You are on page 1of 8

European Drilling

Case study: HPHT infill well drilled successfully


in highly depleted reservoir on UKCS field
By L. Fambon, G. Joffroy, TOTAL E&P UK ly be fully sheared off. Both threats have
been experienced on UKCS HPHT fields
Drilling infill wells on by different operators.
HPHT fields after a significant depletion
has occurred represents a difficult chal- The identification of these threats
lenge. It requires drilling from a cap rock pushed the operator to design a well
remaining at or close to virgin pressure architecture to overcome the 100-bar
into a reservoir in which pore and frac- depletion limit and to drill into a signifi-
ture pressures have largely decreased cantly depleted reservoir, in order to be
due to production. No mud-weight win- able to replace a well if and when it has
dow exists anymore at the transition failed. A feasibility study was launched
between cap rock and reservoir. in 2004, which concluded that drilling
such a well was feasible and identified
The difficulty is further increased by two possible architectures. Based on
uncertainties in the pressure profile these results, the development phase
along the well path, the rock mechanics was launched.
and their change generated by the high
and rapid depletion, and also by depth The Geoscience Department subsequent-
uncertainty on the top reservoir. ly identified a candidate for such an infill
Figure 1: On HPHT fields, wells are well, which would increase the reserves
For this reason, most HPHT fields are of the field. This provided an opportunity
exposed to multiple threats due to the
developed by drilling all wells before to try the proposed solutions and vali-
a pre-defined limit of depletion level is
large amount of depletion, such as liner
date the feasibility study conclusions.
reached where the mud-weight window deformation.
closes. This limit is usually low.
reaches 200°C. The fluid produced is gas The Challenge
However, HPHT producer wells face condensate, with 3-4% CO2 and 30-40 For wells drilled before depletion occurs,
depletion-related threats to their integ- ppm H2S. Depletion on this field is ini- a mud-weight window exists between
rity: sand production and/or deforma- tially very quick. The order of magnitude the pore pressure and the fracturation
tion of the production liner under rock is a decrease of 100 bar per six months. pressure. When depletion occurs, the
movement. When these threats become fracturation pressure in the reservoir
effective, the well and its associated pro- Initial studies had concluded that infill decreases along with the pore pressure.
duction will be lost. Replacement wells drilling was not possible after depletion At the interface between the cap rock,
will need to be drilled. Additional wells had reached 100 bar. Based on these which stayed at virgin pressure, and the
are also needed to increase reserves by studies, the field development plan stipu- depleted reservoir, no mud-weight win-
creating new off-take points. lated that all planned development wells dow exists anymore (Figure 2).
(F1 to F6) be drilled prior to the start of
This article describes the preparation production. This was performed in the a) Defining the pore pressure profile
work performed before drilling an HPHT late 1990s, and production started in As can be seen in Figure 3, FIA was
infill well (Franklin Infill A - FIA) in the 2001. Subsequently, one well (G9) was located in a graben separated from the
highly depleted Franklin reservoir in the drilled on the nearby Elgin field just at existing crestal wells by a fault, and
UKCS, the management of uncertainties the 100-bar depletion limit and did not from the F5 down dip well by another
during the drilling and some of the les- encounter noticeable difficulty. fault.
sons learned from this first experience.
Among them is the important influence On HPHT fields such as Elgin/Franklin, The Fulmar reservoir consists of three
of the reservoir depletion on the mechan- wells are exposed to multiple threats due main units:
ics of the formations above reservoir. to the large amount of depletion. One
such threat is sand production, which • The C sands at the top have relatively
The success of this first HPHT infill well can lead to erosion of materials such as poor characteristics: degraded perme-
after significant depletion proves the the downhole safety valve, Christmas ability and presence of vertical baffles.
feasibility of drilling such wells. It opens tree and surface piping. At the moment, • The B sands in the middle have the
the door to new opportunities in HPHT no reliable downhole sand control best properties and are the main con-
developments. method can be run in HPHT wells. The tributors to production.
wells have to be choked down and can
Background ultimately be lost, which leads to a sig- • The A sands at the bottom are tighter
nificant loss of production. but can include good layers at the top
Franklin, located in the Central North
Sea, is one of the highest profile HPHT The other threat is liner deformation Under the main Fulmar reservoir are
fields in the world. The reservoir lies at due either to subsidence, which leads the Pentland sands with poor charac-
5,300 m below sea level in 92 m water to buckling of the liner, or to tectonic teristics. They are barely depleted and
depth. Its original pressure was 1,100 movements along faults or other bedding remain close to virgin pressure.
bar, and the downhole temperature plane (Figure 1). The liner can ultimate-

