PRODUCTIVITY OUTPUT V. TILEWORKS 1-Mason 20 sq.m.

/day All Surface levellled


2-Helper with tapping
ACTIVITY INPUT/ PRODUCTIVITY REMARKS
METHOD HRS./DAY VI. REINFORCING STEEL BARS
Cutting,Bending and Ticing 1-Steelman 150 kgs./day Sizes from 10mm dia.
I. EARTHWORK 2-helpers to 16mm dia.

a) Excavating loam or Sand 1-man 1.5 cu.m./day VII.CARPENTRY WORKS


b) Excavating clay or heavy 1-man 1.5 cu.m./day
soil a) Roof Framing 2-Carpenters 10 sq.m./day For 1 storey building
c) Excavating Rocks 1-man Depending on Hardness w/ 1-Helper
Spreading Tamping 0.15cm
thk of lift b) Ceiling 2-Carpenters 15 sq.m./day Plywood with studs
d) Backfilling 1-man 2.0 cu.m./day at 0.60 m.o.c.
e) Spreading, tamping and c) Exterior walls(S-cut sidings) 2-Carpenters 17 sq.m./day Studding at 0.60m.o.c.
grading 1-man 2.5 cu.m./day 1-Helper
f) Clearing undergrowth and d) Partition(single wall) 2-carpenters 6 sq.m./day Single wall w/ joist and
Trees 12" 1-man 20 sq.m./day 1-Helper nailers at 0.60m.o.c.
g) Clearing undergrowth and e) Door and window frames 1-Helper 15 lin.m./day Planed
small brush 1-man 100 sq.m.
VIII. TINNERY
II. LAYING OF CHB OR ADOBE 1-mason 150 pcs/day For 3m max. ht. Of wall a) Corr. GI Sheet
2-helper nails 1-tinsmith 25 sq.m./day To include ridge roll,
III. PLASTERING rivets 2-Helpers Flashing gutter & Downspout
a) Plain Plastering 1-mason 20 sq.m./day For 3m max. ht. Of wall b) Flashing Soldered
2-helper c) Inst. Of GI Gutter Soldered & Riveted
b) Edge Plastering 1-mason d) Inst. Of GI Downspout Soldered & Riveted

IV. CONCRETE WORKS XI. INSTALLATION OF PVC 1-Master Plumber 150 lin.m./day 13mm dia.-50mm dia.
6-Laborers
a) Erecting Forms 1-Carpenter 14 sq.m./day
1-Helper 1-Asst. Plumber 100 lin.m./day 63mm dia.-100mm dia.
b) Removing of Forms 1-Carpenter 14 sq.m./day 6-Laborers

c) Pouring Concrete on slabs 1-mason 4 cu.m./day Handmixing XII. PAINTING 1-Painter 5 sq.m./day 3 Coatings to include Sanding
VARNISHING 1-Painter 4 sq.m./day 3 Coatings to include Sanding
d) Pouring Concrete on walls, 1-mason 3 cu.m./day Handmixing
columns and slabs 6-laborers