IV. CONCRETE WORKS XI. INSTALLATION OF PVC 1-Master Plumber 150 lin.m./day 13mm dia.-50mm dia.
6-Laborers
a) Erecting Forms 1-Carpenter 14 sq.m./day
1-Helper 1-Asst. Plumber 100 lin.m./day 63mm dia.-100mm dia.
b) Removing of Forms 1-Carpenter 14 sq.m./day 6-Laborers
c) Pouring Concrete on slabs 1-mason 4 cu.m./day Handmixing XII. PAINTING 1-Painter 5 sq.m./day 3 Coatings to include Sanding
VARNISHING 1-Painter 4 sq.m./day 3 Coatings to include Sanding
d) Pouring Concrete on walls, 1-mason 3 cu.m./day Handmixing
columns and slabs 6-laborers