40 July/August 2008 D r i l l i n g contractor


European Drilling

The only other information available


was obtained from production logging
runs performed on crestal producers.
Their analysis showed that C sands were
produced on these wells. The degree
of dynamic communication through
the fault between crestal wells and
FIA panel at the level of the C sands
was nevertheless difficult to ascertain.
Material balance could not help there as
the contribution of the C sands was mini-
mal compared to the B sands.
The production logging runs indicated
also a differential depletion between B
and C sands, but its amount could not be
reliably estimated.
The highest uncertainty lies in the pres-
sure transition profile between the cap
rock, believed to have remained at virgin
pressure, and the reservoir section. Is it
at the very top of the reservoir, or is the
bottom of the cap rock affected by deple-
Figure 2: The mud-weight window disappears along with depletion. tion through microfractures? How thick
All field data were reviewed to define the date. It was regularly revisited to take is the reverse pressure transition zone
pore pressure profile along the well path into account continuous production (RPTZ), and how steep is the pressure
as it was crossing the different units. and drilling planning. An uncertainty gradient in this zone? Rock mechanics
range of +/- 30 bar was attached to this study suggested that it could be less
The monitoring of the average pres- value, based on uncertainties on field than one meter thick.
sure of existing Franklin producers had internal fault continuity an transmis- Considering all uncertainties, different
shown a depletion of more than 600 bar sivity. scenarios were envisaged, and a pres-
of the main reservoir. Material balance
sure profile along the well path was
analysis, interpretation of faults pat- The pressure of the tighter C sands
drawn for each of them. A probability of
tern and review of 4D seismic data pro- was more difficult to predict. Open hole
encountering higher pressure at top res-
vided a relatively good understanding pressure measurements taken on the
ervoir was evaluated for each scenario.
of the reservoir behavior. The pressure Elgin G9 well drilled seven months after
The result is shown in Figure 4.
of the Fulmar B sands was confidently production start-up had shown a 60-bar
estimated at 500 bar at FIA location difference with the B sands. b) Rock mechanic properties
at the planned reservoir penetration Rock mechanic experts were brought in
to estimate the two main rock properties
necessary to design the well: fracture
gradient of the reservoirs and borehole
stability of the cap rock. One has to dif-
ferentiate between the fracture initiation
gradient (FIG) and the fracture propaga-
tion gradient (FPG). The fracture propa-
gation gradient is close to the minimum
horizontal stress and can be modeled.
In the case of Elgin/Franklin, a full-scale
rock mechanic model, coupled with the
geological and dynamic reservoir model,
had already been built and was used for
this purpose. It estimated the FPG at
1.65 sg equivalent mud weight (EMW).
The FIG is much more difficult than the
FPG to predict; therefore, it was used
only as an indication and considered as
an unreliable, but existing, margin. On
this well, it was predicted to be around
1.87 sg EMW.
Both gradients are a function of forma-
tion pressure. As such, their profile in
the RPTZ suffers from the same uncer-
Figure 3: The FIA well was located in a graben. tainty as the reservoir pressure profiles.

42 July/August 2008 D r i l l i n g contractor


European Drilling

FIA Predicted Pressure (bar)


d) High-pressure layers in cap rock

On Elgin/Franklin, thin limestone lay-


350
360
370
380
390
400
410
420
430
440
450
460
470
480
490
500
510
520
530
540
550
560
570
580
590
600
610
620
630
640
650
660
670
680
690
700
-50 ers (centimetric to decimetric) are often
-25 95 % 85 % 75 % 50 % 25 % 10 % found in the cap rock. They are gas-bear-
0
ing, although they don’t constitute res-
Top Fulm ar C
ervoirs, being too small and of very poor
25
properties. Their pore pressure should
50 not be affected by the reservoir depletion.
Depth below top fulmar TVDss

75 When they are submitted to a fluid col-


Top Upper B
100 umn pressure lower than their pore pres-
sure, they slowly but continuously bleed
125
Case uniform F3 small amounts of high-pressure gas into
150
Top Lo wer B Case uniform F6 the wellbore. They can be drilled under-
175 FIA Case uniform (average B) balanced but sometimes require high
200 FIA Kv/Kh dow ngraded in C sand mud weight to enable trips. They are
225
FIA B/C Multi-layer behaviour encountered more often on Elgin than on
FIA Tigth top C Franklin. A geology study concluded that
250 Initial the probability was low to find any in the
275 FIA Base case bottom section of the cap rock.
300
e) High-pressure layers within reservoir
325
The likelihood of high-pressure layers in
Figure 4 (above): A pre-drilling prediction was made for the penetration into the reser- the reservoir was considered low. If any,
voir, with different scenarios being considered due to pressure prediction uncertainties. they would have been very tight layers.

Figure 5 (below): The two architectures defined at the feasibility study. On the left is
The two architectures
architecture 1 retained as primary. On the right is architecture 2 retained as contingent.
In order to tackle this drilling challenge,
Contingency the 2004 feasibility study identified two
First option
Borehole Strengthening
Run expandable -
Penetrate reservoir different architectures. They are shown
then reservoir at low
MW.
below frac P - Drilling
liner - reservoir at low in Figure 5.
MW

7" TOL @ 4 1/2" TOL The first one involves the use of a spe-
5040m @ 5015m
cially designed mud loaded preventively
6-5/8" TOL
@ 5065m with specific loss circulation materials
9 7/8" @ Exp TOL @
5115 m
(LCM). The technique is known as “bore-
5141m 9 7/8" @
5141m Mw = 2.00 to hole strengthening.” Once reservoir has
2.15 sg
Mw = 1.86 sg 8-½" Drilling
been penetrated, the RPTZ is cased off
Cap Rock

