You are on page 1of 11

TIME-SCALED

NETWORK

A Guide to the Project


PMBOK Management Body of
Knowledge
PMBOK PMBOK

a set of standard terminology


and guidelines for project used as a framework for new
management, developed and product development for
marketed by Project products with defined scope
Management Institute (PMI)
A Guide to the Project Management Body of Knowledge A Guide to the Project Management Body of Knowledge

PMBOK PMBOK

is the primary knowledge base It has been recognized by the


for the Project Management American National Standards
Professional (PMP) credential Institute (ANSI)

A Guide to the Project Management Body of Knowledge A Guide to the Project Management Body of Knowledge
TIME-SCALED
PMBOK NETWORK

Time-Scaled Network Time-Scaled Network

any project schedule network


diagram drawn in such a way
that the positioning and length it is a bar chart that includes
of the schedule activity schedule network logic
represents its duration
A Guide to the Project Management Body of Knowledge A Guide to the Project Management Body of Knowledge
Previous Example #1

Activity Est’d ES EF LS LF Total Free Critical


Time Float Float Activity
1–2 10 0 10 0 10 0 0 
1–3 6 0 6 5 11 5 0
2–4 8 10 18 11 19 1 0
2–5 13 10 23 10 23 0 0 
3–5 12 6 18 11 23 5 5
4–5 4 18 22 19 23 1 1
5–6 2 23 25 23 25 0 0 

Determine the ES, EF, LS, LF, the Total Float, and the Free Float
Activity Est’d ES EF LS LF Total Free Critical
Time Float Float Activity
1–2 10 0 10 0 10 0 0 
1–3 6 0 6 5 11 5 0
2–4 8 10 18 11 19 1 0
2–5 13 10 23 10 23 0 0  0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
3–5 12 6 18 11 23 5 5 2 4
4–5 4 18 22 19 23 1 1
2 5
5–6 2 23 25 23 25 0 0 
1
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 2 4
2 4 5 6

3 4 5

1 3

3 4

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
2 4

1 C – 13

4
A – 10

3 D–8 H–2
F–4
B–6
E – 12 K–0
MANPOWER the consequence of
employment fluctuation and
LEVELING equipment utilization adds to
the cost of the project

the only solution to this


problem is to keep the
employment at an
acceptable level
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

K – 10 men (6)

I – 15 men (14)

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
C – 5 men (7) G – 10 men (6)
F – 5 men (5)
K – 10 men (6)
H – 5 men (5)
E – 15 men (5) J – 5 men (6)
I – 15 men (14)
L – 5 men (4)
B – 10 men (4)
C – 5 men (7) G – 10 men (6)
D – 15 men (8)
F – 5 men (5)
H – 5 men (5)
A – 10 men (11)
E – 15 men (5) J – 5 men (6)
L – 5 men (4) 50
B – 10 men (4) 45
D – 15 men (8) 40
35
A – 10 men (11) 30
25
20
15
10
5
0

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

K – 10 men (6)

I – 15 men (14)

C – 5 men (7) G – 10 men (6)


F – 5 men (5)
H – 5 men (5)
E – 15 men (5) J – 5 men (6)
L – 5 men (4)
B – 10 men (4)
D – 15 men (8)

A – 10 men (11)

50
45
40
35
30
25
20
15
10
5
0
a curve of cumulative project
S – CURVE cost plotted against time

typically follows the shape of it allows the progress of a


the letter "S" project to be tracked visually
over time
Analyses of S-curves allow project
managers to quickly identify project
it also forms a record of what growth, slippage, and potential
has happened to date problems that could adversely
impact the project if no remedial
action is taken

Descrip Qty Unit Unit Cost Amount Equivalent Parameter Total Duration Crew 1 2 3 4 5 6 7 8 9 10
tion % Weight Man- Size
hours

100
A–B 1 lot 1000 1 2
90
B–C 1 lot 3500 1 2
80
C–D 25 sq.m. 450 6.00 3
D– 70
E/F/G/H 1 lot 675 1 1
60
E–I 4.75 cu.m. 550 12 2
50
F–J 1.5 cu.m. 330 1.48 1
40
G–J 32 sq.m. 1250 2.22 3
30
H-end 1 lot 850 1 1
20
I-end 1 kg 700 4.20 1
10
J-end 1 lot 5500 2 4
0
Total
Daily

Progress
Planned
Cumulative
Des Qty Unit Unit Amount Equivalent % Parameter Total Duration Crew 1 2 3 4 5 6 7 8 9 10
crip Cost Weight Man- Size
tion hours

100
A 1 lot 1000 1000 0.0150 1 2 0.0150

90
B 1 lot 3500 3500 0.0526 1 2 0.0526

80
C 25 sq.m. 450 11250 0.1690 6.00 150 3 5 0.0563 0.0563 0.0564

70
D 1 lot 675 675 0.0101 1 1 0.0101

60
E 4.75 cu.m. 550 2612.50 0.0392 12 57 2 3

SEATWORK
0.0196 0.0196

50
F 1.5 cu.m. 330 495 0.0074 1.48 2.22 1 1 0.0074

40
G 32 sq.m. 1250 40000 0.6008 2.22 71.04 3 3 0.2003 0.2003 0.2002

30
H 1 lot 850 850 0.0128 1 1 0.0128

20
I 1 kg 700 700 0.0105 4.20 4.20 1 1 0.0105

10
J 1 lot 5500 5500 0.0826 2 4 0.0413 0.0413

0
Total 66582.5 1
Daily

0.0150

0.0526

0.0563

0.0563

0.0564

0.2374

0.2199

0.2002

0.0646

0.0413
Progress
Planned

Cumulative

0.0150

0.0676

0.1239

0.1802

0.2366

0.6939

0.8941

0.9587
0.474

1.00
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

K – 10 men (6)

I – 15 men (14)

C – 5 men (7) G – 10 men (6)


F – 5 men (5)
H – 5 men (5)
E – 15 men (5) J – 5 men (6)
L – 5 men (4)
B – 10 men (4)
D – 15 men (8)

A – 10 men (11)

50
45
40
35
30
25
20
15
10
5
0
Seatwork #2 Activites Time Duration in Weeks
Seatwork #2
From the following data, create the following: 1–2 Demolition and Clearing 8
2–3 Excavation 14
2–5 Underground Installation 6
a. Network Diagram 3–4 Foundation and Columns 5
b. the Early Start (ES) 4–5 Dummy 0

c. the Early Finish (EF) 4–6 Construction of 2nd Floor 6


4–7 Roof framing and flooring 6
d. the Last Start (LS) 5–7 Ground floor slab 4
e. the Last Finish (LF) 5–8 Mechanical and Electrical Services 12

f. the Total Float 6–7 Construction of Exterior Walls 12

g. the Free Float 7–8


7–9
Dummy
Construction of Interior Partitions
0
10
h. the Critical Activities/Path 8–9 Mechanical and Electrical Equipment and Fixtures 12
i. the Expected Completion Time 9 – 10 Painting and Finishing Works 8

You might also like