Task Name: Indoor Plaster

Total Work Completion Work Work No of


Qty. Day Qty/day Qty/Person Person
1200 sq.ft 2 (02/02/2017) 600 sq.ft 100 sq.ft 6

Day - 01(31/01/17) Day - 02(01/02/17)


No
Work completed Verified by Work completed Verified by

Labor - 01

Labor - 02

Labor - 03

Labor - 04

Labor - 05

Labor - 06
Task Name: Outdoor Plaster

Total Work Completion Work Work No of


Qty. Day Qty/day Qty/Person Person/day

3100 6(06.02.17) 517 50 sq.ft 11

Day - 01(31.01.17) Day - 02(01.02.17) Day - 03(02.02.17) Day - 04(03.02.17) Day - 05(04.02.17) Day - 06(05.02.17)
No Work Work Work Work Work Work
Verified by Verified by Verified by Verified by Verified by Verified by
completed completed completed completed completed completed

Labor - 01 59

Labor - 02 59

Labor - 03 59

Labor - 04 59

Labor - 05

Labor - 06

Labor - 07

Labor - 08

Labor - 09

Labor - 10

Labor - 11

TOTAL
236
WORK
Remaining 2864

Task Name: Inside Plaster

Total Work Completion Work Work No of


Qty. Day Qty/day Qty/Person Person/day

4400 6(06.02.17) 733 200 sq.ft 4

Day - 01(31.01.17) Day - 02(01.02.17) Day - 03(02.02.17) Day - 04(03.02.17) Day - 05(04.02.17) Day - 06(05.02.17)
No Work Work Work Work Work Work
Verified by Verified by Verified by Verified by Verified by Verified by
completed completed completed completed completed completed
Labor - 01 226
Labor - 02 226
Labor - 03 245
Labor - 04 245
Labor - 05 260
Labor - 06 260
Labor - 07
Labor - 08
Labor - 09
Labor - 10
Labor - 11
TOTAL
1462
WORK
Remaining 2938