8-½" Drilling 7" liner


solid
expandable
by a 7-in. liner. The liner is a standard
just above
reservoir E/F production liner 42.7 ppf, 25% Cr
Designer fluid 6 5/8"
with premium connections.
@ 5400 m Drill type
hanger &shoe

4-1/2" TOL
The second one involves the use of an
@ 5400 m Top reservoir
@ 5433 m
Mw = 1.86 sg Liner drilling
7.375" drill shoe
expandable liner to cover most of the
7" @ 5453m +30 / -45 m 6-5/8" @
5453m cap rock. The RTPZ is then drilled with
a lower mud weight below the FPG. The
Reservoir

5-5/8" Drilling
5-5/8" Drilling
4 1/2" liner
4 1/2" liner
remaining opened cap rock would be
Mw = 1.15 to
1.35 sg short enough so that borehole instabili-
4 1/2" @
5675m
4 1/2" @
5675m ties can be managed. The RPTZ is then
4 1/2" liner 18.9 ppf 4 1/2" liner covered with a cemented 6 5/8-in. flush
25%Cr set in 7"
production liner
25%Cr to cover 6-5/8"
intermediate liner and connection drilling liner. Once the reser-
expandable
voir has been drilled, the 6 5/8-in. liner is
covered by a 4 ½-in. production liner 18.9
The other information requested from c) Top reservoir depth uncertainty ppf, 25% Cr with premium connections.
rock mechanics was the borehole stabil-
Depending on the architecture selected, Once RPTZ is covered, the mud weight
ity of the cap rock. This allows definition
the top reservoir depth prediction was can be decreased to a value just enough
of the minimum mud weight one can
critical to maximize the success of the to safely drill the reservoir.
use to cross the RPTZ without suffering
RPTZ drilling. Extensive geophysical
unmanageable borehole instability of the As the main difficulty was lying across
techniques were used to minimize the
open hole above. The amount of informa- the RPTZ crossing, the top architecture
uncertainty attached to this test predic-
tion on the cap rock is even more limited of the well was taken as a standard
tion. These included, among others,
than on the reservoir. The uncertainty Elgin/Franklin architecture as designed
thorough examination of the seismic
on the defined value is consequently for virgin pressure. Production casing
data and uncertainty studies on depth
higher. set at the top of the cap rock (above
conversion. The prediction was given to
PTZ) is 10 ¾-in. and 9 7/8-in. casing. This
+30m / -45 m.

