 Columnas Segundo Nivel Encofrado 14 días lun 2/10/17 dom 15/10/17
83 Columnas Segundo Nivel Vaciado 14 días lun 9/10/17 dom 22/10/17
84 Losa Segundo Nivel Acero y Encofrado 21 días lun 16/10/17 dom 5/11/17
85 Losa Segundo Nivel Vaciado 0 días dom 5/11/17 dom 5/11/17 Losa Segundo Nivel Vaciado 5/11

86 Losa Desencofrado Segundo Nivel 7 días lun 20/11/17 dom 26/11/17


87 Revestimientos y Enchapes 35 días lun 6/11/17 dom 10/12/17
88 Techo Exterior Montaje EEMM 42 días lun 16/10/17 dom 26/11/17
89 Techo Exterior Instalación de Coberturas 42 días lun 13/11/17 dom 24/12/17
90 Letreros Anclajes Montaje EEMM 14 días lun 27/11/17 dom 10/12/17
91 Letreros Reubicación 7 días lun 11/12/17 dom 17/12/17
92 Letreros IIEE 21 días lun 11/12/17 dom 31/12/17
93 Escaleras CA Demolición 7 días lun 17/07/17 dom 23/07/17
94 Escaleras CA Cimentacion 14 días lun 24/07/17 dom 6/08/17
95 Escalera CA Primer Nivel Acero y Encofrado 7 días lun 7/08/17 dom 13/08/17
96 Escalera CA Primer Nivel Vaciado 0 días dom 13/08/17 dom 13/08/17 Escalera CA Primer Nivel Vaciado 13/08

97 Escalera CA Segundo Nivel Acero y Encofrado 14 días lun 14/08/17 dom 27/08/17
98 Escalera CA Segundo Nivel Vaciado 0 días dom 27/08/17 dom 27/08/17 Escalera CA Segundo Nivel Vaciado 27/08

99 Escalera CA Tercer Nivel Acero y Encofrado 7 días lun 28/08/17 dom 3/09/17
100 Escalera CA Tercer Nivel Vaciado 0 días dom 3/09/17 dom 3/09/17 Escalera CA Tercer Nivel Vaciado 3/09

101 Escalera CA Revestimientos 21 días lun 4/09/17 dom 24/09/17


102 Escalera MM Montaje EEMM 14 días lun 27/11/17 dom 10/12/17
103 Escalera MM Revestimientos 14 días lun 11/12/17 dom 24/12/17
104 Pintura en Fachadas 37 días lun 11/12/17 mar 16/01/18
105 Colaborante METRO Montaje EEMM 14 días lun 14/08/17 dom 27/08/17
106 Colaborante METRO Vaciado 0 días dom 27/08/17 dom 27/08/17 Colaborante METRO Vaciado 27/08

107 Colaborante SAGA Montaje EEMM 10.5 días lun 28/08/17 jue 7/09/17
108 Colaborante SAGA Vaciado 0 días jue 7/09/17 jue 7/09/17 Colaborante SAGA Vaciado 7/09

109 Colaborante FITNES Montaje EEMM 10.5 días jue 7/09/17 dom 17/09/17
110 Colaborante FITNES Vaciado 0 días dom 17/09/17 dom 17/09/17 Colaborante FITNES Vaciado 17/09

111 Colaborante SEDACAJ Montaje EEMM 14 días lun 18/09/17 dom 1/10/17
112 Colaborante SEDACAJ Vaciado 0 días dom 1/10/17 dom 1/10/17 Colaborante SEDACAJ Vaciado 1/10

113 Colaborante ASCENSOR Montaje EEMM 7 días lun 2/10/17 dom 8/10/17
114 Colaborante ASCENSOR Vaciado 0 días dom 8/10/17 dom 8/10/17 Colaborante ASCENSOR Vaciado 8/10

115 Colaborante Pisos Contrapisos Enchapes 42 días lun 4/09/17 dom 15/10/17
116 Demolición Desmontaje de Lucarnas 14 días lun 18/09/17 dom 1/10/17
117 Puente Montaje EEMM 21 días lun 2/10/17 dom 22/10/17
118 Reubicación de Extractores Eólicos 14 días lun 23/10/17 dom 5/11/17
119 Escalera Sótano Demoliciones 14 días lun 17/07/17 dom 30/07/17
120 Escalera Sótano Cimentacion 7 días lun 31/07/17 dom 6/08/17
121 Escalera Sótano Acero y Encofrado 7 días lun 7/08/17 dom 13/08/17
122 Escalera Sótanos Vaciado 0 días dom 13/08/17 dom 13/08/17 Escalera Sótanos Vaciado 13/08

123 Escalera Sótanos Revestimientos 14 días lun 14/08/17 dom 27/08/17


124 Sótanos IIEE y Comunicaciones 35 días lun 7/08/17 dom 10/09/17
125 Sótanos IISS y ACI 35 días lun 14/08/17 dom 17/09/17
126 Señalización Horizontal 37 días lun 11/12/17 mar 16/01/18
127 Fin de Obra 0 días mar 16/01/18 mar 16/01/18 Fin de Obra 16/01