PROJECT:MARCO POLO CEBU RESIDENCES - TOWER 3

OWNER : FEDERAL LAND INC.


LOCATION: Cebu Veterans Drive, Nivel Hills, Cebu City

SCHEDULE OF DELIVERY & SITE INSTALLATION


FLOOR JANUARY 2018 FEBUARY 2018 MARCH 2018 APRIL 2018
1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH
Delivery
KITCHEN
Site installation
17th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
18th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
19th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
20th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
21st
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
22nd
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
23rd
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
25th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
26th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
27th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
28th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
29th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
30th
Delivery
CLOSET
Site installation

Note: -all materials, melamine boards & accessories were all prepared.
-production status: Work in process
-all 17th floor kitchen cabinets were delivered to site

Prepared by: Noted by: Approved by:

Girlie N. Tesio Dante Agustin Andrei S.Chang


Cost Engineer Operations Manager General Manager
PROJECT:MARCO POLO CEBU RESIDENCES - TOWER 3
OWNER : FEDERAL LAND INC.
LOCATION: Cebu Veterans Drive, Nivel Hills, Cebu City

SCHEDULE OF DELIVERY & SITE INSTALLATION


FLOOR JANUARY 2018 FEBUARY 2018
1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH
Delivery
KITCHEN
Site installation
17th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
18th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
19th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
20th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
21st
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
22nd
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
23rd
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
25th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
26th
Delivery
CLOSET
26th
CLOSET
Site installation
Delivery
KITCHEN
Site installation
27th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
28th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
29th
Delivery
CLOSET
Site installation
Delivery
KITCHEN
Site installation
30th
Delivery
CLOSET
Site installation

Note: -all materials, melamine boards & accessories were all prepared.
-production status: Work in process
-all 17th floor kitchen cabinets were delivered to site

Prepared by: Noted by:

Girlie N. Tesio Dante Agustin


Cost Engineer Operations Manager
TION
MARCH 2018 APRIL 2018 REMARKS
1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH

1/16-85%cut
were all prepared.

Approved by:

Andrei S.Chang
General Manager