44 July/August 2008 D r i l l i n g contractor


European Drilling

allowed focus on the RPTZ crossing and Figure 6 shows efficiency of plugging at one was planned to be installed in front
gave a comfort factor, because this top various concentrations. of the previous casing to act as a top
architecture is designed to hold well seal and hanger mean.
full of gas at virgin reservoir pressure, Expandable liner
regardless of circumstances. Expandable liners are becoming more Implementation Strategy
Before being implemented, both architec- widely used in the industry. They are Primary and back-up architecture
tures needed further development work, usually used to seal off weak zones to
thorough testing, qualification and engi- allow for increasing the mud weight to Out of the two architectures, it was
neering calculations. The main ones are penetrate deeper zones at higher pres- decided to implement architecture 1 as
detailed in the next section. sure. This makes them work under a the primary. The main reasons were:
burst mode. In our case, the expandable
liner had to work in a collapse mode. • In case of failure of the borehole-
Special Developments Expanded pipe has low collapse capac- strengthening method, it allowed plug-
Specially designed mud ity, and this is one of the limitations of ging of the hole with a cement plug
the technique. The standard off-the-shelf and side track from the 9 7/8-in. shoe,
The borehole-strengthening technique expandable for this application was starting with a fresh hole to implement
was already used in the industry. The 75/8-in. x 9 5/8-in.- 29.7 ppf, with a claimed the contingent architecture.
principle is to create a fracture by using collapse capacity of 218 bar. To increase
a mud weight higher than the FIP and • Also, in case of failure of the borehole-
the collapse capacity to the required strengthening method when reaching
plug it on creation, to prevent its further value, a development programme was
development. The plug is formed by the reservoir, the depth of the top
undertaken with the selected provider. reservoir would then be accurately
LCM continuously present in the mud.
The created fracture increases the rock A heavier expandable pipe of 38 ppf known, and the placement of the
stress locally, enhancing the hole’s ability (0.5-in. wall thickness) was selected, and expandable liner would be optimized.
to support high mud weight. The process the associated connection was designed. • It was quicker.
is easier when filtration exists behind An expansion test of the system was car-
the plug in the fracture, because the ried out in the provider facility during Architecture 2 was kept as contingent
pressure inside the fracture decreases summer 2005, including expansion of an and preparatory work was done to make
and allows it to close back on the plug. elastomer-bonded section inside a joint it ready for deployment.
It is therefore more commonly used with of base pipe. This test proved that such
water-based mud, which exhibit higher thick pipe and connections could be suc- Two situations were identified when
filtration values. The high temperatures cessfully expanded. The expanded pipe the contingent architecture would be
experienced on Elgin/Franklin dictate was then cut into sections and pressure- deployed prior to entering the reservoir:
the use of oil-based mud. As filtration of tested to burst, collapse and tension con- • If high-pressure gas-bearing limestone
oil-based mud is very tight, the filtration ditions. The minimum collapse pressure layers were encountered in the cap
from the fracture faces into the formation was 366 bar. So the operator confidently rock. This would require a high mud
is virtually nil. The consequence is that considered the system capable of sus- weight to be controlled safely during
the plug at the fracture mouth needs to taining 345 bar collapse pressure. a trip, and therefore the probability of
be tightly sealing as soon as it is created. success of the borehole-strengthening
Although expandable liner has been run
The other difficulty is to define the width previously in high-temperature wells, the method would be lowered to an unac-
of the fracture to seal. Rock mechan- operator thought it prudent to test the ceptable value.
ics calculations show that there is a expansion system with high mud weight • If the defined mud weight was found
direct relationship between geometry of and high temperatures. This was done too low to manage borehole instability
the fracture, width and length, and the in a shallow well in a special facility in in the cap rock, necessitating again an
amount of overpressure. The higher the Dallas, Texas. The system was left soak- increase in the mud weight and com-
pressure, the wider the fracture, at a ing with 2.15 sg oil-based mud at 176°C promise the borehole-strengthening
given length. For a given overpressure, for 18 hr before initiating expansion and technique success.
the equation has two unknowns, so one expanding 18 m of pipe. Examination of
has to fix a parameter. In our case, it was the seals and parts of the system after- Mud weight definition
estimated that the mud could be designed wards showed no significant degrada-
to form an efficient plug of 1-mm width, tion. The system was declared qualified The mud weight necessary to implement
while keeping reasonable rheological for the application. the primary architecture had to be a com-
properties despite a high solid content. promise: Using a low mud weight maxi-
It was decided to not cement the expand- mizes the chances for a successful bore-
The mud was therefore designed and able liner on deployment in the well. The hole strengthening, but it increases the
tested to be able to seal a 1-mm gap. The volumes of cement involved were too chances of borehole instabilities in the cap
LCM additives consist of sized grounded small to guarantee good-quality cement rock. Although instabilities can be man-
marble and sized graphitic material. at 5,000 m depth. Any problem encoun- aged to a certain level, there is a thresh-
The graphitic material comprises some tered during the expansion process old from which they cannot be managed
very coarse sections. Laboratory testing would have left the cement setting and without raising the mud weight. Using
took place to adjust LCM additives rela- prevented the expansion process to take high mud weight reverses the problems.
tive concentrations, to achieve a quick place. Instead, some joints of the liner
and efficient plugging of 1-mm slots. As were bonded with elastomer. Some were Given the uncertainties on the rock
well as these in house tests, tests were planned to be installed in the open hole mechanic properties in the cap rock and
performed in a third-party laboratory. to seal against the formation. Another in the reservoir, a probabilistic approach

