TR 616,134 334,455 84% Took an oportunity for 15m meter blast in KCD to generate more blasted material FR 493,056 630,761 -22% Some Blocks in KOM could not be drilled due to the delay in mining the area as a re 1,109,190 965,216 15% enerate more blasted material (Tansitional material) delay in mining the area as a result of the breakdown of one of 9350 excavators.Drilling capacities were there moved to PKK and KCD ere moved to PKK and KCD