D r i l l i n g contractor July/August 2008 45


European Drilling

was taken to define a theoretical opti- practice to deal with losses is to pump If losses happened, the first thing we
mum mud weight. For each mud weight, LCM pills with increasing concentration wanted to achieve was to pull back the
a probability of success of the borehole- of LCM material, and if that’s not suc- BHA into the previous shoe, set approxi-
strengthening technique was defined, cessful, keep the hole filled with mud and mately 300 m above, in order to remove
as well as a probability of managing the then revert to a lighter fluid, firstly base it from the cap rock formation most
borehole instability. The two curves were oil then water, when available volume of susceptible to collapsing under loss of
plotted on the same graph (Figure 7). The mud has been used. hydrostatic. The level in the well would
mud weight value at which they cross is be allowed to drop. The potential small
the optimum mud weight. In our case, a This was not applicable in this case: gas ingress from the limestone layers in
1.86 sg mud was deemed optimum, yet the mud is already largely charged with the wellbore would be kept at bottom by
the minimum mud weight the cap rock LCM material; therefore chances of pumping mud at a low rate of 100 l/min.
had been drilled so far was 2.15 sg. success with LCM pills would be low.
Additionally, the potential for collapsing As soon as the BHA is safely pulled
Drilled in 6 5/
8-in. liner of cap rock around the BHA (bottomhole to shoe, the level in the well would be
assembly), as well as the potential for assessed by the use of an echo meter.
The liner drilling technique was becom- small gas layers to flow into the bore- This would allow the definition of the
ing available at the time development hole, under a decrease of the hydrostatic mud weight required to control losses.
work was ongoing. This technique column, were to be considered. The well would then be displaced to the
presented two main advantages. First, required mud weight, and a cement plug
there is no need to trip out of hole to The expected rate of losses also set at bottom to abandon the bottom of
run the liner, leaving the cap rock in an had to be taken into consideration: the hole and revert to the contingent
underbalance condition for a long time. Geomechanical calculations indicated architecture. This was the ideal case.
On these wells, it is typically four days that, given the amount of expected over-
balance, any fracture opening would However, so much uncertainty was lying in
between when the bit is picked off bot-
propagate so quickly that very little time the expected pressures and well behaviour
tom and when the liner arrives at bot-
would be allowed to prepare a pill. that all cases had to be considered care-
tom, applying HPHT procedures.
fully and a way of regaining full control of
Second, it allows using a higher mud Keeping the well full with lighter fluid, the well found for each permutation.
weight during drilling. If heavy losses typically water, once all available mud The benefits of the plan were explained
were experienced when entering the res- had been pumped into the well, would to the offshore crew, who then agreed
ervoir, and the hydrostatic applied on the have resulted with a mixture of incom- to the proposed losses response plan.
cap rock dropped, the formation may col- patible fluids in the wellbore. This would The fact that the top well architecture
lapse. With a drilled-in liner, it would col- have created more difficulties in regain- was able to sustain a well full of gas
lapse around the liner, leaving the hole ing control of the well. increased their confidence in applying it.
cased off. Isolation behind the liner might In our well, the chance of important gas As will be developed in the following sec-
be already achieved by the collapsed for- ingress following losses was considered tions, this losses response plan did not
mation. In case further isolation is need- low. In the reservoir itself, the fracture need to be applied. However, it had to be
ed, an integral liner top packer would propagation pressure was higher than revisited several times to incorporate the
seal off the top of the liner, and the shoe the pore pressure. Above it, the only new information acquired while drilling
could be tacked by a cement squeeze. source of gas ingress was the potential and to adapt it to each drilling situation.
Losses response plan small carbonate layers. They would bleed
gas into the wellbore rather than gener- Actual Drilling
The main risk associated with the prima- ate a genuine kick. Therefore, the usual
ry architecture was encountering total requirement of keeping the well full at Herring anomaly
losses when penetrating the reservoir any price was challenged very strongly. Top sections were drilled as planned.
with a high overbalance. The common The 13 3/8-in. casing was called 100 m
8069 Total: Depleted Well Testing; Test 1; Pressure Response 8069 Total: Depleted Well Testing; Test 3; Pressure Response
Temperature: 150 o C; Fracture Profile: 1mm - 0.2mm; Injection Pressure: 160 bar Temperature: 150°C; Fracture Profile: 1mm Parallel; Injection Pressure: 140 bar

180 0.50 200

0.45 180
160

0.40 160
140

0.35 140
120
0.30 120
Injection Pressure (bar)

100
Pressure (bar)

Pressure (bar)

0.25 100
80
0.20 80

60
0.15 60

40
0.10 40

20 0.05 20

0 0.00 0
0 100 200 300 400 500 600 700 800 900 1000 0 1000 2000 3000 4000 5000 6000 7000 8000
Time (seconds) Time (seconds)

Injection Pressure P1 P2 P3 P4 P5 P1 P2 P3 P4 P5 Injection Pressure

Figure 6: Different mud formulations used for sealing a 1-mm gap. On the left, a plug forms but breaks out. On the right, the plug forms
and does not transmit any pressure past it.

46 July/August 2008 D r i l l i n g contractor


European Drilling

expandable liner. No specially designed


additives were added at that time as
there was no intention to penetrate the
reservoir with this type of mud weight.

When reaching the Plenus Marl forma-


tion at 5,111 m, some losses occurred at
an equivalent mud weight of 2.16 sg. To
take into account equivalent circulating
density (ECD), the mud weight had to be
decreased to 2.08 sg. On previous wells,
this formation was drilled in the 12 ¼-in.
phase with lower mud weights.

The originally planned depth of the pro-


Figure 7: Probability of success of the borehole-strengthening technique in the reservoir duction casing was reached, and drilling
and of the borehole instability management in the cap rock function of the mud weight. continued into the cap rock. Further
The optimum mud weight is at the crossing point of the two curves. down, in the Valhall formation at 5,241
m, some high gas were seen again, indi-
short at 3,585 m. This resulted in a LOT at this depth usually increased tenfold cating the presence of a charged lime-
(leak off test) value of 1.84 sg EMW from 0.3% to 3%, before returning to a stone layer, but drilling could continue
instead of a planned 2.10 sg EMW. These background level of 0.3%. without raising the mud weight.
types of lower values had already been
experienced on Elgin/Franklin without At this date, there is no firm conclusion When reaching phase TD, however, the
creating problems, so drilling continued on the presence of this flowing layer flow checks indicated that the well was
as planned into the 12 ¼-in. phase with there, but a strong suspicion exists that it not balanced, and the mud weight had to
the planned 1.60 sg mud weight. is linked to the depletion of the reservoir. be raised to 2.10 sg to control the Valhall
gas, and 2.12 sg to give a reasonable
As drilling was progressing in the Herring Eventually, after considering all possibili- swab margin for pulling out. The section
formation, 150 m before planned phase ties to continue the drilling of this well, required therefore a very tight mud-
TD and 450 m above top reservoir, the gas the hole was side-tracked above the aban- weight window.
level suddenly increased. The drilling was donment cement plugs. The new hole was
stopped, and the flow checks performed stopped 50 m above the anomaly depth, Prediction enhancement
indicated a constant flow of 500 l/hr. When and the production casing was run and
shutting the BOP, the casing pressure was successfully cemented at 4,939 m. In order to place the expandable liner
rising only very slowly, and no stabiliza- shoe as close as possible to the reservoir
tion of the pressure could be achieved in The main consequence of this event was without risking penetrating it with such
a reasonable time. The encountered layer that this Herring high-pressure layer was high mud weight, chemo-stratigraphic
was highly pressurized, but with very now to be crossed in the 8 ½-in. section. and bio-stratigraphic correlations were
low permeability. Further, numerous flow Its required mud weight, confirmed when performed. Although it seems a promising
checks were performed in an attempt to crossing it again to be 2.05 sg minimum, technique, the accuracy was reduced by
depressurize it, but proved unsuccessful was considered too high to implement the lower sampling intervals in the refer-
as the flow remained constant. the borehole-strengthening technique. ence wells. It did not succeed in improv-
Therefore, the primary architecture was ing the placement of the expandable liner
An incremental rise in mud weight to 1.8 and establishing the greater thickness of
ruled out from the start of the 8 ½-in.
sg slightly decreased it. Analysis of the the reservoir overlaying Heather interval
flow trend function of the mud weight section. A decision was made to imple-
ment the contingent architecture. on this well. This phase TD was called
indicated a 2.05 sg EMW formation at 5,393 m eventually, and proved after-
pressure. As the BHA included a MWD wards to be 58 m above the reservoir.
Tight mud weight window
tool and a mud motor, spotting cement
in the 8 ½-in. x 8 ¾-in. drilling section
through the BHA was considered too Running expandable liner
risky. After 20 days of investigations, As the expanded outside diameter of the
the bottomhole hydrostatic was eventu- liner, including the connections protec- Prior to running the liner, a caliper was
ally raised to 1.98 sg EMW by filling the tion sleeve, was 8.55-in., the hole had to run in the open hole to estimate the best
open hole with heavy mud at 2.4 sg while be opened from 8 ½ in. to 8 ¾ in. This placement for the elastomer-bonded
the mud inside the casing remained at was achieved by inserting a hole opener pipes. The hole proved to be mostly in
1.75 sg. The ingress flow, although not with PDC cutting structure within the gauge. An imaging tool was incorporated
stopped, decreased enough to pull back drilling BHA. in the logging suite to try to establish the
the BHA to surface and run a stinger to reason for the Herring anomaly. Nothing
After confirming that the minimum mud noticeable could be seen at the Herring
set a cement plug at bottom and regain
weight to control the Herring anomaly anomaly, but a fracture could be clearly
full control of the well.
was 2.05 sg, the mud weight was further seen at the Plenus Marl interval where
It was the first time out of 21 wells increased to 2.15 sg. This was the origi- losses were experienced.
drilled in the Elgin/Franklin area that nal mud weight used in previous wells
this formation was found with such a and was supposed to ensure a gauged The liner was run with four joints with
high-pressure, flowing gas. It had usually hole in the cap rock, to allow proper elastomer bonding. One joint was located
been drilled with a 1.6 sg mud. Gas levels sealing of the elastomer around the close to the shoe, two were straddling

48 July/August 2008 D r i l l i n g contractor


European Drilling

FIA Predicted Pressure (bar)


Drilling with liner

350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200 Once the expandable shoe was cleared,
-50 and the stability of the well assessed, the
6 5/8-in. drilled in liner was run. The well
0 was displaced to the specially designed
Top C mud loaded with LCM originally designed
50
for the borehole-strengthening technique.

Case uniform F3
The running string was spaced out so
Top Up B
100 Case uniform F6 that continuous drilling could be achieved
FIA Case uniform (average B) on a full 28-m stand, hoping to penetrate
Depth below top fulmar TVDss

150 FIA Kv/Kh dow ngraded in C sand the reservoir in this interval. The idea
FIA B/C Multi-layer behaviour Top Lw B was to keep a high ECD while drilling,
FIA Tigth top C
200 therefore keep the open hole high-
Initial
FIA Base case
pressure shale open. A connection would
Top A
250 Measure FMT make the downhole pressure decrease to
Average BHSIP derived from WHSIP equivalent static density and increase the
chances of borehole collapsing.
300
As seen above, the reservoir was deeper,
Top Up Pent
350 so a connection had to be performed. The
hole remained stable when circulation
400 was stopped to connect the next stand
and drilling could resume. The cutting
450 Top Lw Pent
structure of the shoe was damaged on a
hard limestone stringer before encoun-
tering the reservoir, and drilling stopped.
500
The decision was made to pull out to
Figure 8: Comparison of actual pressures versus planned pressures within the reser- change the cutting structure. As some
voir. In thick red are the actual pressures. The red dot in the C sands is the pressure cutters were left in the hole, a clean-out
measurement taken at 1004 bar just below the shoe of the drilled-in liner. run was undertaken with a bit and a
junk basket. Then the drilled in liner was
the Valhall high gas layer, and one was launcher element. Once initiated, the run again.
installed at the top to seal against the expansion process went smoothly, and During all these operations, the hole
existing casing. There were lengthy dis- the liner was installed as planned. remained perfectly in gauge without
cussions on the thickness of the elasto- any fill found at bottom. This was a
mer. They needed to be thick enough so Injectivity test at expandable liner
surprise as rock mechanic calculations
to ensure sealing against the formation shoe
had accounted for manageable borehole
in the open hole, but thin enough to mini- Prior to continuing to drill, the well was instabilities with this mud weight in the
mize the piston effect when run inside displaced to the planned 1.86 sg mud high-pressure cap rock.
the casing and to ensure that they would weight. It was checked that the hanger
not prevent the expansion process. The liner drilled the remaining of the
joint was sealing properly, then the shoe cap rock and penetrated the reservoir
was drilled with a special drill bit. As at 5,451 m. No more than 500 l of losses
A consensus was reached with 0.19-in.
soon as the shoe was drilled, an influx were noticed when penetrating the res-
(4.8-mm) thickness. The specially bonded
was recorded from the well. Multiple ervoir. These very low levels of losses
joints had to be flown from the US to pro-
flow checks and circulations showed a lead to questioning the top reservoir
vide the required elastomer thickness.
decrease in the flowing trend. At some depletion. Drilling was continued until
The liner reached TD without problem. stage, it was believed that the elastomer 5,484 m, where the liner hanger was
The dart was dropped, but the circulat- around the liner was not properly isolat- about to hang on top of the expandable
ing rate was limited to 300 l/min to mini- ing the Valhall formation. liner. The liner was then cemented.
mize ECD on bottom and prevent losses At the end of the cement job, the liner
In provision of a cement squeeze at the
in the Plenus Marls fracture. With this top packer could not be energized. When
shoe, an injectivity test was performed,
low flow rate, the dart was not displaced the running tool was pulled to surface,
which gave an injection pressure of 2.17
properly and stopped half-way down the it was found that the packer energizing
sg EMW. This value was a surprise, as
string. Pumping was stopped after theo- dogs had been prevented to expand by
the formation had always been drilled
retical displacement volume plus some jammed LCM material from the designer
with a 2.23 sg ECD on the non-depleted
margin. After investigation, including mud. The debris barrier, plugged by
wells. Further flow checks and cir-
wireline work to locate the dart in the the same material, had collapsed and
culations were performed with still a
string at 600 m, a decision was made to failed under the increase of pressure
decreasing trend, the last one being per-
displace the dart at 600 l/min. This flow downhole. A separate run had to be per-
fectly stable. This showed that the seal
rate achieved dart displacement to bot- formed to run a back-up liner top packer.
was effectively achieved. It is believed
tom, but with only 5% mud returns.
that the influx – experienced after drill- Reservoir drilling
The expansion process was initiated at ing the shoe – was created by the mud,
Once achieved, the successful isolation
a much higher pressure than expected, which had been squeezed when displac-
of the transition between cap rock and
close to the burst pressure of the cone ing the dart.
reservoir, one could believe that the mud

50 July/August 2008 D r i l l i n g contractor


European Drilling

weight could be decreased to drill the could not create enough drawdown rela- • Despite efforts to reduce geological
remaining of the reservoir with a mini- tive to the hydrostatic pressure of the and reservoir uncertainties, surprises
mum overbalance. mud to give actual formation pressure. were found – the biggest in the over-
The indication gained was only that the burden, long before reaching the res-
Mud weight was decreased down to 1.5
pressure was lower than 1.42 sg EMW. ervoir. Most are believed to be a conse-
sg prior to drilling the shoe with a special
PDC bit. High levels of gas were experi- A wiper trip was performed with a quence of the reservoir depletion.
enced as soon as the shoe was drilled. formation evaluation tool in the string. • High permeability sands up to 100 mil-
Mud weight was raised to 1.60 sg, and There was no blockage of the tool by the lidarcy were drilled with 600 bar over-
drilling continued on 40 m, in the believed LCM within the designer mud. balance without any significant losses.
poor productivity C sands, still with high
Final 4 ½-in. liner was then run. It hung
gas levels. These high gas levels could • The formation damage created by the
up 40 m above TD. It was decided to
have come from the cap rock via a leak designer mud, if any, was bypassed by
cement it in place and drill out inside
path through a deficient cement sheet of the perforations.
cement afterwards to give access to the
the liner, or from a higher-than-expected
lowest planned perforation intervals. Aknowledgements: The Elgin / Franklin
pressure in the drilled reservoir section.
project is a development operated by Elf
Completion and perforation
Drilling stopped, and wireline logging Exploration UK PLC on behalf of itself and
was performed, including pressure mea- For completion, the well was displaced its co-venturers, whose support is acknowl-
edged: Elf Exploration UK PLC (operator);
surements. The well was displaced back to water and checked for integrity. The
E.F. Oil and Gas Ltd; Eni Elgin/Franklin Ltd;
to 1.86 sg designer mud to allow a safe completion was installed without notice- BG International (CNS) Ltd; E.ON Ruhrgas
trip out of hole. able problem. Perforation was started on UK Exploration & Production Ltdl; Esso
wireline. Because the formation pressure Exploration and Production UK Ltd; Chevrom
A resistivity/gamma ray log was then
was not yet ascertained, pressure was North Sea Ltd; Dyas UK Ltd; Oranje-Nassau
run. These logs showed the presence (UK) Ltd.
applied at surface to make sure the perfo-
of good sands at the top of the reser-
ration would not take place largely under- The authors want to thank the TOTAL man-
voir, covered partially by the drilled-in
balance. There were problems during agement who supported this publication, and.
liner. A pressure measurement logging The authors want to thank M. Gregoire, S.
perforations operations, including misfire,
tool indicated a pressure in this layer Robertson, A. Humphreys, V. Neillo, C. Tindle,
stuck guns and coiled tubing fishing. The
of 1,004 bar, which was an equivalent C. Onu, G. Holm, Total Exploration UK Ltd,
last part of the perforation was performed A. Onaisi, TOTAL, for their important contri-
mud weight of 1.92 sg. Nevertheless, the
on coiled tubing. The Top C layer perfo- bution to this project. The authors want to
Geoscience Department remained con-
ration was aborted for fear of potential thank the offshore team that contributed to
vinced that the best reservoir sands still
problems generated by the high-pressure the successful drilling of this well. This would
to come were heavily depleted. not have been achieved without their strong
difference between this layer and already-
involvement and commitment.
The situation was as follows: All tech- perforated low-pressure sands.
niques planned to isolate the high-pres- References
Clean-up, bottom pressure
sure formations from the low-pressure Aston, M.S., Alberty, M.W., McLean, M.R., de
ones had been used, and still the open The well was lifted with coiled tubing by Jong, H.J. and Armagost, K., BP explora-
hole was showing high pressure. The pumping nitrogen and cleaned up. The tion. 2004. Drilling Fluids for Wellbore
only remaining option was to drill to wellhead shut-in pressure by the end Strengthening. SPE 87130
final depth with the designer mud. The of the clean-up indicated a bottomhole Alberty, M.W., McLean, M.R., BP exporation.
losses response plan was updated, and shut-in pressure of 440 bar: 0.82 sg 2004. A physical model for stress cages. SPE
drilling continued at a reduced penetra- EMW. This indicated that the best sands 90493
tion rate into the remaining C sands, the had been drilled with 600 bar (8,700 psi) Demong, K., Halliburton Energy Services,
B sands and 55 m into the A sands. The overbalance. Figure 8 illustrates the Rivenbark, M., Enventure Global Technology
plan was to stay away from the virgin comparison between pressure prediction and Mason, D., Shell Technology ventures.
2004. Breakthroughs using Solid Expandable
pressure pentland sands. and actual pressure at the time drilling Tubulars to Construct Extended Reach Wells.
the reservoir was performed. SPE 87209
TD was reached at 5,678 m with only a
seepage losses rate noticed around 200 Moreover, the indications were that the Dupriest, F. E., ExxonMobil. 2005. Fracture
l/hr for a small period. ECD during this well was delivering its expected potential Closure Stress (FCS) and Lost returns
drilling was computed at around 1.93 sg, and that the formation damage created Practices. SPE 92192
with peaks up to 2.0 sg EMW. It is dif- by the designer mud, even under this Hemphill, T., Halliburton Baroid. 2005.
ficult to ascertain which of the following large overbalance, was either insignifi- Integrated management of the safe operating
happened: cant or largely bypassed by the perfora- window: Wellbore stability is more than just
fluid density. SPE 94732
• The borehole was fractured, and the tion tunnels. Since then, the well has
been delivering 17,000 bbl/day. Marchina, P., SPE, and Onaisi, A., SPE,
borehole-strengthening technique Total. 2004. Reservoir-geomechanics Coupled
worked. Simulations: a Powerful Tool for Well Design
Conclusions and operations in an HPHT Environment.
• The designer mud increased the frac- SPE 92546
ture initiation pressure by creating a • An infill well was successfully drilled,
perfect seal between the borehole and completed and perforated in an HPHT Sinor, L.A., Hughes Christensen Co., Tybero,
reservoir after depletion of 660 bar P., and Eide, O., Amoco Norway Oil Co, and
the formation. Wenande, B.C., Consultant. 1998. Rotary Liner
had occurred.
Drilling for depleted Reservoirs. SPE 39399.
• The mud column pressure was below
the initial fracture initiation pressure. • Two architectures were designed to This article is based on IADC/SPE 112708,
achieve this goal, providing a fallback “Successful Development Drilling of an HP/
Wireline logging was performed, which HT Infill Well in a Highly Depleted Reservoir:
solution for any geological or reservoir
included pressure measurement points. Case Study,” 2008 IADC/SPE Drilling
surprises encountered. Conference, held in Orlando, Fla., 4-6 March.
However, the pressure measurement tool

D r i l l i n g contractor July/August 2008 51

You might also like